CARLOCK WS PATCHING 2020-1
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Beniach Construction Co., Inc. Low bidder | $135,953 | ||
| 2 | Otto Baum Company, Inc. | $148,884 | +9.5% | |
| 3 | Kinney Contractors, Inc. | $152,766 | +12.4% | |
| 4 | Stark Excavating, Inc. | $163,526 | +20.3% | |
| 5 | G. M. Sipes Construction, Inc. | $175,720 | +29.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Beniach Constru… | #2 Otto Baum Compa… | #3 Kinney Contract… | #4 Stark Excavatin… | #5 G. M. Sipes Con… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 42000060 | WELDED WIRE REINF | 586 | SQ YD | $12.87 | $11.11 | $12.00 | $15.05 | $10.00 | |
| 2 | 44201007 | CL B PATCH T2 13 | 109 | SQ YD | $150.20 | $149.14 | $160.00 | $184.20 | $250.00 | |
| 3 | 44201011 | CL B PATCH T3 13 | 89 | SQ YD | $146.03 | $137.00 | $157.00 | $177.60 | $250.00 | |
| 4 | 44201013 | CL B PATCH T4 13 | 497 | SQ YD | $138.51 | $137.00 | $154.00 | $162.00 | $200.00 | |
| 5 | 44201299 | DOWEL BARS 1 1/2 | 866 | EACH | $12.33 | $16.27 | $18.00 | $17.60 | $7.50 | |
| 6 | 44213200 | SAW CUTS | 1,983 | FOOT | $0.0100 | $5.74 | $3.00 | $4.95 | $0.0100 | |
| 7 | 44213204 | TIE BARS 3/4 | 89 | EACH | $7.62 | $11.98 | $14.00 | $13.50 | $5.00 | |
| 8 | 67100100 | MOBILIZATION | 1 | L SUM | $7,000.00 | $7,900.00 | $9,000.00 | $8,300.00 | $7,000.00 | |
| 9 | 70100820 | TRAF CONT-PROT 701451 | 1 | L SUM | $11,827.00 | $11,396.54 | $6,000.00 | $3,750.00 | $7,000.00 |