D5 CM PATCH 2020-1
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Lion Construction 1, LLC Low bidder | $321,387 | ||
| 2 | G. M. Sipes Construction, Inc. | $326,800 | +1.7% | |
| 3 | H. J. Eppel & Co. | $411,800 | +28.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Lion Constructi… | #2 G. M. Sipes Con… | #3 H. J. Eppel & C… |
|---|---|---|---|---|---|---|---|---|
| 1 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $15,556.00 | $21,000.00 | $87,000.00 | |
| 2 | 44201777 | CL D PATCH T2 11 | 160 | SQ YD | $211.50 | $205.00 | $240.00 | |
| 3 | 44201815 | CL D PATCH T2 14 | 1,000 | SQ YD | $211.50 | $215.00 | $236.00 | |
| 4 | 44201819 | CL D PATCH T3 14 | 80 | SQ YD | $211.50 | $215.00 | $227.00 | |
| 5 | 44201821 | CL D PATCH T4 14 | 120 | SQ YD | $211.50 | $215.00 | $227.00 | |
| 6 | 67100100 | MOBILIZATION | 1 | L SUM | $18,191.00 | $15,000.00 | $5,000.00 |