121 BDR
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Sangamo Construction Company Low bidder | $1,348,258 | ||
| 2 | White Construction LLC | $1,549,931 | +15.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Sangamo Constru… | #2 White Construct… |
|---|---|---|---|---|---|---|---|
| 1 | X4401198 | HMA SURF REM VAR DP | 1,659 | SQ YD | $7.73 | $5.50 | |
| 2 | X5030250 | BR DECK GROOVING LONG | 1,324 | SQ YD | $9.55 | $22.00 | |
| 3 | X6330725 | SPBGR (SHORT RADIUS) | 25 | FOOT | $31.76 | $39.75 | |
| 4 | X7200201 | WIDTH RESTRICT SIGN | 1 | L SUM | $3,267.44 | $2,100.00 | |
| 5 | Z0006016 | BR DK LTX C OLY 2 3/4 | 1,755 | SQ YD | $187.39 | $180.00 | |
| 6 | Z0012130 | BR DECK SCAR 3/4 | 1,781 | SQ YD | $42.50 | $57.00 | |
| 7 | Z0012754 | STR REP CON DP = < 5 | 64 | SQ FT | $188.78 | $180.00 | |
| 8 | Z0016002 | DECK SLAB REP (FD-T2) | 7.2 | SQ YD | $2,051.13 | $2,350.00 | |
| 9 | Z0029090 | DIAMOND GRIND BR SEC | 1,484 | SQ YD | $15.03 | $33.00 | |
| 10 | 20200100 | EARTH EXCAVATION | 105 | CU YD | $48.91 | $120.00 | |
| 11 | 40600290 | BIT MATLS TACK CT | 1,620 | POUND | $2.65 | $2.50 | |
| 12 | 40604050 | HMA SC IL-9.5 C N50 | 340 | TON | $254.07 | $240.00 | |
| 13 | 44000156 | HMA SURF REM 1 3/4 | 1,057 | SQ YD | $15.94 | $9.50 | |
| 14 | 48203100 | HMA SHOULDERS | 164 | TON | $316.69 | $265.00 | |
| 15 | 50102400 | CONC REM | 1.5 | CU YD | $3,679.63 | $3,750.00 | |
| 16 | 50104000 | BRIDGE RAIL REMOVAL | 160 | FOOT | $14.55 | $12.00 | |
| 17 | 50300100 | FLOOR DRAINS | 12 | EACH | $337.15 | $600.00 | |
| 18 | 50300255 | CONC SUP-STR | 7.2 | CU YD | $2,648.89 | $2,300.00 | |
| 19 | 50300300 | PROTECTIVE COAT | 1,812 | SQ YD | $2.82 | $5.50 | |
| 20 | 50800205 | REINF BARS, EPOXY CTD | 830 | POUND | $10.24 | $4.00 | |
| 21 | 50900200 | STEEL RAIL TYPE 2399 | 159 | FOOT | $232.90 | $257.00 | |
| 22 | 63000001 | SPBGR TY A 6FT POSTS | 987.5 | FOOT | $23.29 | $31.00 | |
| 23 | 63100045 | TRAF BAR TERM T2 | 2 | EACH | $1,482.11 | $1,420.00 | |
| 24 | 63100085 | TRAF BAR TERM T6 | 12 | EACH | $3,175.94 | $3,850.00 | |
| 25 | 63100087 | TRAF BAR TERM T6A | 12 | EACH | $3,705.26 | $4,250.00 | |
| 26 | 63100167 | TR BAR TRM T1 SPL TAN | 22 | EACH | $2,858.34 | $3,375.00 | |
| 27 | 63200310 | GUARDRAIL REMOV | 3,427.5 | FOOT | $4.99 | $7.55 | |
| 28 | 67000500 | ENGR FIELD OFFICE B | 6 | CAL MO | $1,999.32 | $2,500.00 | |
| 29 | 67100100 | MOBILIZATION | 1 | L SUM | $80,760.63 | $95,000.00 | |
| 30 | 70100405 | TRAF CONT-PROT 701321 | 6 | EACH | $12,898.97 | $25,000.00 | |
| 31 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $14,139.76 | $30,000.00 | |
| 32 | 70106500 | TEMP BR TRAF SIGNALS | 6 | EACH | $15,648.37 | $15,000.00 | |
| 33 | 70400100 | TEMP CONC BARRIER | 2,000 | FOOT | $26.14 | $30.00 | |
| 34 | 70400200 | REL TEMP CONC BARRIER | 1,962.5 | FOOT | $6.99 | $22.00 | |
| 35 | 70600250 | IMP ATTN TEMP NRD TL3 | 12 | EACH | $6,170.79 | $3,600.00 | |
| 36 | 70600350 | IMP ATTN REL NRD TL3 | 12 | EACH | $913.97 | $1,500.00 | |
| 37 | 72501000 | TERMINAL MARKER - DA | 22 | EACH | $31.76 | $42.00 | |
| 38 | 78200005 | GRDRAIL REF TYPE A | 46 | EACH | $8.47 | $10.25 |