32RS-10
Bidders 1
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Gunther Construction, a div of UCM, Inc. Low bidder | $4,415,604 |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Gunther Constru… |
|---|---|---|---|---|---|---|
| 1 | XZ013798 | CONSTR STA LAYOUT | 1 | L SUM | $12,208.95 | |
| 2 | X4400196 | HMA SURF REM SPL | 1,025 | SQ YD | $119.34 | |
| 3 | X4402020 | CONC MEDIAN SURF REM | 76 | SQ FT | $13.75 | |
| 4 | X4421000 | PARTIAL DEPTH PATCH | 297 | TON | $834.68 | |
| 5 | X4421002 | PART DEPTH PATCH SPL | 2,646 | SQ YD | $77.59 | |
| 6 | X6024503 | INLET ADJ NEW F&G SPL | 1 | EACH | $2,750.00 | |
| 7 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $36,215.39 | |
| 8 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | |
| 9 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | |
| 10 | 40600295 | P BIT MATLS TACK CT | 72,442 | POUND | $0.9500 | |
| 11 | 40600405 | MATL TRANSFER DEVICE | 10,425 | TON | $10.06 | |
| 12 | 40600982 | HMA SURF REM BUTT JT | 1,480 | SQ YD | $62.88 | |
| 13 | 40600990 | TEMPORARY RAMP | 1,850 | SQ YD | $22.13 | |
| 14 | 40602978 | HMA BC IL-9.5 N50 | 3,545 | TON | $234.78 | |
| 15 | 40604162 | P HMA SC IL-9.5 D N70 | 4,166 | TON | $223.70 | |
| 16 | 40800050 | INCIDENTAL HMA SURF | 294 | TON | $375.05 | |
| 17 | 44000157 | HMA SURF REM 2 | 1,616 | SQ YD | $9.22 | |
| 18 | 44000164 | HMA SURF REM 3 3/4 | 48,562 | SQ YD | $9.22 | |
| 19 | 44000500 | COMB CURB GUTTER REM | 24 | FOOT | $99.00 | |
| 20 | 48102100 | AGG WEDGE SHLD TYPE B | 3 | TON | $512.80 | |
| 21 | 48203100 | HMA SHOULDERS | 2,715 | TON | $236.43 | |
| 22 | 60605000 | COMB CC&G TY B-6.24 | 24 | FOOT | $220.00 | |
| 23 | 60618300 | CONC MEDIAN SURF 4 | 76 | SQ FT | $27.50 | |
| 24 | 64200116 | SHOULDER RUM STRIP 16 | 14,290 | FOOT | $1.63 | |
| 25 | 67000400 | ENGR FIELD OFFICE A | 5 | CAL MO | $5,349.21 | |
| 26 | 67100100 | MOBILIZATION | 1 | L SUM | $187,561.31 | |
| 27 | 70100310 | TRAF CONT-PROT 701421 | 1 | L SUM | $51,489.25 | |
| 28 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $3,516.65 | |
| 29 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $22,022.40 | |
| 30 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $32,827.38 | |
| 31 | 70103815 | TR CONT SURVEILLANCE | 10 | CAL DA | $2,225.69 | |
| 32 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $121.00 | |
| 33 | 70300100 | SHORT TERM PAVT MKING | 8,242 | FOOT | $1.11 | |
| 34 | 70300150 | SHRT TRM PAVT MK REM | 569 | SQ FT | $14.03 | |
| 35 | 70300211 | TEMP PVT MK LTR & SYM PAINT | 187 | SQ FT | $0.0100 | |
| 36 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 12,603 | FOOT | $0.0100 | |
| 37 | 70300241 | TEMP PVT MK LINE 6 - PAINT | 16,417 | FOOT | $0.0100 | |
| 38 | 70300251 | TEMP PVT MK LINE 8 - PAINT | 448 | FOOT | $0.0100 | |
| 39 | 70300261 | TEMP PVT MK LINE 12 - PAINT | 205 | FOOT | $0.0100 | |
| 40 | 78009000 | MOD URETH PM LTR-SYM | 314 | SQ FT | $4.95 | |
| 41 | 78009004 | MOD URETH PM LINE 4 | 12,659 | FOOT | $0.9500 | |
| 42 | 78009006 | MOD URETH PM LINE 6 | 16,447 | FOOT | $1.42 | |
| 43 | 78009008 | MOD URETH PM LINE 8 | 495 | FOOT | $1.89 | |
| 44 | 78009012 | MOD URETH PM LINE 12 | 205 | FOOT | $2.84 | |
| 45 | 78009024 | MOD URETH PM LINE 24 | 66 | FOOT | $5.78 | |
| 46 | 78011000 | GRV RCSD PM LTR & SYM | 431 | SQ FT | $4.79 | |
| 47 | 78011025 | GRV RCSD PVT MRKG 5 | 12,044 | FOOT | $0.5000 | |
| 48 | 78011035 | GRV RCSD PVT MRKG 7 | 15,679 | FOOT | $0.7400 | |
| 49 | 78011045 | GRV RCSD PVT MRKG 9 | 495 | FOOT | $0.9900 | |
| 50 | 78011065 | GRV RCSD PVT MRKG 13 | 205 | FOOT | $2.75 | |
| 51 | 78011125 | GRV RCSD PVT MRKG 25 | 66 | FOOT | $6.05 | |
| 52 | 78100100 | RAISED REFL PAVT MKR | 223 | EACH | $42.35 | |
| 53 | 78300200 | RAISED REF PVT MK REM | 200 | EACH | $38.01 | |
| 54 | 78300202 | PVT MKG REM WTR BLAST | 589 | SQ FT | $11.00 |