D3 HWY DAMAGE REPAIR FY 25
- Let date
- Friday, August 2, 2024
- Contract
- 66P31 · job page
- District
- District 3
- County
- Various
- Highway
- Limits
- One year contract to repair damaged High Tension Cable Median Barrier, Guardrail, Attenuators, etc., caused by motorists along various routes in District 3. Funded by MCHD funds, Contract Maintenance funds, and Maintenance of HTC Median Barrier funds.
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Northern Contracting, Inc. Low bidder | $1,803,903 | ||
| 2 | COLLINS & HERMANN, INC. | $1,999,471 | +10.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Northern Contra… | #2 COLLINS & HERMA… |
|---|---|---|---|---|---|---|---|
| 1 | X0322878 | TIMBER CURB | 10 | FOOT | $57.15 | $5.56 | |
| 2 | X0326126 | WOOD TERMINAL POST | 10 | EACH | $400.00 | $56.33 | |
| 3 | X6300215 | RAIL ELEMENT PLATES | 325 | EACH | $381.00 | $258.52 | |
| 4 | X6300230 | STEEL POSTS | 175 | EACH | $162.00 | $70.07 | |
| 5 | X6310301 | REP TRAF B TERM T1 SP | 20 | EACH | $2,411.00 | $2,827.29 | |
| 6 | X6331101 | TUBULAR THRIE BEAM | 25 | FOOT | $10.00 | $66.22 | |
| 7 | X6331105 | STEEL POSTS MODIFIED | 2 | EACH | $266.00 | $388.85 | |
| 8 | X6331110 | STEEL POSTS SPECIAL | 53 | EACH | $135.00 | $82.99 | |
| 9 | X6350204 | LINEAR DELIN PANELS 4 | 70 | EACH | $58.00 | $55.55 | |
| 10 | X6432110 | REPL IMP ATTN NRD TL3 | 115 | EACH | $831.00 | $699.93 | |
| 11 | X6432200 | REP IMP ATT (F R) | 3 | EACH | $4,861.00 | $16,665.00 | |
| 12 | X6440106 | REPL HT CBLE END SECT | 17 | EACH | $1,143.00 | $5,555.00 | |
| 13 | X6440108 | REP HT CABLE | 800 | FOOT | $3.90 | $31.11 | |
| 14 | X6440118 | REP HT BAR TERM | 53 | EACH | $1,143.00 | $2,222.00 | |
| 15 | X6440122 | REM REPL HT CBLE POST | 950 | EACH | $467.20 | $314.48 | |
| 16 | X6440124 | REM REPL HTC POST HD | 1,000 | EACH | $476.00 | $573.32 | |
| 17 | X6610200 | HMA CURB REPAIR | 25 | FOOT | $59.90 | $50.50 | |
| 18 | X6640502 | CHAIN LINK FENCE POST | 35 | EACH | $173.00 | $111.10 | |
| 19 | X7011834 | TC-PROT CALL OUT WORK | 20 | EACH | $2,680.00 | $3,618.20 | |
| 20 | X7011836 | TC-PROT XPWY CALL OUT | 10 | EACH | $2,866.00 | $48.24 | |
| 21 | Z0012752 | CONC STRUCTURE REPAIR | 2 | CU FT | $233.00 | $505.00 | |
| 22 | Z0020210 | PULL POST ARRANGEMENT | 10 | EACH | $283.00 | $111.10 | |
| 23 | Z0029657 | HTC SYSTEM MAINTENANCE | 599 | EACH | $40.34 | $67.83 | |
| 24 | Z0029665 | REP TB TERM T1 SP RLP | 5 | FOOT | $38.15 | $144.21 | |
| 25 | Z0052600 | REPAIR TR BAR TERM T2 | 1 | EACH | $837.00 | $88.88 | |
| 26 | Z0053200 | REPAIR TR BAR TERM T6 | 1 | EACH | $2,969.10 | $1,666.50 | |
| 27 | Z0053210 | REPAIR TR BAR TRM T6A | 1 | EACH | $1,439.00 | $1,666.50 | |
| 28 | Z0053220 | REPAIR TR BAR TRM T6B | 1 | EACH | $1,465.00 | $1,666.50 | |
| 29 | Z0053400 | REPAIR TR BAR TERM T8 | 1 | EACH | $43.00 | $55.55 | |
| 30 | Z0053500 | REPAIR TR BAR TERM T9 | 1 | EACH | $41.00 | $111.10 | |
| 31 | Z0053575 | REPAIR TR BAR TRM T12 | 1 | EACH | $44.00 | $83.33 | |
| 32 | 63100045 | TRAF BAR TERM T2 | 3 | EACH | $1,294.00 | $1,054.28 | |
| 33 | 63100070 | TRAF BAR TERM T5 | 1 | EACH | $715.00 | $812.64 | |
| 34 | 63100085 | TRAF BAR TERM T6 | 4 | EACH | $4,331.00 | $2,659.07 | |
| 35 | 63100087 | TRAF BAR TERM T6A | 1 | EACH | $2,510.00 | $2,653.62 | |
| 36 | 63100089 | TRAF BAR TERM T6B | 1 | EACH | $2,910.00 | $2,471.64 | |
| 37 | 63100101 | TRAF BAR TERM T9 | 1 | EACH | $31.00 | $277.75 | |
| 38 | 63100105 | TRAF BAR TERM T10 | 1 | EACH | $387.00 | $38.89 | |
| 39 | 63100115 | TRAF BAR TERM T12 | 1 | EACH | $34.00 | $444.40 | |
| 40 | 63100119 | TRAF BAR TERM T14 | 1 | EACH | $5,172.60 | $275.94 | |
| 41 | 63100167 | TR BAR TRM T1 SPL TAN | 25 | EACH | $4,680.14 | $5,971.12 | |
| 42 | 63100169 | TR BAR TRM T1 SPL FLR | 12 | EACH | $3,933.00 | $3,069.90 | |
| 43 | 63301210 | REM RE-E SPBGR TY A | 50 | FOOT | $3.08 | $2.78 | |
| 44 | 63301215 | REM RE-E SPBGR TY B | 50 | FOOT | $5.14 | $5.56 | |
| 45 | 64300260 | IMP ATTEN FRD NAR TL3 | 2 | EACH | $22,853.00 | $15,554.00 | |
| 46 | 66400105 | CH LK FENCE 4 | 350 | FOOT | $16.29 | $16.67 | |
| 47 | 66400305 | CH LK FENCE 6 | 25 | FOOT | $19.38 | $22.22 | |
| 48 | 66500105 | WOV W FENCE 4 | 1,250 | FOOT | $21.56 | $29.81 | |
| 49 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $1,288.00 | $3,030.00 | |
| 50 | 67100100 | MOBILIZATION | 1 | L SUM | $57,346.00 | $150,305.68 | |
| 51 | 78200005 | GRDRAIL REF TYPE A | 20 | EACH | $15.00 | $5.56 |