38(3-5)PP-3
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | G. M. Sipes Construction, Inc. Low bidder | $511,011 | ||
| 2 | Kinney Contractors, Inc. | $658,083 | +28.8% | |
| 3 | K-Five Construction Corporation | $861,878 | +68.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 G. M. Sipes Con… | #2 Kinney Contract… | #3 K-Five Construc… |
|---|---|---|---|---|---|---|---|---|
| 1 | X2700001 | TEMP RUMBLE STRIPS SP | 16 | EACH | $50.00 | $1,300.00 | $1,000.00 | |
| 2 | Z0018911 | DRILL-GROUT #6 T-BAR | 143 | EACH | $0.0100 | $18.00 | $40.00 | |
| 3 | Z0018913 | DRILL-GROUT #8 T-BAR | 1,092 | EACH | $0.0100 | $21.00 | $45.00 | |
| 4 | 44200610 | CL A PATCH T2 13 | 773 | SQ YD | $250.00 | $230.00 | $370.00 | |
| 5 | 44200612 | CL A PATCH T3 13 | 72 | SQ YD | $250.00 | $227.00 | $350.00 | |
| 6 | 44200614 | CL A PATCH T4 13 | 573 | SQ YD | $225.00 | $225.00 | $325.00 | |
| 7 | 44213000 | PATCH REINFORCEMENT | 1,418 | SQ YD | $85.00 | $74.00 | $80.00 | |
| 8 | 44213200 | SAW CUTS | 4,306 | FOOT | $0.0100 | $3.00 | $5.50 | |
| 9 | 67100100 | MOBILIZATION | 1 | L SUM | $24,000.00 | $38,000.00 | $60,000.00 | |
| 10 | 70100420 | TRAF CONT-PROT 701411 | 4 | EACH | $0.0100 | $1,200.00 | $1,000.00 | |
| 11 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $4,000.00 | $102,000.00 | $16,500.00 | |
| 12 | 70103815 | TR CONT SURVEILLANCE | 20 | CAL DA | $0.0100 | $0.0100 | $1,250.00 | |
| 13 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $0.0100 | $130.00 | $40.00 | |
| 14 | 78005110 | EPOXY PVT MK LINE 4 | 2,164 | FOOT | $4.30 | $4.50 | $10.00 | |
| 15 | 78005130 | EPOXY PVT MK LINE 6 | 1,880 | FOOT | $6.46 | $6.75 | $15.00 |