(111)CLV,CLV-1
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $627,241 | ||
| 2 | Gensini Excavating, Inc. | $707,289 | +12.8% | |
| 3 | Tobey's Construction & Cartage, Inc. | $781,224 | +24.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 Gensini Excavat… | #3 Tobey's Constru… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0900064 | MEMBR WTRPR SYS B STR | 42 | SQ YD | $75.00 | $75.00 | $73.85 | |
| 2 | X2700001 | TEMP RUMBLE STRIPS SP | 12 | EACH | $1,500.00 | $1,000.00 | $850.00 | |
| 3 | X6350204 | LINEAR DELIN PANELS 4 | 6 | EACH | $132.00 | $60.00 | $58.00 | |
| 4 | X7010101 | TRAF CONT-PROT 701201 SPL | 2 | EACH | $10,000.00 | $500.00 | $100.00 | |
| 5 | X7011801 | TRAF CONT-PROT BLR 22 | 1 | L SUM | $0.0100 | $500.00 | $100.00 | |
| 6 | Z0030850 | TEMP INFO SIGNING | 84 | SQ FT | $25.00 | $30.00 | $25.00 | |
| 7 | 20400800 | FURNISHED EXCAVATION | 56 | CU YD | $100.00 | $50.00 | $100.81 | |
| 8 | 31101200 | SUB GRAN MAT B 4 | 73 | SQ YD | $55.00 | $15.00 | $32.42 | |
| 9 | 42000060 | WELDED WIRE REINF | 273 | SQ YD | $25.00 | $10.00 | $21.17 | |
| 10 | 44004250 | PAVED SHLD REMOVAL | 58 | SQ YD | $40.00 | $15.00 | $34.36 | |
| 11 | 44201069 | CL B PATCH T4 18 | 53 | SQ YD | $300.00 | $213.00 | $368.00 | |
| 12 | 44201106 | CL B PATCH T4 20 | 220 | SQ YD | $300.00 | $223.00 | $364.53 | |
| 13 | 44201299 | DOWEL BARS 1 1/2 | 66 | EACH | $25.00 | $50.00 | $28.74 | |
| 14 | 44213200 | SAW CUTS | 461 | FOOT | $4.00 | $12.00 | $8.02 | |
| 15 | 44213204 | TIE BARS 3/4 | 35 | EACH | $20.00 | $40.00 | $20.82 | |
| 16 | 48101200 | AGGREGATE SHLDS B | 24 | TON | $50.00 | $35.00 | $122.59 | |
| 17 | 50102400 | CONC REM | 51 | CU YD | $750.00 | $694.00 | $658.75 | |
| 18 | 50800205 | REINF BARS, EPOXY CTD | 12,520 | POUND | $3.00 | $4.00 | $4.67 | |
| 19 | 50800530 | MECHANICAL SPLICERS | 94 | EACH | $50.00 | $200.00 | $191.76 | |
| 20 | 52200020 | TEMP SOIL RETEN SYSTM | 2,320 | SQ FT | $45.00 | $65.00 | $52.01 | |
| 21 | 54002060 | EXPAN BOLTS 3/4 X 12 | 55 | EACH | $35.00 | $150.00 | $39.46 | |
| 22 | 54003000 | CONC BOX CUL | 59 | CU YD | $1,400.00 | $2,396.00 | $3,664.13 | |
| 23 | 58600101 | GRANULAR BACKFILL STR | 61 | CU YD | $60.00 | $50.00 | $115.00 | |
| 24 | 63000003 | SPBGR TY A 9FT POSTS | 275 | FOOT | $57.20 | $41.00 | $38.67 | |
| 25 | 63000030 | SPGR ATT TO CULVERT | 37.5 | FOOT | $275.00 | $260.00 | $237.00 | |
| 26 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $4,290.00 | $3,500.00 | $3,216.00 | |
| 27 | 63200310 | GUARDRAIL REMOV | 442.5 | FOOT | $8.80 | $13.50 | $10.32 | |
| 28 | 67100100 | MOBILIZATION | 1 | L SUM | $37,000.00 | $25,000.00 | $43,993.71 | |
| 29 | 70100405 | TRAF CONT-PROT 701321 | 2 | EACH | $0.0100 | $9,000.00 | $8,250.00 | |
| 30 | 70106500 | TEMP BR TRAF SIGNALS | 2 | EACH | $30,000.00 | $13,500.00 | $12,280.00 | |
| 31 | 70300100 | SHORT TERM PAVT MKING | 28 | FOOT | $2.00 | $10.00 | $1.32 | |
| 32 | 70300150 | SHRT TRM PAVT MK REM | 9 | SQ FT | $3.00 | $10.00 | $28.43 | |
| 33 | 70400100 | TEMP CONC BARRIER | 500 | FOOT | $30.00 | $56.00 | $41.27 | |
| 34 | 70400200 | REL TEMP CONC BARRIER | 300 | FOOT | $15.00 | $15.00 | $24.07 | |
| 35 | 70600251 | IMP ATTN TEMP NRN TL3 | 4 | EACH | $6,500.00 | $6,000.00 | $5,500.00 | |
| 36 | 70600352 | IMP ATTN REL NRN TL3 | 2 | EACH | $2,500.00 | $2,200.00 | $1,850.00 | |
| 37 | 78009004 | MOD URETH PM LINE 4 | 4,416 | FOOT | $1.23 | $3.75 | $1.12 | |
| 38 | 78009006 | MOD URETH PM LINE 6 | 552 | FOOT | $1.85 | $7.00 | $1.68 | |
| 39 | 78200005 | GRDRAIL REF TYPE A | 6 | EACH | $27.50 | $12.00 | $12.00 | |
| 40 | 78300202 | PAVMT MRKG REM WTR BL | 139 | SQ FT | $19.80 | $60.00 | $18.00 |