(103BR)BR-1
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $868,946 | ||
| 2 | Gillan Construction LLC | $994,097 | +14.4% | |
| 3 | Gensini Excavating, Inc. | $1,146,216 | +31.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 Gillan Construc… | #3 Gensini Excavat… |
|---|---|---|---|---|---|---|---|---|
| 1 | X6350204 | LINEAR DELIN PANELS 4 | 8 | EACH | $30.80 | $100.00 | $109.17 | |
| 2 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $0.0100 | $13,640.00 | $13,537.34 | |
| 3 | X7200061 | TEMP INFO SIGNING | 105 | SQ FT | $35.00 | $27.50 | $27.29 | |
| 4 | X7200203 | DETOUR SIGNING | 1 | L SUM | $26,500.00 | $13,200.00 | $13,100.65 | |
| 5 | 20100110 | TREE REMOV 6-15 | 62 | UNIT | $170.50 | $100.00 | $169.22 | |
| 6 | 20200100 | EARTH EXCAVATION | 200 | CU YD | $35.00 | $39.00 | $20.79 | |
| 7 | 20400800 | FURNISHED EXCAVATION | 1,480 | CU YD | $30.00 | $40.00 | $38.50 | |
| 8 | 20700220 | POROUS GRAN EMBANK | 810 | CU YD | $50.00 | $65.00 | $45.00 | |
| 9 | 25000210 | SEEDING CL 2A | 0.5 | ACRE | $7,854.00 | $7,854.00 | $7,794.88 | |
| 10 | 25000400 | NITROGEN FERT NUTR | 47 | POUND | $5.50 | $5.50 | $5.46 | |
| 11 | 25000500 | PHOSPHORUS FERT NUTR | 47 | POUND | $5.50 | $5.50 | $5.46 | |
| 12 | 25000600 | POTASSIUM FERT NUTR | 47 | POUND | $5.50 | $5.50 | $5.46 | |
| 13 | 25100630 | EROSION CONTR BLANKET | 2,477 | SQ YD | $2.20 | $2.20 | $2.18 | |
| 14 | 28000250 | TEMP EROS CONTR SEED | 53 | POUND | $0.0100 | $3.50 | $5.46 | |
| 15 | 28000305 | TEMP DITCH CHECKS | 40 | FOOT | $22.00 | $22.00 | $21.83 | |
| 16 | 28000400 | PERIMETER EROS BAR | 1,058 | FOOT | $4.40 | $4.40 | $4.37 | |
| 17 | 28000500 | INLET & PIPE PROTECT | 4 | EACH | $250.00 | $150.00 | $272.93 | |
| 18 | 28001100 | TEMP EROS CONTR BLANK | 2,477 | SQ YD | $2.20 | $2.20 | $2.18 | |
| 19 | 28100105 | STONE RIPRAP CL A3 | 24 | SQ YD | $80.00 | $77.00 | $99.29 | |
| 20 | 28100107 | STONE RIPRAP CL A4 | 143 | SQ YD | $80.00 | $77.00 | $108.79 | |
| 21 | 28200200 | FILTER FABRIC | 176 | SQ YD | $5.00 | $4.50 | $13.44 | |
| 22 | 31101810 | SUB GRAN MAT B 12 | 272 | SQ YD | $22.00 | $28.75 | $28.62 | |
| 23 | 35501316 | HMA BASE CSE 8 | 232 | SQ YD | $50.00 | $137.50 | $136.47 | |
| 24 | 40200800 | AGG SURF COURSE TY B | 40 | TON | $40.00 | $57.00 | $28.89 | |
| 25 | 40600275 | BIT MATLS PR CT | 104 | POUND | $0.0100 | $3.30 | $3.28 | |
| 26 | 40600290 | BIT MATLS TACK CT | 1,077 | POUND | $0.0100 | $1.65 | $1.64 | |
| 27 | 40600370 | LONG JOINT SEALANT | 1,483 | FOOT | $10.00 | $8.80 | $8.73 | |
| 28 | 40603080 | HMA BC IL-19.0 N50 | 180 | TON | $120.00 | $192.50 | $191.05 | |
| 29 | 40604050 | HMA SC IL-9.5 C N50 | 120 | TON | $125.00 | $269.50 | $267.47 | |
| 30 | 44000100 | PAVEMENT REM | 155 | SQ YD | $20.00 | $18.00 | $20.00 | |
| 31 | 44000164 | HMA SURF REM 3 3/4 | 1,198 | SQ YD | $8.00 | $16.50 | $16.38 | |
| 32 | 44000500 | COMB CURB GUTTER REM | 354 | FOOT | $10.00 | $10.00 | $7.50 | |
| 33 | 44004250 | PAVED SHLD REMOVAL | 92 | SQ YD | $20.00 | $15.50 | $20.00 | |
| 34 | 48101200 | AGGREGATE SHLDS B | 62 | TON | $50.00 | $80.00 | $109.17 | |
| 35 | 48203029 | HMA SHOULDERS 8 | 387 | SQ YD | $55.00 | $71.50 | $70.96 | |
| 36 | 50100100 | REM EXIST STRUCT | 1 | EACH | $30,000.00 | $47,500.00 | $75,000.00 | |
| 37 | 50200100 | STRUCTURE EXCAVATION | 511 | CU YD | $35.00 | $42.00 | $20.79 | |
| 38 | 50800205 | REINF BARS, EPOXY CTD | 8,769 | POUND | $2.00 | $3.30 | $3.31 | |
| 39 | 51500100 | NAME PLATES | 1 | EACH | $2,000.00 | $1,100.00 | $1,000.00 | |
| 40 | 54003000 | CONC BOX CUL | 88 | CU YD | $1,200.00 | $950.00 | $1,825.00 | |
| 41 | 54011212 | PCBC 12X12 | 148 | FOOT | $1,900.00 | $1,900.00 | $2,398.00 | |
| 42 | 550A0050 | STORM SEW CL A 1 12 | 40 | FOOT | $100.00 | $86.00 | $97.80 | |
| 43 | 60235700 | INLETS TA T3F&G | 1 | EACH | $2,500.00 | $1,900.00 | $3,002.39 | |
| 44 | 60260500 | INLETS ADJ NEW T3F&G | 2 | EACH | $1,500.00 | $975.00 | $1,173.68 | |
| 45 | 60500060 | REMOV INLETS | 1 | EACH | $600.00 | $500.00 | $532.28 | |
| 46 | 60605000 | COMB CC&G TY B-6.24 | 286 | FOOT | $50.00 | $47.00 | $54.19 | |
| 47 | 63000001 | SPBGR TY A 6FT POSTS | 487.5 | FOOT | $41.21 | $49.00 | $53.49 | |
| 48 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $3,808.20 | $4,200.00 | $4,585.23 | |
| 49 | 63200310 | GUARDRAIL REMOV | 790 | FOOT | $7.74 | $10.00 | $10.92 | |
| 50 | 64200108 | SHOULDER RUM STRIP 8 | 495 | FOOT | $7.00 | $7.00 | $6.43 | |
| 51 | 67000400 | ENGR FIELD OFFICE A | 4 | CAL MO | $4,000.00 | $3,750.00 | $3,300.00 | |
| 52 | 67100100 | MOBILIZATION | 1 | L SUM | $30,000.00 | $50,000.00 | $40,000.00 | |
| 53 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $0.0100 | $110.00 | $109.17 | |
| 54 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $0.0100 | $110.00 | $109.17 | |
| 55 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $0.0100 | $110.00 | $109.17 | |
| 56 | 70107025 | CHANGEABLE MESSAGE SN | 140 | CAL DA | $50.00 | $38.50 | $38.21 | |
| 57 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $50.00 | $20.00 | $21.84 | |
| 58 | 78009004 | MOD URETH PM LINE 4 | 1,978 | FOOT | $2.09 | $2.09 | $2.07 | |
| 59 | 78009006 | MOD URETH PM LINE 6 | 1,977 | FOOT | $2.86 | $2.86 | $2.84 | |
| 60 | 78200005 | GRDRAIL REF TYPE A | 8 | EACH | $11.00 | $20.00 | $21.84 |