(101, 39, 39C)SFY
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Gallagher Asphalt Corporation Low bidder | $1,297,408 | ||
| 2 | Kankakee Valley Construction Company, Inc. | $1,347,664 | +3.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Gallagher Aspha… | #2 Kankakee Valley… |
|---|---|---|---|---|---|---|---|
| 1 | X0800001 | SHLDR REM SPL | 19,108 | SQ YD | $9.50 | $11.25 | |
| 2 | Z0030850 | TEMP INFO SIGNING | 63 | SQ FT | $32.00 | $25.00 | |
| 3 | 40600290 | BIT MATLS TACK CT | 8,640 | POUND | $0.0100 | $0.0100 | |
| 4 | 40800050 | INCIDENTAL HMA SURF | 8.2 | TON | $334.00 | $750.00 | |
| 5 | 44000157 | HMA SURF REM 2 | 70.6 | SQ YD | $48.00 | $130.00 | |
| 6 | 48203029 | HMA SHOULDERS 8 | 19,108 | SQ YD | $52.00 | $51.00 | |
| 7 | 64200108 | SHOULDER RUM STRIP 8 | 42,557 | FOOT | $0.3000 | $0.2900 | |
| 8 | 66900200 | NON SPL WASTE DISPOSL | 100 | CU YD | $200.00 | $101.00 | |
| 9 | 66900530 | SOIL DISPOSAL ANALY | 3 | EACH | $2,500.00 | $1,225.00 | |
| 10 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $3,900.00 | $2,250.00 | |
| 11 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $1,200.00 | $2,300.00 | |
| 12 | 66901006 | REG SUB MON | 2 | CAL DA | $1,000.00 | $1,525.00 | |
| 13 | 67100100 | MOBILIZATION | 1 | L SUM | $27,500.00 | $78,000.00 | |
| 14 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $15,000.00 | $18,000.00 | |
| 15 | 70103815 | TR CONT SURVEILLANCE | 5 | CAL DA | $1,300.00 | $0.0100 | |
| 16 | 78001110 | PAINT PVT MK LINE 4 | 88,344 | FOOT | $0.2000 | $0.1300 |