2021-1 TREE REMOVAL
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Nettle Creek Nursery, Inc. Low bidder | $40,720 | ||
| 2 | Clean Cut Tree Service, Inc. | $42,786 | +5.1% | |
| 3 | Endrizzi Contracting, Inc | $75,982 | +86.6% | |
| 4 | Scruggs Machinery Equipment Construction Commodity Co. | $114,702 | +181.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Nettle Creek Nu… | #2 Clean Cut Tree … | #3 Endrizzi Contra… | #4 Scruggs Machine… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 20100110 | TREE REMOV 6-15 | 99 | UNIT | $40.00 | $38.00 | $126.00 | $101.68 | |
| 2 | 20100210 | TREE REMOV OVER 15 | 546 | UNIT | $60.00 | $44.00 | $98.00 | $176.08 | |
| 3 | 67100100 | MOBILIZATION | 1 | L SUM | $4,000.00 | $15,000.00 | $10,000.00 | $8,496.48 |