(17,18)SFY,Y
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Curran Contracting Company Low bidder | $742,928 | ||
| 2 | Advanced Asphalt Company | $823,869 | +10.9% | |
| 3 | D. Construction, Inc. | $981,188 | +32.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Curran Contract… | #2 Advanced Asphal… | #3 D. Construction… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0800001 | SHLDR REM SPL | 20,149 | SQ YD | $2.15 | $6.15 | $8.39 | |
| 2 | Z0030850 | TEMP INFO SIGNING | 42 | SQ FT | $30.00 | $30.00 | $25.00 | |
| 3 | 40600290 | BIT MATLS TACK CT | 9,140 | POUND | $0.0100 | $0.7500 | $0.0100 | |
| 4 | 40800050 | INCIDENTAL HMA SURF | 42.5 | TON | $85.00 | $140.00 | $85.00 | |
| 5 | 44000157 | HMA SURF REM 2 | 313.1 | SQ YD | $3.90 | $13.00 | $12.00 | |
| 6 | 48102100 | AGG WEDGE SHLD TYPE B | 782 | TON | $45.00 | $35.50 | $28.00 | |
| 7 | 48203029 | HMA SHOULDERS 8 | 20,149 | SQ YD | $26.00 | $25.75 | $31.00 | |
| 8 | 64200108 | SHOULDER RUM STRIP 8 | 53,284 | FOOT | $0.2500 | $0.2500 | $0.2200 | |
| 9 | 66900200 | NON SPL WASTE DISPOSL | 220 | CU YD | $80.00 | $50.50 | $80.00 | |
| 10 | 66900530 | SOIL DISPOSAL ANALY | 7 | EACH | $1,250.00 | $2,000.00 | $1,375.00 | |
| 11 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,600.00 | $4,500.00 | $2,475.00 | |
| 12 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $2,200.00 | $3,500.00 | $2,475.00 | |
| 13 | 66901006 | REG SUB MON | 12 | CAL DA | $880.00 | $700.00 | $990.00 | |
| 14 | 67100100 | MOBILIZATION | 1 | L SUM | $40,000.00 | $45,000.00 | $50,000.00 | |
| 15 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $12,650.00 | $21,200.00 | $20,400.00 | |
| 16 | 70103815 | TR CONT SURVEILLANCE | 10 | CAL DA | $1,250.00 | $1.00 | $0.0100 | |
| 17 | 78001110 | PAINT PVT MK LINE 4 | 128,892 | FOOT | $0.1100 | $0.1100 | $0.2400 |