Bid tab 66J55

Let Mar 8, 2019 · District 3 · Lasalle Sign up free

‹ Mar 2019 results

(4,5)CJS

Let date
Friday, March 8, 2019
Contract
66J55 · job page
District
District 3
County
Lasalle
Highway
Limits
9.76 miles of crack and joint sealing on IL 71 from north of I-80 to US 52.

Bidders 5

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 Complete Asphalt Service Co. Low bidder $32,347
2 Countryman, Inc. $48,080 +48.6%
3 Denler, Inc. $61,727 +90.8%
4 SKC Construction, Inc. $68,296 +111.1%
5 Fahrner Asphalt Sealers, LLC $120,444 +272.4%

Bid tab: unit prices 7 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Complete Asphal…#2 Countryman, Inc.#3 Denler, Inc.#4 SKC Constructio…#5 Fahrner Asphalt…
1Z0030850 TEMP INFO SIGNING42SQ FT $30.00 $72.00 $25.00 $27.00 $25.00
245100100 CRACK ROUTING (PAVT)51,552FOOT $0.0100 $0.1300 $0.1000 $0.0100 $0.7600
345100200 CRACK FILLING19,847POUND $1.07 $1.00 $1.40 $1.77 $2.54
467100100 MOBILIZATION1L SUM $2,000.00 $8,000.00 $3,500.00 $3,000.00 $16,000.00
570100460 TRAF CONT-PROT 7013061L SUM $500.00 $5,200.00 $5,000.00 $12,000.00 $4,250.00
678001110 PAINT PVT MK LINE 433,675FOOT $0.1300 $0.1000 $0.3600 $0.3100 $0.1800
778001130 PAINT PVT MK LINE 612,932FOOT $0.1900 $0.1500 $0.5500 $0.4700 $0.2700