Bid tab 66H95

Let Mar 9, 2018 · District 3 · Bureau Sign up free

‹ Mar 2018 results

D3 CRACK SEAL 2018-2

Let date
Friday, March 9, 2018
Contract
66H95 · job page
District
District 3
County
Bureau
Highway
Limits
Centerline crack and joint sealing on I-80 from 0.7 mile east of I-180 to west of IL 89.

Bidders 5

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 Complete Asphalt Service Co. Low bidder $65,466
2 Countryman, Inc. $72,767 +11.2%
3 Denler, Inc. $83,497 +27.5%
4 Fahrner Asphalt Sealers, LLC $93,275 +42.5%
5 SKC Construction, Inc. $108,140 +65.2%

Bid tab: unit prices 7 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Complete Asphal…#2 Countryman, Inc.#3 Denler, Inc.#4 Fahrner Asphalt…#5 SKC Constructio…
1X0326880 MESSAGE BOARD VEH DRV30HOUR $160.00 $110.00 $140.00 $100.00 $150.00
2X0326907 PORT VHMNT CH MSS SGN0.5CAL MO $5,000.00 $3,000.00 $5,000.00 $10,000.00 $6,000.00
3X7010216 TRAF CONT & PROT SPL1L SUM $1,500.00 $17,600.00 $25,000.00 $20,000.00 $38,000.00
4X7015005 CHANGEABLE MESSAGE SN30CAL DA $75.00 $205.00 $175.00 $125.00 $65.00
545100100 CRACK ROUTING (PAVT)77,657FOOT $0.0100 $0.0500 $0.0100 $0.5200 $0.0100
645100200 CRACK FILLING27,180POUND $1.83 $1.30 $1.50 $0.4100 $1.91
767100100 MOBILIZATION1L SUM $3,900.00 $5,000.00 $5,000.00 $10,000.00 $8,000.00