D3 CRACK SEAL 2018-1
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Freehill Asphalt, Inc. Low bidder | $65,778 | ||
| 2 | Fahrner Asphalt Sealers, LLC | $102,188 | +55.4% | |
| 3 | SKC Construction, Inc. | $209,506 | +218.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Freehill Asphal… | #2 Fahrner Asphalt… | #3 SKC Constructio… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0326880 | MESSAGE BOARD VEH DRV | 80 | HOUR | $10.00 | $125.00 | $275.00 | |
| 2 | X0326907 | PORT VHMNT CH MSS SGN | 1 | CAL MO | $100.00 | $15,000.00 | $19,000.00 | |
| 3 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $15,000.00 | $13,000.00 | $45,000.00 | |
| 4 | X7015005 | CHANGEABLE MESSAGE SN | 45 | CAL DA | $75.00 | $100.00 | $125.00 | |
| 5 | 45100100 | CRACK ROUTING (PAVT) | 82,546 | FOOT | $0.0100 | $0.4100 | $0.2500 | |
| 6 | 45100200 | CRACK FILLING | 28,889 | POUND | $1.46 | $0.4100 | $2.57 | |
| 7 | 67100100 | MOBILIZATION | 1 | L SUM | $3,500.00 | $14,000.00 | $23,000.00 |