(140)SFY
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Kankakee Valley Construction Company, Inc. Low bidder | $606,504 | ||
| 2 | Gallagher Asphalt Corporation | $787,000 | +29.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Kankakee Valley… | #2 Gallagher Aspha… |
|---|---|---|---|---|---|---|---|
| 1 | X0800001 | SHLDR REM SPL | 9,365 | SQ YD | $4.85 | $5.00 | |
| 2 | Z0030850 | TEMP INFO SIGNING | 42 | SQ FT | $20.00 | $20.00 | |
| 3 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $3,500.00 | $3,000.00 | |
| 4 | 20200600 | EXC & GR EX SHOULDER | 211 | UNIT | $220.00 | $375.00 | |
| 5 | 40600290 | BIT MATLS TACK CT | 4,215 | POUND | $0.0100 | $0.0100 | |
| 6 | 48203029 | HMA SHOULDERS 8 | 9,365 | SQ YD | $38.00 | $48.00 | |
| 7 | 64200108 | SHOULDER RUM STRIP 8 | 21,072 | FOOT | $0.6000 | $0.7500 | |
| 8 | 66900200 | NON SPL WASTE DISPOSL | 625 | CU YD | $105.00 | $85.00 | |
| 9 | 66900450 | SPL WASTE PLNS/REPORT | 1 | L SUM | $5,000.00 | $7,000.00 | |
| 10 | 66900530 | SOIL DISPOSAL ANALY | 6 | EACH | $950.00 | $1,300.00 | |
| 11 | 67100100 | MOBILIZATION | 1 | L SUM | $21,000.00 | $47,000.00 | |
| 12 | 70100310 | TRAF CONT-PROT 701421 | 1 | L SUM | $19,000.00 | $51,475.33 | |
| 13 | 70103815 | TR CONT SURVEILLANCE | 5 | CAL DA | $200.00 | $200.00 | |
| 14 | 78008210 | POLYUREA PM T1 LN 4 | 42,144 | FOOT | $0.5800 | $0.5800 |