D3-J REPLACEMENT FY 2018
- Let date
- Friday, September 21, 2018
- Contract
- 66H68 · job page
- District
- District 3
- County
- Dekalb, Kendall
- Highway
- Limits
- Guardrail end section replacement on various routes in DeKalb and Kendall Counties.
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Curran Contracting Company Low bidder | $1,677,677 | ||
| 2 | Northern Contracting, Inc. | $1,895,919 | +13.0% | |
| 3 | COLLINS & HERMANN, INC. | $2,364,298 | +40.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Curran Contract… | #2 Northern Contra… | #3 COLLINS & HERMA… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0325667 | WD CTRL MWNG STRP SP | 3,809 | SQ YD | $27.11 | $73.00 | $48.86 | |
| 2 | 20100110 | TREE REMOV 6-15 | 48 | UNIT | $40.00 | $67.24 | $30.97 | |
| 3 | 20400800 | FURNISHED EXCAVATION | 4,101 | CU YD | $136.00 | $125.00 | $91.62 | |
| 4 | 25000210 | SEEDING CL 2A | 3.9 | ACRE | $6,900.00 | $7,871.00 | $4,645.80 | |
| 5 | 25000400 | NITROGEN FERT NUTR | 359 | POUND | $1.80 | $6.50 | $8.26 | |
| 6 | 25000500 | PHOSPHORUS FERT NUTR | 359 | POUND | $1.80 | $3.00 | $8.26 | |
| 7 | 25000600 | POTASSIUM FERT NUTR | 359 | POUND | $1.80 | $6.18 | $8.26 | |
| 8 | 25100635 | HD EROS CONTR BLANKET | 19,051 | SQ YD | $2.30 | $4.75 | $3.10 | |
| 9 | 28000400 | PERIMETER EROS BAR | 4,176 | FOOT | $4.20 | $7.81 | $8.78 | |
| 10 | 60600605 | CONC CURB TB | 135 | FOOT | $80.00 | $100.00 | $206.48 | |
| 11 | 63000001 | SPBGR TY A 6FT POSTS | 1,012.5 | FOOT | $25.10 | $25.10 | $45.37 | |
| 12 | 63000003 | SPBGR TY A 9FT POSTS | 6,712.5 | FOOT | $32.65 | $32.65 | $59.71 | |
| 13 | 63000350 | LSG OV CUL 12'6" SPAN | 637.5 | FOOT | $30.35 | $30.35 | $130.34 | |
| 14 | 63000360 | LSG OV CUL 18'9" SPAN | 175 | FOOT | $30.35 | $30.35 | $134.38 | |
| 15 | 63100085 | TRAF BAR TERM T6 | 13 | EACH | $3,518.00 | $3,518.00 | $5,024.44 | |
| 16 | 63100167 | TR BAR TRM T1 SPL TAN | 59 | EACH | $2,731.00 | $2,731.00 | $5,090.41 | |
| 17 | 63200310 | GUARDRAIL REMOV | 9,112 | FOOT | $7.00 | $7.00 | $13.86 | |
| 18 | 67100100 | MOBILIZATION | 1 | L SUM | $95,000.00 | $112,000.00 | $174,620.24 | |
| 19 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $1.00 | $500.00 | $212,363.36 | |
| 20 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $1.00 | $230,400.00 | $191,627.02 | |
| 21 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $274,774.65 | $2,200.00 | $11,758.64 | |
| 22 | 70102631 | TR CONT & PROT 701601 | 1 | EACH | $1.00 | $40,000.00 | $11,758.64 | |
| 23 | 72501000 | TERMINAL MARKER - DA | 59 | EACH | $35.00 | $35.00 | $36.65 | |
| 24 | 78200005 | GRDRAIL REF TYPE A | 169 | EACH | $12.00 | $12.00 | $4.58 |