((142)&(81-2))TR
- Let date
- Friday, September 19, 2025
- Contract
- 64U54 · job page
- District
- District 2
- County
- Rock Island
- Highway
- Limits
- Tree removal along I-74 from 0.9 miles south of 23rd Ave. in Moline to 0.5 miles south of IL 5 and along IL 5 from west of 16th St. to 0.2 miles west of 38th St. (approximately 2.0 miles total).
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Homer Tree Service, Inc. Low bidder | $297,068 | ||
| 2 | Clean Cut Tree Service, Inc. | $562,997 | +89.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Homer Tree Serv… | #2 Clean Cut Tree … |
|---|---|---|---|---|---|---|---|
| 1 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $15,000.00 | $41,500.00 | |
| 2 | 20100110 | TREE REMOV 6-15 | 1,466 | UNIT | $40.00 | $66.00 | |
| 3 | 20100210 | TREE REMOV OVER 15 | 916 | UNIT | $50.00 | $76.00 | |
| 4 | 20100500 | TREE REMOV ACRES | 4.75 | ACRE | $15,000.00 | $25,000.00 | |
| 5 | 25000350 | SEEDING CL 7 | 4.75 | ACRE | $900.00 | $12,500.00 | |
| 6 | 25100125 | MULCH METHOD 3 | 4.75 | ACRE | $6,500.00 | $8,000.00 | |
| 7 | 28000250 | TEMP EROS CONTR SEED | 475 | POUND | $8.90 | $40.00 | |
| 8 | 67100100 | MOBILIZATION | 1 | L SUM | $10,000.00 | $75,000.00 | |
| 9 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $19,000.00 | $15,000.00 | |
| 10 | 70100825 | TRAF CONT-PROT 701456 | 1 | L SUM | $19,000.00 | $15,000.00 | |
| 11 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $19,000.00 | $15,000.00 |