(195-1B-1)BP
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Civil Coatings and Construction Inc. Low bidder | $367,125 | ||
| 2 | Eagle Painting & Maintenance Company, Inc. | $468,850 | +27.7% | |
| 3 | Venus Painting Co. | $677,750 | +84.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Civil Coatings … | #2 Eagle Painting … | #3 Venus Painting … |
|---|---|---|---|---|---|---|---|---|
| 1 | X5067501 | BR CLN & PT WAR #1 | 1 | L SUM | $100.00 | $500.00 | $1,000.00 | |
| 2 | X5067502 | BR CLN & PT WAR #2 | 1 | L SUM | $100.00 | $500.00 | $1,000.00 | |
| 3 | X7010208 | TC-PROT 701402 SPL | 2 | EACH | $9,000.00 | $21,000.00 | $3,000.00 | |
| 4 | Z0007101 | C&D LEAD PT CL RS N1 | 1 | L SUM | $1,000.00 | $36,700.00 | $8,000.00 | |
| 5 | Z0007102 | C&D LEAD PT CL RS N2 | 1 | L SUM | $1,000.00 | $36,700.00 | $8,000.00 | |
| 6 | Z0010501 | CLEAN & PT STL BR N1 | 1 | L SUM | $154,761.50 | $146,800.00 | $295,000.00 | |
| 7 | Z0010502 | CLEAN & PT STL BR N2 | 1 | L SUM | $154,761.50 | $146,800.00 | $295,000.00 | |
| 8 | 67100100 | MOBILIZATION | 1 | L SUM | $18,000.00 | $25,000.00 | $38,000.00 | |
| 9 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $5,000.00 | $2,000.00 | $5,000.00 | |
| 10 | 70400100 | TEMP CONC BARRIER | 775 | FOOT | $15.00 | $30.00 | $15.00 | |
| 11 | 70400200 | REL TEMP CONC BARRIER | 275 | FOOT | $1.00 | $4.00 | $15.00 | |
| 12 | 70600250 | IMP ATTN TEMP NRD TL3 | 2 | EACH | $1,250.00 | $3,000.00 | $1,500.00 | |
| 13 | 70600350 | IMP ATTN REL NRD TL3 | 2 | EACH | $1.00 | $750.00 | $1,000.00 |