(30,31,43,44,45)J
- Let date
- Friday, April 27, 2018
- Contract
- 64M33 · job page
- District
- District 2
- County
- Jo Daviess
- Highway
- Limits
- Replacing non-compliant guardrail end sections along US 20 from the Mississippi River to NB IL 84.
- Classification
- ·
- Project number
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Lovewell Fencing, Inc. Low bidder | $589,385 | ||
| 2 | Northern Contracting, Inc. | $648,914 | +10.1% | |
| 3 | Access Control Company, Inc. | $666,667 | +13.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Lovewell Fencin… | #2 Northern Contra… | #3 Access Control … |
|---|---|---|---|---|---|---|---|---|
| 1 | Z0052410 | REPAIR TRBT T1 SP TAN | 1 | EACH | $100.00 | $400.00 | $947.00 | |
| 2 | 20400800 | FURNISHED EXCAVATION | 345 | CU YD | $150.00 | $125.00 | $95.00 | |
| 3 | 28000400 | PERIMETER EROS BAR | 960 | FOOT | $4.00 | $5.00 | $4.15 | |
| 4 | 48102100 | AGG WEDGE SHLD TYPE B | 266 | TON | $100.00 | $99.00 | $85.00 | |
| 5 | 60600605 | CONC CURB TB | 10 | FOOT | $1,500.00 | $150.00 | $600.00 | |
| 6 | 63000003 | SPBGR TY A 9FT POSTS | 10,272 | FOOT | $29.00 | $26.66 | $31.55 | |
| 7 | 63000350 | LSG OV CUL 12'6" SPAN | 75 | FOOT | $25.00 | $25.00 | $24.00 | |
| 8 | 63100045 | TRAF BAR TERM T2 | 15 | EACH | $1,200.00 | $1,116.00 | $1,315.00 | |
| 9 | 63100070 | TRAF BAR TERM T5 | 1 | EACH | $800.00 | $685.00 | $1,100.00 | |
| 10 | 63100085 | TRAF BAR TERM T6 | 2 | EACH | $2,900.00 | $2,880.00 | $3,200.00 | |
| 11 | 63100167 | TR BAR TRM T1 SPL TAN | 13 | EACH | $2,650.00 | $2,748.00 | $3,250.00 | |
| 12 | 63100169 | TR BAR TRM T1 SPL FLR | 3 | EACH | $2,550.00 | $2,345.00 | $3,250.00 | |
| 13 | 63200310 | GUARDRAIL REMOV | 10,967 | FOOT | $4.00 | $5.85 | $6.00 | |
| 14 | 63500105 | DELINEATORS | 16 | EACH | $55.00 | $12.00 | $55.00 | |
| 15 | 67100100 | MOBILIZATION | 1 | L SUM | $28,000.00 | $40,000.00 | $60,000.00 | |
| 16 | 70100310 | TRAF CONT-PROT 701421 | 1 | L SUM | $7,500.00 | $20,000.00 | $4,200.00 | |
| 17 | 70100700 | TRAF CONT-PROT 701406 | 1 | L SUM | $4,000.00 | $100,000.00 | $55,000.00 | |
| 18 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $40,200.00 | $5,000.00 | $8,000.00 | |
| 19 | 72501000 | TERMINAL MARKER - DA | 16 | EACH | $25.00 | $35.00 | $30.00 | |
| 20 | 78200005 | GRDRAIL REF TYPE A | 98 | EACH | $8.00 | $12.00 | $9.00 |