(81-1WS)M-4
- Let date
- Friday, July 30, 2021
- Contract
- 64M00 · job page
- District
- District 2
- County
- Rock Island
- Highway
- Limits
- 1.15 miles / replacement of Westbound scale and pavement patching in both weigh scale stations on I-80 located 1.4 miles south of IL 84.
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | G. M. Sipes Construction, Inc. Low bidder | $1,072,933 | ||
| 2 | Brandt Construction Co. | $1,205,448 | +12.4% | |
| 3 | Valley Construction Co. | $1,418,100 | +32.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 G. M. Sipes Con… | #2 Brandt Construc… | #3 Valley Construc… |
|---|---|---|---|---|---|---|---|---|
| 1 | X4403300 | CONC MEDIAN REMOV | 566 | SQ FT | $5.00 | $15.00 | $13.00 | |
| 2 | X6020084 | MANHOLE SPECIAL | 1 | EACH | $1,000.00 | $5,200.00 | $10,500.00 | |
| 3 | X6060714 | CONC MEDIAN SPL | 566 | SQ FT | $25.00 | $35.00 | $24.00 | |
| 4 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $8,000.00 | $20,800.00 | $14,000.00 | |
| 5 | X7830070 | GRV RCSD PVT MRKG 5 | 22,290 | FOOT | $0.5000 | $0.5500 | $0.5000 | |
| 6 | Z0001500 | APPROACH SLAB R&R | 12 | SQ YD | $1,166.66 | $100.00 | $1,200.00 | |
| 7 | Z0012754 | STR REP CON DP = < 5 | 28.3 | SQ FT | $353.30 | $300.00 | $36.00 | |
| 8 | Z0025710 | F&I STATIC SCALE COMP | 1 | L SUM | $190,546.10 | $285,000.00 | $215,000.00 | |
| 9 | Z0028415 | GEOTECHNICAL REINF | 961 | SQ YD | $2.50 | $4.50 | $6.75 | |
| 10 | 30300001 | AGG SUBGRADE IMPROVE | 110 | CU YD | $35.00 | $120.00 | $125.00 | |
| 11 | 42400200 | PC CONC SIDEWALK 5 | 685 | SQ FT | $15.00 | $13.00 | $20.00 | |
| 12 | 44000600 | SIDEWALK REM | 685 | SQ FT | $5.00 | $3.50 | $3.00 | |
| 13 | 44200050 | WELDED WIRE REINF | 3,499 | SQ YD | $15.00 | $16.00 | $20.00 | |
| 14 | 44200970 | CL B PATCH T2 10 | 341 | SQ YD | $150.00 | $110.00 | $230.00 | |
| 15 | 44200974 | CL B PATCH T3 10 | 327 | SQ YD | $150.00 | $110.00 | $185.00 | |
| 16 | 44200976 | CL B PATCH T4 10 | 3,172 | SQ YD | $125.00 | $110.00 | $160.00 | |
| 17 | 44201294 | CL B PATCH EXPAN JT | 170 | FOOT | $25.00 | $25.00 | $8.00 | |
| 18 | 44201299 | DOWEL BARS 1 1/2 | 2,128 | EACH | $25.00 | $22.50 | $30.00 | |
| 19 | 44213200 | SAW CUTS | 10,128 | FOOT | $0.0100 | $4.50 | $7.75 | |
| 20 | 44213204 | TIE BARS 3/4 | 838 | EACH | $10.00 | $20.00 | $21.50 | |
| 21 | 50101500 | REM EXIST SUP-STR | 1 | EACH | $23,767.00 | $20,000.00 | $20,000.00 | |
| 22 | 50102400 | CONC REM | 16.5 | CU YD | $2,424.24 | $1,500.00 | $2,500.00 | |
| 23 | 50300225 | CONC STRUCT | 17.1 | CU YD | $1,169.60 | $2,500.00 | $1,200.00 | |
| 24 | 50300300 | PROTECTIVE COAT | 233 | SQ YD | $1.00 | $10.00 | $18.00 | |
| 25 | 50500405 | F & E STRUCT STEEL | 1,930 | POUND | $1.03 | $10.00 | $1.05 | |
| 26 | 50800205 | REINF BARS, EPOXY CTD | 2,110 | POUND | $9.00 | $3.50 | $9.00 | |
| 27 | 58600101 | GRANULAR BACKFILL STR | 26 | CU YD | $153.84 | $110.00 | $155.00 | |
| 28 | 59000200 | EPOXY CRACK INJECTION | 12 | FOOT | $166.66 | $200.00 | $170.00 | |
| 29 | 60255500 | MAN ADJUST | 1 | EACH | $500.00 | $1,300.00 | $1,200.00 | |
| 30 | 67000400 | ENGR FIELD OFFICE A | 3 | CAL MO | $2,000.00 | $3,500.00 | $2,000.00 | |
| 31 | 67100100 | MOBILIZATION | 1 | L SUM | $52,000.00 | $70,000.00 | $80,000.00 | |
| 32 | 78009004 | MOD URETH PM LINE 4 | 22,290 | FOOT | $0.7500 | $0.8500 | $0.7500 |