2023-943-I
- Let date
- Friday, March 7, 2025
- Contract
- 62W63 · job page
- District
- District 1
- County
- Cook
- Highway
- Limits
- This is a parking lot resurfacing improvement includes pavement removal, drainage structure adjustment, placement of subbase material, HMA binder course HMA surface course, Portland cement concrete, thermoplastic pavement markings. Located in the IDOT Hillside Maintenance Yard at, 4160 May St., Hillside, IL.
- Classification
- ·
- Project number
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | A Lamp Concrete Contractors, Inc. Low bidder | $794,968 | ||
| 2 | R. W. Dunteman Company | $798,811 | +0.5% | |
| 3 | Schroeder Asphalt Services, Inc. | $814,698 | +2.5% | |
| 4 | Builders Paving, LLC | $854,500 | +7.5% | |
| 5 | Brothers Asphalt Paving, Inc. | $1,016,238 | +27.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 A Lamp Concrete… | #2 R. W. Dunteman … | #3 Schroeder Aspha… | #4 Builders Paving… | #5 Brothers Asphal… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X5537800 | SS CLEANED 12 | 400 | FOOT | $2.00 | $2.00 | $2.25 | $2.00 | $2.20 | |
| 2 | X6700407 | ENGRS FLD OFC TY A D1 | 6 | CAL MO | $1,000.00 | $4,000.00 | $3,500.00 | $4,000.00 | $3,000.00 | |
| 3 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $3,000.00 | $5,000.00 | $7,500.00 | $7,500.00 | $5,500.00 | |
| 4 | Z0018400 | DRAINAGE STR ADJ | 4 | EACH | $850.00 | $600.00 | $660.00 | $600.00 | $660.00 | |
| 5 | Z0018500 | DRAINAGE STR CLEANED | 6 | EACH | $850.00 | $525.00 | $600.00 | $525.00 | $578.00 | |
| 6 | 20200100 | EARTH EXCAVATION | 1,918 | CU YD | $57.00 | $19.38 | $43.00 | $22.00 | $65.00 | |
| 7 | 31101400 | SUB GRAN MAT B 6 | 11,507 | SQ YD | $8.85 | $6.00 | $9.31 | $12.00 | $10.00 | |
| 8 | 40600275 | BIT MATLS PR CT | 25,891 | POUND | $0.0100 | $0.3300 | $0.0100 | $0.0100 | $0.2500 | |
| 9 | 40600290 | BIT MATLS TACK CT | 2,574 | POUND | $0.0100 | $0.9100 | $0.0100 | $0.0100 | $0.2500 | |
| 10 | 40603085 | HMA BC IL-19.0 N70 | 1,922 | TON | $95.00 | $88.12 | $89.00 | $95.00 | $100.00 | |
| 11 | 40604062 | HMA SC IL-9.5 D N70 | 961 | TON | $100.50 | $100.23 | $93.00 | $95.00 | $120.00 | |
| 12 | 42000060 | WELDED WIRE REINF | 316 | SQ YD | $7.00 | $13.55 | $10.75 | $11.50 | $43.00 | |
| 13 | 42000300 | PCC PVT 8 | 316 | SQ YD | $127.00 | $91.54 | $130.00 | $125.00 | $128.70 | |
| 14 | 42001300 | PROTECTIVE COAT | 316 | SQ YD | $3.00 | $0.8000 | $0.0200 | $1.00 | $1.10 | |
| 15 | 44000100 | PAVEMENT REM | 11,508 | SQ YD | $7.25 | $15.10 | $5.65 | $9.00 | $8.00 | |
| 16 | 66900200 | NON SPL WASTE DISPOSL | 1,625 | CU YD | $60.00 | $70.00 | $115.00 | $87.50 | $150.00 | |
| 17 | 66900530 | SOIL DISPOSAL ANALY | 3 | EACH | $1,525.00 | $1,620.00 | $1,500.00 | $1,620.00 | $1,540.00 | |
| 18 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $3,400.00 | $2,700.00 | $3,400.00 | $2,700.00 | $4,400.00 | |
| 19 | 66901006 | REG SUB MON | 6 | CAL DA | $700.00 | $990.00 | $785.00 | $990.00 | $1,100.00 | |
| 20 | 67100100 | MOBILIZATION | 1 | L SUM | $47,650.00 | $41,342.23 | $14,000.00 | $54,640.84 | $20,000.00 | |
| 21 | 78000200 | THPL PVT MK LINE 4 | 250 | FOOT | $8.00 | $19.40 | $23.00 | $19.40 | $21.34 |