2023 ROD YARD PARKING
Bidders 8
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | R. W. Dunteman Company Low bidder | $1,427,900 | ||
| 2 | A Lamp Concrete Contractors, Inc. | $1,487,925 | +4.2% | |
| 3 | Plote Construction, Inc. | $1,566,978 | +9.7% | |
| 4 | Berger Excavating Contractors, Inc. d/b/a Berger Contractors, Inc. | $1,597,798 | +11.9% | |
| 5 | K-Five Construction Corporation | $1,696,000 | +18.8% | |
| 6 | Martam Construction Incorporated | $1,729,832 | +21.1% | |
| 7 | Builders Paving, LLC | $2,083,830 | +45.9% | |
| 8 | Lenny Hoffman Excavating, Inc. | $2,379,452 | +66.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 R. W. Dunteman … | #2 A Lamp Concrete… | #3 Plote Construct… | #4 Berger Excavati… | #5 K-Five Construc… | #6 Martam Construc… | #7 Builders Paving… | #8 Lenny Hoffman E… |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X4400503 | CC&G RMVL REPL > 10FT | 1,279 | FOOT | $65.53 | $37.00 | $43.77 | $41.50 | $51.00 | $37.30 | $65.00 | $41.25 | |
| 2 | X5537800 | SS CLEANED 12 | 400 | FOOT | $3.00 | $3.00 | $3.00 | $5.50 | $3.00 | $3.00 | $3.00 | $14.00 | |
| 3 | X6700407 | ENGRS FLD OFC TY A D1 | 12 | CAL MO | $2,000.00 | $2,000.00 | $2,500.00 | $2,400.00 | $3,300.00 | $4,307.89 | $3,500.00 | $4,500.00 | |
| 4 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $6,000.00 | $4,900.00 | $10,000.00 | $2,800.00 | $10,000.00 | $47,000.00 | $10,000.00 | $50,415.00 | |
| 5 | Z0018400 | DRAINAGE STR ADJ | 2 | EACH | $1,000.00 | $950.00 | $1,000.00 | $625.00 | $900.00 | $818.23 | $950.00 | $863.00 | |
| 6 | Z0018500 | DRAINAGE STR CLEANED | 10 | EACH | $485.00 | $325.00 | $485.00 | $245.00 | $325.00 | $325.00 | $325.00 | $257.00 | |
| 7 | Z0018600 | DRAINAGE STR RECONST | 4 | EACH | $3,125.00 | $1,850.00 | $3,125.00 | $1,850.00 | $1,800.00 | $1,636.45 | $2,500.00 | $1,500.00 | |
| 8 | 20200100 | EARTH EXCAVATION | 4,305 | CU YD | $47.85 | $41.50 | $50.00 | $42.50 | $43.00 | $48.22 | $65.00 | $35.00 | |
| 9 | 31101400 | SUB GRAN MAT B 6 | 20,663 | SQ YD | $7.45 | $8.00 | $7.25 | $9.35 | $8.27 | $7.36 | $11.00 | $17.00 | |
| 10 | 40600275 | BIT MATLS PR CT | 46,492 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.2500 | $0.0100 | $0.2800 | $0.4000 | $0.0100 | |
| 11 | 40600290 | BIT MATLS TACK CT | 8,789 | POUND | $0.0100 | $0.0100 | $0.0100 | $1.00 | $0.0100 | $1.11 | $1.75 | $0.0100 | |
| 12 | 40603085 | HMA BC IL-19.0 N70 | 3,472 | TON | $83.08 | $91.00 | $93.00 | $80.00 | $91.93 | $89.01 | $80.00 | $92.00 | |
| 13 | 40604062 | HMA SC IL-9.5 D N70 | 2,510 | TON | $94.34 | $101.00 | $95.00 | $88.00 | $105.16 | $97.91 | $90.00 | $104.75 | |
| 14 | 42001300 | PROTECTIVE COAT | 569 | SQ YD | $0.9900 | $0.0100 | $0.0100 | $0.0100 | $1.00 | $4.47 | $0.1000 | $4.25 | |
| 15 | 42300400 | PCC DRIVEWAY PAVT 8 | 261 | SQ YD | $63.99 | $121.00 | $106.00 | $105.00 | $105.00 | $99.87 | $140.00 | $100.00 | |
| 16 | 42400200 | PC CONC SIDEWALK 5 | 300 | SQ FT | $14.73 | $9.75 | $15.00 | $9.55 | $15.95 | $16.45 | $17.00 | $12.00 | |
| 17 | 42400800 | DETECTABLE WARNINGS | 20 | SQ FT | $50.79 | $25.00 | $30.00 | $40.00 | $33.00 | $59.60 | $50.00 | $30.00 | |
| 18 | 44000100 | PAVEMENT REM | 20,663 | SQ YD | $3.70 | $3.25 | $5.00 | $9.00 | $4.00 | $7.96 | $5.00 | $22.00 | |
| 19 | 44000155 | HMA SURF REM 1 1/2 | 9,216 | SQ YD | $2.05 | $2.60 | $4.00 | $3.00 | $2.00 | $3.34 | $3.50 | $2.40 | |
| 20 | 44000200 | DRIVE PAVEMENT REM | 261 | SQ YD | $31.00 | $15.00 | $25.00 | $10.50 | $33.00 | $10.75 | $20.00 | $28.00 | |
| 21 | 44000500 | COMB CURB GUTTER REM | 212 | FOOT | $12.00 | $7.25 | $21.00 | $6.00 | $18.00 | $6.18 | $10.00 | $17.00 | |
| 22 | 44000600 | SIDEWALK REM | 300 | SQ FT | $2.00 | $2.15 | $11.00 | $2.00 | $5.25 | $2.78 | $4.00 | $3.50 | |
| 23 | 44200970 | CL B PATCH T2 10 | 56 | SQ YD | $229.70 | $175.00 | $487.00 | $212.50 | $225.00 | $259.92 | $320.00 | $160.00 | |
| 24 | 44200974 | CL B PATCH T3 10 | 50 | SQ YD | $225.88 | $150.00 | $487.00 | $212.50 | $225.00 | $259.99 | $320.00 | $158.00 | |
| 25 | 44201713 | CL D PATCH T1 6 | 24 | SQ YD | $99.98 | $60.00 | $88.00 | $100.00 | $62.45 | $138.40 | $100.00 | $79.00 | |
| 26 | 44201717 | CL D PATCH T2 6 | 306 | SQ YD | $63.44 | $30.00 | $88.00 | $50.00 | $62.45 | $82.78 | $50.00 | $79.00 | |
| 27 | 44201721 | CL D PATCH T3 6 | 139 | SQ YD | $53.22 | $30.00 | $88.00 | $50.00 | $62.45 | $82.78 | $50.00 | $79.00 | |
| 28 | 44201723 | CL D PATCH T4 6 | 116 | SQ YD | $50.17 | $30.00 | $88.00 | $50.00 | $62.45 | $82.77 | $50.00 | $79.00 | |
| 29 | 66900200 | NON SPL WASTE DISPOSL | 2,650 | CU YD | $46.72 | $79.00 | $44.00 | $70.00 | $86.29 | $75.00 | $150.00 | $139.00 | |
| 30 | 66900530 | SOIL DISPOSAL ANALY | 4 | EACH | $1,570.00 | $850.00 | $1,650.00 | $1,570.00 | $850.00 | $850.00 | $1,570.00 | $1,290.00 | |
| 31 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,700.00 | $4,200.00 | $3,350.00 | $2,700.00 | $4,200.00 | $4,200.00 | $2,700.00 | $5,100.00 | |
| 32 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $2,000.00 | $500.00 | $1,250.00 | $2,000.00 | $500.00 | $500.00 | $2,000.00 | $500.00 | |
| 33 | 66901006 | REG SUB MON | 4 | CAL DA | $1,000.00 | $1,200.00 | $1,000.00 | $1,000.00 | $700.00 | $700.00 | $1,000.00 | $880.00 | |
| 34 | 67100100 | MOBILIZATION | 1 | L SUM | $74,101.00 | $89,250.00 | $93,500.00 | $95,400.00 | $175,244.10 | $103,789.90 | $220,999.80 | $148,000.00 | |
| 35 | 78000100 | THPL PVT MK LTR & SYM | 19 | SQ FT | $15.00 | $6.00 | $20.65 | $15.00 | $9.38 | $20.65 | $27.00 | $15.00 | |
| 36 | 78000200 | THPL PVT MK LINE 4 | 1,253 | FOOT | $2.50 | $3.00 | $4.05 | $2.50 | $2.35 | $4.05 | $1.35 | $2.50 | |
| 37 | 78000600 | THPL PVT MK LINE 12 | 202 | FOOT | $15.00 | $4.00 | $11.85 | $15.00 | $6.00 | $11.85 | $3.60 | $15.00 |