2022 I80 TREE REMOVAL
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | McGinty Bros., Inc. Low bidder | $683,392 | ||
| 2 | Homer Tree Service, Inc. | $707,456 | +3.5% | |
| 3 | Clean Cut Tree Service, Inc. | $793,485 | +16.1% | |
| 4 | Endrizzi Contracting, Inc | $2,279,060 | +233.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 McGinty Bros., … | #2 Homer Tree Serv… | #3 Clean Cut Tree … | #4 Endrizzi Contra… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X2010350 | TREE REMOV ACRES SPL | 0.75 | ACRE | $25,000.00 | $20,000.00 | $25,000.00 | $92,000.00 | |
| 2 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $25,000.00 | $20,000.00 | $25,000.00 | $55,000.00 | |
| 3 | X7011015 | TR C-PROT EXPRESSWAYS | 1 | L SUM | $60,000.00 | $24,000.00 | $25,000.00 | $65,000.00 | |
| 4 | Z0064800 | SELECTIVE CLEARING | 445 | UNIT | $550.00 | $650.00 | $450.00 | $400.00 | |
| 5 | 20100110 | TREE REMOV 6-15 | 2,629 | UNIT | $28.00 | $29.00 | $35.00 | $245.00 | |
| 6 | 20100210 | TREE REMOV OVER 15 | 1,299 | UNIT | $45.00 | $35.00 | $55.00 | $295.00 | |
| 7 | 20100500 | TREE REMOV ACRES | 11.75 | ACRE | $13,500.00 | $18,000.00 | $17,500.00 | $65,000.00 | |
| 8 | 28000250 | TEMP EROS CONTR SEED | 600 | POUND | $7.00 | $10.00 | $9.00 | $35.00 | |
| 9 | 67100100 | MOBILIZATION | 1 | L SUM | $40,000.00 | $20,000.00 | $150,000.00 | $100,000.00 |