FAP 0305 22 RS2
- Let date
- Friday, September 22, 2023
- Contract
- 62T64 · job page
- District
- District 1
- County
- Mchenry
- Highway
- Limits
- (7.92-Mile) FAP 324: US 14 / Division Street): Crack and Joint Sealing from North of IL 23 to Brink Street. Type of work consists of crack routing, crack filling urethane PMK. Net Length = 41,805-feet (7.92-miles) located within the City of Harvard and unincorporated McHenry County.
- Classification
- Crack routing, crack filling urethane PMK
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Peter Baker & Son Co. Low bidder | $4,282,507 | ||
| 2 | Plote Construction, Inc. | $4,320,103 | +0.9% | |
| 3 | Curran Contracting Company | $6,555,752 | +53.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Peter Baker & S… | #2 Plote Construct… | #3 Curran Contract… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0301242 | PIEZO AXLE SEN CL 2 | 2 | FOOT | $12,151.30 | $15,000.00 | $12,758.87 | |
| 2 | X0326898 | CENTERLN RUM STRIP 16 | 36,260 | FOOT | $0.3100 | $0.5000 | $1.06 | |
| 3 | X2020110 | GRADING & SHAP SHLDRS | 730 | UNIT | $73.50 | $100.00 | $50.00 | |
| 4 | X6700407 | ENGR FLD OFF A D1 | 12 | CAL MO | $3,200.00 | $3,600.00 | $3,000.00 | |
| 5 | X7800815 | HS THPL PM LN 4 | 88,850 | FOOT | $0.2900 | $0.3000 | $0.3000 | |
| 6 | Z0030850 | TEMP INFO SIGNING | 155 | SQ FT | $15.00 | $10.00 | $26.25 | |
| 7 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 8 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 9 | 40600290 | BIT MATLS TACK CT | 60,910 | POUND | $1.00 | $0.0100 | $1.00 | |
| 10 | 40600370 | LONG JOINT SEALANT | 56,575 | FOOT | $2.47 | $3.15 | $3.25 | |
| 11 | 40600400 | MIX CR JTS FLANGEWYS | 205 | TON | $75.00 | $100.00 | $375.00 | |
| 12 | 40600982 | HMA SURF REM BUTT JT | 250 | SQ YD | $1.00 | $75.00 | $25.00 | |
| 13 | 40601005 | HMA REPL OVER PATCH | 2,700 | TON | $50.00 | $50.00 | $160.00 | |
| 14 | 40604062 | HMA SC IL-9.5 D N70 | 11,370 | TON | $87.85 | $110.00 | $120.00 | |
| 15 | 44000155 | HMA SURF REM 1 1/2 | 135,346 | SQ YD | $4.75 | $8.25 | $2.73 | |
| 16 | 44002215 | HMA RM OV PATCH 3 3/4 | 12,850 | SQ YD | $0.5000 | $0.1000 | $36.00 | |
| 17 | 44201798 | CL D PATCH T1 13 | 500 | SQ YD | $75.00 | $40.00 | $240.00 | |
| 18 | 44201803 | CL D PATCH T2 13 | 5,500 | SQ YD | $75.00 | $40.00 | $200.00 | |
| 19 | 44201807 | CL D PATCH T3 13 | 2,850 | SQ YD | $75.00 | $40.00 | $180.00 | |
| 20 | 44201809 | CL D PATCH T4 13 | 4,000 | SQ YD | $75.00 | $40.00 | $165.00 | |
| 21 | 45100100 | CRACK ROUTING (PAVT) | 20,900 | FOOT | $0.0100 | $0.0100 | $0.0900 | |
| 22 | 45100200 | CRACK FILLING | 5,975 | POUND | $3.45 | $5.50 | $4.36 | |
| 23 | 48102100 | AGG WEDGE SHLD TYPE B | 2,130 | TON | $44.25 | $15.00 | $44.00 | |
| 24 | 64200108 | SHOULDER RUM STRIP 8 | 72,520 | FOOT | $0.2100 | $0.2000 | $0.8000 | |
| 25 | 67100100 | MOBILIZATION | 1 | L SUM | $359,973.50 | $245,000.00 | $500,000.00 | |
| 26 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $518,833.00 | $1.00 | $70,000.00 | |
| 27 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $1.00 | $1.00 | $15,000.00 | |
| 28 | 70102622 | TR CONT & PROT 701502 | 1 | L SUM | $1.00 | $403,511.00 | $15,000.00 | |
| 29 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.00 | $1,000.00 | |
| 30 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1.00 | $1.00 | $1,000.00 | |
| 31 | 70300100 | SHORT TERM PAVT MKING | 15,760 | FOOT | $0.0100 | $0.1000 | $0.7000 | |
| 32 | 70300150 | SHRT TRM PAVT MK REM | 5,225 | SQ FT | $1.85 | $0.1000 | $2.50 | |
| 33 | 70300211 | TEMP PVT MK LTR & SYM PAINT | 345 | SQ FT | $0.0100 | $0.0100 | $1.42 | |
| 34 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 42,960 | FOOT | $0.0100 | $0.0100 | $0.4700 | |
| 35 | 70300241 | TEMP PVT MK LINE 6 - PAINT | 1,000 | FOOT | $0.0100 | $0.0100 | $0.7400 | |
| 36 | 70300251 | TEMP PVT MK LINE 8 - PAINT | 530 | FOOT | $0.0100 | $0.0100 | $0.9500 | |
| 37 | 70300261 | TEMP PVT MK LINE 12 - PAINT | 450 | FOOT | $0.0100 | $0.0100 | $1.42 | |
| 38 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 245 | FOOT | $0.0100 | $0.0100 | $2.84 | |
| 39 | 70306120 | TEMP PVT MK L4 T3 TAPE | 39,540 | FOOT | $0.0100 | $0.0100 | $1.05 | |
| 40 | 78000100 | THPL PVT MK LTR & SYM | 345 | SQ FT | $4.22 | $4.22 | $4.43 | |
| 41 | 78000200 | THPL PVT MK LINE 4 | 42,960 | FOOT | $0.6800 | $0.6800 | $0.7100 | |
| 42 | 78000400 | THPL PVT MK LINE 6 | 1,000 | FOOT | $0.8500 | $0.8500 | $0.8900 | |
| 43 | 78000500 | THPL PVT MK LINE 8 | 530 | FOOT | $1.45 | $1.45 | $1.52 | |
| 44 | 78000600 | THPL PVT MK LINE 12 | 450 | FOOT | $3.96 | $3.96 | $4.16 | |
| 45 | 78000650 | THPL PVT MK LINE 24 | 245 | FOOT | $5.22 | $5.22 | $5.48 | |
| 46 | 78009000 | MOD URETH PM LTR-SYM | 1,410 | SQ FT | $5.05 | $5.05 | $5.30 | |
| 47 | 78009004 | MOD URETH PM LINE 4 | 27,120 | FOOT | $0.6500 | $0.6500 | $0.6800 | |
| 48 | 78009006 | MOD URETH PM LINE 6 | 5,760 | FOOT | $0.9500 | $0.9500 | $1.00 | |
| 49 | 78009008 | MOD URETH PM LINE 8 | 265 | FOOT | $1.22 | $1.22 | $1.28 | |
| 50 | 78009012 | MOD URETH PM LINE 12 | 540 | FOOT | $3.45 | $3.45 | $3.62 | |
| 51 | 78009024 | MOD URETH PM LINE 24 | 570 | FOOT | $5.05 | $5.05 | $5.30 | |
| 52 | 78100100 | RAISED REFL PAVT MKR | 915 | EACH | $38.00 | $38.00 | $39.90 | |
| 53 | 78300200 | RAISED REF PVT MK REM | 915 | EACH | $0.0100 | $15.00 | $18.71 | |
| 54 | 78300202 | PAVMT MRKG REM WTR BL | 415 | SQ FT | $7.00 | $11.00 | $10.50 | |
| 55 | 88600100 | DET LOOP T1 | 300 | FOOT | $32.10 | $33.00 | $33.71 | |
| 56 | 88600600 | DET LOOP REPL | 555 | FOOT | $32.40 | $35.00 | $33.71 |