2020-156-RS&SW
- Let date
- Friday, March 11, 2022
- Contract
- 62M44 · job page
- District
- District 1
- County
- Cook
- Highway
- Limits
- (1.51-Mile) Standard overlay project consisting of hot-mix asphalt surface removal, pavement patching, hot-mix asphalt resurfacing, detector loop replacement, ADA improvements and thermoplastic pavement marking on Ogden Avenue from Kedzie Avenue to Taylor Street in the City of Chicago.
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Bigane Paving Company Low bidder | $1,996,353 | ||
| 2 | MAT Construction Leasing, Inc. | $2,065,889 | +3.5% | |
| 3 | K-Five Construction Corporation | $2,099,795 | +5.2% | |
| 4 | Gallagher Asphalt Corporation | $2,273,437 | +13.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Bigane Paving C… | #2 MAT Constructio… | #3 K-Five Construc… | #4 Gallagher Aspha… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $3,500.00 | $3,500.00 | $13,648.25 | $1,200.00 | |
| 2 | X4240800 | DETECTABLE WARN SPL | 43 | SQ FT | $34.00 | $35.00 | $35.00 | $40.00 | |
| 3 | X4400501 | COMB C&G REMOV REPL < = 10FT | 32 | FOOT | $55.00 | $55.00 | $55.00 | $62.00 | |
| 4 | X5537800 | SS CLEANED 12 | 88 | FOOT | $2.00 | $3.00 | $3.00 | $3.50 | |
| 5 | X6700407 | ENGR FLD OFF A D1 | 12 | CAL MO | $3,000.00 | $3,000.00 | $3,800.00 | $500.00 | |
| 6 | Z0004562 | COMB C C&G REM & REPL | 3,863 | FOOT | $35.00 | $35.00 | $35.00 | $40.00 | |
| 7 | Z0018500 | DRAINAGE STR CLEANED | 7 | EACH | $600.00 | $550.00 | $550.00 | $630.00 | |
| 8 | Z0030850 | TEMP INFO SIGNING | 51.4 | SQ FT | $20.00 | $15.00 | $18.00 | $17.00 | |
| 9 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $15,000.00 | $12,000.00 | $3,450.00 | $16,000.00 | |
| 10 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 11 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 12 | 20200100 | EARTH EXCAVATION | 7 | CU YD | $75.00 | $50.00 | $75.00 | $85.79 | |
| 13 | 21101615 | TOPSOIL F & P 4 | 644 | SQ YD | $9.00 | $10.00 | $7.00 | $8.00 | |
| 14 | 25200110 | SODDING SALT TOLERANT | 644 | SQ YD | $20.00 | $14.00 | $10.00 | $11.50 | |
| 15 | 40600290 | BIT MATLS TACK CT | 55,230 | POUND | $0.8000 | $0.8200 | $0.0100 | $0.0100 | |
| 16 | 40600370 | LONG JOINT SEALANT | 18,645 | FOOT | $2.00 | $2.09 | $2.30 | $2.40 | |
| 17 | 40600400 | MIX CR JTS FLANGEWYS | 123 | TON | $300.00 | $150.00 | $50.00 | $50.00 | |
| 18 | 40600982 | HMA SURF REM BUTT JT | 795 | SQ YD | $40.00 | $3.30 | $4.00 | $26.50 | |
| 19 | 40603200 | P HMA BC IL-4.75 N50 | 3,376 | TON | $119.00 | $126.00 | $135.00 | $135.00 | |
| 20 | 40604062 | HMA SC IL-9.5 D N70 | 6,873 | TON | $82.00 | $95.00 | $100.00 | $97.00 | |
| 21 | 42001300 | PROTECTIVE COAT | 761 | SQ YD | $2.00 | $2.00 | $2.00 | $2.30 | |
| 22 | 42400200 | PC CONC SIDEWALK 5 | 85 | SQ FT | $12.00 | $12.00 | $12.00 | $13.70 | |
| 23 | 44000158 | HMA SURF REM 2 1/4 | 81,821 | SQ YD | $2.75 | $3.30 | $4.50 | $4.20 | |
| 24 | 44000600 | SIDEWALK REM | 85 | SQ FT | $2.00 | $2.00 | $2.00 | $2.40 | |
| 25 | 44003510 | MEDIAN REMOVAL (PD) | 2,435 | SQ FT | $12.00 | $4.50 | $0.5000 | $2.80 | |
| 26 | 44201803 | CL D PATCH T2 13 | 654 | SQ YD | $115.00 | $125.00 | $42.00 | $178.00 | |
| 27 | 44201807 | CL D PATCH T3 13 | 409 | SQ YD | $115.00 | $124.50 | $42.00 | $169.00 | |
| 28 | 44201809 | CL D PATCH T4 13 | 573 | SQ YD | $115.00 | $124.00 | $42.00 | $149.00 | |
| 29 | 60300305 | FR & LIDS ADJUST | 7 | EACH | $700.00 | $600.00 | $700.00 | $800.00 | |
| 30 | 66900200 | NON SPL WASTE DISPOSL | 7 | CU YD | $85.00 | $80.00 | $150.00 | $300.00 | |
| 31 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $1,950.00 | $1,450.00 | $1,700.00 | $2,250.00 | |
| 32 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,300.00 | $2,800.00 | $6,500.00 | $2,630.00 | |
| 33 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $2,000.00 | $2,200.00 | $500.00 | $2,290.00 | |
| 34 | 66901006 | REG SUB MON | 15 | CAL DA | $980.00 | $900.00 | $400.00 | $1,120.00 | |
| 35 | 67100100 | MOBILIZATION | 1 | L SUM | $100,000.00 | $80,000.00 | $126,000.00 | $130,000.00 | |
| 36 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $100.00 | $12,800.00 | $1.00 | $750.00 | |
| 37 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $100.00 | $1.00 | $25,000.00 | $4,500.00 | |
| 38 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $23,000.00 | $1.00 | $6,500.00 | $4,500.00 | |
| 39 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $100.00 | $1.00 | $1.00 | $4,500.00 | |
| 40 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1,500.00 | $1.00 | $1.00 | $660.00 | |
| 41 | 70300100 | SHORT TERM PAVT MKING | 3,498 | FOOT | $0.5000 | $0.8000 | $1.00 | $1.00 | |
| 42 | 70300150 | SHRT TRM PAVT MK REM | 583 | SQ FT | $1.00 | $1.00 | $2.00 | $3.00 | |
| 43 | 70300211 | TEMP PVT MK LTR & SYM PAINT | 713 | SQ FT | $1.00 | $1.50 | $3.55 | $2.00 | |
| 44 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 18,948 | FOOT | $0.1000 | $0.3000 | $0.3000 | $0.3500 | |
| 45 | 70300241 | TEMP PVT MK LINE 6 - PAINT | 2,970 | FOOT | $0.2000 | $0.4500 | $0.3000 | $0.5500 | |
| 46 | 70300261 | TEMP PVT MK LINE 12 - PAINT | 4,756 | FOOT | $0.2500 | $0.8000 | $0.3000 | $1.10 | |
| 47 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 1,057 | FOOT | $1.00 | $1.50 | $3.55 | $2.10 | |
| 48 | 70306120 | TEMP PVT MK L4 T3 TAPE | 1,749 | FOOT | $1.50 | $0.9500 | $1.25 | $1.40 | |
| 49 | 78000100 | THPL PVT MK LTR & SYM | 713 | SQ FT | $6.00 | $9.00 | $3.50 | $4.00 | |
| 50 | 78000200 | THPL PVT MK LINE 4 | 18,948 | FOOT | $0.6500 | $0.5000 | $0.6000 | $0.7000 | |
| 51 | 78000400 | THPL PVT MK LINE 6 | 2,970 | FOOT | $1.20 | $1.05 | $1.10 | $1.30 | |
| 52 | 78000600 | THPL PVT MK LINE 12 | 4,756 | FOOT | $3.25 | $1.05 | $2.25 | $2.60 | |
| 53 | 78000650 | THPL PVT MK LINE 24 | 1,057 | FOOT | $6.00 | $9.00 | $3.50 | $4.00 | |
| 54 | 88600600 | DET LOOP REPL | 396 | FOOT | $17.00 | $17.00 | $17.00 | $20.00 |