2020-116-RS
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Bigane Paving Company Low bidder | $1,172,657 | ||
| 2 | Plote Construction, Inc. | $1,345,321 | +14.7% | |
| 3 | Builders Paving, LLC | $1,378,000 | +17.5% | |
| 4 | K-Five Construction Corporation | $1,382,985 | +17.9% | |
| 5 | Arrow Road Construction Co. | $1,435,812 | +22.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Bigane Paving C… | #2 Plote Construct… | #3 Builders Paving… | #4 K-Five Construc… | #5 Arrow Road Cons… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $2,745.00 | $5,000.00 | $2,500.00 | $1,200.00 | $2,440.00 | |
| 2 | X0327611 | REM & REIN BRIC PAVER | 120 | SQ FT | $30.00 | $15.00 | $30.00 | $30.00 | $30.00 | |
| 3 | X4240800 | DETECTABLE WARN SPL | 250 | SQ FT | $35.00 | $32.00 | $32.00 | $32.00 | $35.00 | |
| 4 | X4400501 | COMB C&G REMOV REPL < = 10FT | 728 | FOOT | $40.00 | $35.00 | $37.50 | $35.00 | $40.00 | |
| 5 | X5537800 | SS CLEANED 12 | 200 | FOOT | $2.00 | $3.00 | $3.00 | $3.00 | $3.00 | |
| 6 | X6030310 | FR & LIDS ADJUST SPL | 77 | EACH | $675.00 | $700.00 | $700.00 | $700.00 | $700.00 | |
| 7 | X7011015 | TR C-PROT EXPRESSWAYS | 1 | L SUM | $600.00 | $1,200.00 | $1,000.00 | $1.00 | $7,175.00 | |
| 8 | Z0001110 | GAS VALVE ADJUSTED | 12 | EACH | $400.00 | $350.00 | $350.00 | $350.00 | $350.00 | |
| 9 | Z0004562 | COMB C C&G REM & REPL | 728 | FOOT | $36.00 | $35.00 | $37.50 | $35.00 | $36.00 | |
| 10 | Z0018500 | DRAINAGE STR CLEANED | 79 | EACH | $400.00 | $365.00 | $365.00 | $365.00 | $330.00 | |
| 11 | Z0030850 | TEMP INFO SIGNING | 52 | SQ FT | $15.00 | $16.00 | $18.00 | $15.00 | $16.00 | |
| 12 | Z0033700 | LONG JOINT SEALANT | 14,381 | FOOT | $2.00 | $2.15 | $2.25 | $2.15 | $2.30 | |
| 13 | 20200100 | EARTH EXCAVATION | 33 | CU YD | $65.00 | $60.00 | $60.00 | $60.00 | $75.00 | |
| 14 | 21101615 | TOPSOIL F & P 4 | 200 | SQ YD | $6.00 | $7.00 | $5.98 | $5.98 | $6.00 | |
| 15 | 25200110 | SODDING SALT TOLERANT | 200 | SQ YD | $16.00 | $13.00 | $16.00 | $16.00 | $16.00 | |
| 16 | 40600290 | BIT MATLS TACK CT | 23,675 | POUND | $0.9000 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 17 | 40600982 | HMA SURF REM BUTT JT | 1,002 | SQ YD | $20.00 | $15.00 | $35.00 | $0.0100 | $6.10 | |
| 18 | 40604172 | P HMA SC IL-9.5 E N70 | 5,156 | TON | $82.00 | $100.00 | $84.00 | $115.00 | $94.50 | |
| 19 | 42001300 | PROTECTIVE COAT | 691 | SQ YD | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 20 | 42300400 | PCC DRIVEWAY PAVT 8 | 67 | SQ YD | $85.00 | $65.00 | $65.00 | $65.00 | $72.00 | |
| 21 | 42400200 | PC CONC SIDEWALK 5 | 2,475 | SQ FT | $8.00 | $7.50 | $7.50 | $7.50 | $7.50 | |
| 22 | 42400410 | PC CONC SIDEWALK 8 | 825 | SQ FT | $10.00 | $8.50 | $8.50 | $8.50 | $9.00 | |
| 23 | 44000156 | HMA SURF REM 1 3/4 | 52,611 | SQ YD | $2.70 | $1.75 | $3.45 | $5.00 | $5.20 | |
| 24 | 44000200 | DRIVE PAVEMENT REM | 67 | SQ YD | $25.00 | $22.00 | $22.00 | $22.00 | $20.00 | |
| 25 | 44000600 | SIDEWALK REM | 3,300 | SQ FT | $2.50 | $2.50 | $2.50 | $2.50 | $2.20 | |
| 26 | 44201773 | CL D PATCH T1 11 | 25 | SQ YD | $95.00 | $100.00 | $90.00 | $100.00 | $30.00 | |
| 27 | 44201777 | CL D PATCH T2 11 | 898 | SQ YD | $50.00 | $70.00 | $90.00 | $27.00 | $30.00 | |
| 28 | 44201781 | CL D PATCH T3 11 | 250 | SQ YD | $50.00 | $65.00 | $90.00 | $25.00 | $30.00 | |
| 29 | 44201783 | CL D PATCH T4 11 | 403 | SQ YD | $50.00 | $60.00 | $90.00 | $23.00 | $30.00 | |
| 30 | 60252800 | CB RECONST | 2 | EACH | $2,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,250.00 | |
| 31 | 60257900 | MAN RECONST | 5 | EACH | $550.00 | $1,300.00 | $1,300.00 | $1,300.00 | $1,250.00 | |
| 32 | 60300105 | FR & GRATES ADJUST | 5 | EACH | $450.00 | $400.00 | $400.00 | $400.00 | $350.00 | |
| 33 | 60300305 | FR & LIDS ADJUST | 15 | EACH | $400.00 | $450.00 | $450.00 | $450.00 | $350.00 | |
| 34 | 60406000 | FR & LIDS T1 OL | 6 | EACH | $350.00 | $400.00 | $400.00 | $400.00 | $400.00 | |
| 35 | 60406100 | FR & LIDS T1 CL | 48 | EACH | $350.00 | $400.00 | $400.00 | $400.00 | $400.00 | |
| 36 | 66900200 | NON SPL WASTE DISPOSL | 33 | CU YD | $120.00 | $152.00 | $100.00 | $100.00 | $110.00 | |
| 37 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $1,500.00 | $1,700.00 | $2,000.00 | $1,950.00 | $1,900.00 | |
| 38 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $3,800.00 | $2,850.00 | $2,500.00 | $2,950.00 | $3,400.00 | |
| 39 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $300.00 | $1,200.00 | $2,500.00 | $900.00 | $500.00 | |
| 40 | 66901006 | REG SUB MON | 5 | CAL DA | $590.00 | $700.00 | $750.00 | $680.00 | $690.00 | |
| 41 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $3,000.00 | $3,800.00 | $2,450.00 | $3,300.00 | $2,500.00 | |
| 42 | 67100100 | MOBILIZATION | 1 | L SUM | $70,000.00 | $82,300.00 | $162,459.00 | $83,000.00 | $231,000.00 | |
| 43 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $28,000.00 | $1.00 | $25,373.10 | $22,000.00 | $1.00 | |
| 44 | 70102634 | TR CONT & PROT 701611 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 45 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 46 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1.00 | $135,300.00 | $5,000.00 | $1.00 | $9,600.00 | |
| 47 | 70200100 | NIGHT WORK ZONE LIGHT | 1 | L SUM | $2,500.00 | $3,000.00 | $1,000.00 | $1,000.00 | $2,750.00 | |
| 48 | 70300100 | SHORT TERM PAVT MKING | 2,057 | FOOT | $1.00 | $1.50 | $2.30 | $2.00 | $1.00 | |
| 49 | 70300210 | TEMP PVT MK LTR & SYM | 685 | SQ FT | $1.25 | $0.5000 | $1.25 | $0.0100 | $0.0100 | |
| 50 | 70300220 | TEMP PVT MK LINE 4 | 5,868 | FOOT | $0.2000 | $0.2500 | $0.2500 | $0.0100 | $0.0100 | |
| 51 | 70300240 | TEMP PVT MK LINE 6 | 2,074 | FOOT | $0.3000 | $0.3500 | $0.4500 | $0.0100 | $0.0100 | |
| 52 | 70300280 | TEMP PVT MK LINE 24 | 5,510 | FOOT | $1.20 | $0.7500 | $1.25 | $0.0100 | $0.0100 | |
| 53 | 70300520 | PAVT MARK TAPE T3 4 | 1,738 | FOOT | $0.9000 | $0.0100 | $0.7500 | $1.00 | $1.00 | |
| 54 | 78000100 | THPL PVT MK LTR & SYM | 271 | SQ FT | $4.25 | $4.50 | $4.50 | $4.25 | $4.25 | |
| 55 | 78000200 | THPL PVT MK LINE 4 | 5,868 | FOOT | $0.5500 | $0.7500 | $0.6000 | $0.5500 | $0.5500 | |
| 56 | 78000400 | THPL PVT MK LINE 6 | 2,074 | FOOT | $1.10 | $1.20 | $1.00 | $1.07 | $1.07 | |
| 57 | 78000650 | THPL PVT MK LINE 24 | 5,510 | FOOT | $4.25 | $4.50 | $5.25 | $4.25 | $4.25 | |
| 58 | 78300200 | RAISED REF PVT MK REM | 115 | EACH | $8.00 | $22.00 | $12.50 | $20.00 | $12.00 | |
| 59 | 85000200 | MAIN EX TR SIG INSTAL | 5 | EACH | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | |
| 60 | 88600600 | DET LOOP REPL | 180 | FOOT | $25.00 | $25.00 | $25.00 | $25.00 | $25.00 |