2020-101-RS&SW
- Let date
- Friday, January 15, 2021
- Contract
- 62L79 · job page
- District
- District 1
- County
- Cook
- Highway
- Limits
- (5.98-Mile) SMART Overlay and ADA Pedestrian Ramps project on IL-43 (FAP 348) from north of US 6 (159th St) to north of 111th St. Located within the Villages of Orland Park, Worth and Palos Heights in Cook County.
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Gallagher Asphalt Corporation Low bidder | $4,409,859 | ||
| 2 | K-Five Construction Corporation | $4,580,463 | +3.9% | |
| 3 | D. Construction, Inc. | $4,595,000 | +4.2% | |
| 4 | Iroquois Paving Corporation | $4,626,450 | +4.9% | |
| 5 | Austin Tyler Construction, Inc. | $4,916,661 | +11.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Gallagher Aspha… | #2 K-Five Construc… | #3 D. Construction… | #4 Iroquois Paving… | #5 Austin Tyler Co… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | K0026700 | TREE CARE | 121 | EACH | $90.00 | $100.00 | $250.00 | $100.00 | $135.00 | |
| 2 | K0029618 | WEED CONT BROADLF TRF | 30 | GALLON | $1,100.00 | $300.00 | $643.50 | $80.00 | $82.00 | |
| 3 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $19,600.00 | $25,000.00 | $20,000.00 | $45,000.00 | $17,000.00 | |
| 4 | X0325222 | WEED CONT BASAL TRTMT | 30 | GALLON | $880.00 | $350.00 | $755.70 | $80.00 | $82.00 | |
| 5 | X0326681 | REM & RE ERCT BOULDER | 1 | L SUM | $1,392.00 | $1,000.00 | $3,500.00 | $1,500.00 | $3,100.00 | |
| 6 | X0327611 | REM & REIN BRIC PAVER | 125 | SQ FT | $22.00 | $25.00 | $9.30 | $40.00 | $18.00 | |
| 7 | X4240800 | DETECTABLE WARN SPL | 200 | SQ FT | $37.00 | $35.00 | $35.20 | $60.00 | $67.00 | |
| 8 | X4400501 | COMB C&G REMOV REPL < = 10FT | 1,227 | FOOT | $42.10 | $40.00 | $48.40 | $72.50 | $75.00 | |
| 9 | X4402020 | CONC MEDIAN SURF REM | 138,808 | SQ FT | $0.5200 | $0.5000 | $1.00 | $2.15 | $1.80 | |
| 10 | X5537800 | SS CLEANED 12 | 2,100 | FOOT | $2.50 | $2.50 | $2.75 | $2.00 | $2.25 | |
| 11 | X6026624 | VALVE BOX ADJ SPL | 5 | EACH | $660.00 | $660.00 | $400.00 | $850.00 | $875.00 | |
| 12 | X6030310 | FR & LIDS ADJUST SPL | 25 | EACH | $950.00 | $950.00 | $650.00 | $950.00 | $1,440.00 | |
| 13 | X7030005 | TEMP PAVT MKING REMOV | 50,869 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 14 | Z0004562 | COMB C C&G REM & REPL | 3,202 | FOOT | $37.00 | $35.00 | $46.20 | $58.00 | $61.00 | |
| 15 | Z0018500 | DRAINAGE STR CLEANED | 346 | EACH | $265.00 | $265.00 | $290.00 | $350.00 | $355.00 | |
| 16 | Z0030850 | TEMP INFO SIGNING | 52 | SQ FT | $18.00 | $18.00 | $25.00 | $18.00 | $19.00 | |
| 17 | Z0033700 | LONG JOINT SEALANT | 65,974 | FOOT | $2.70 | $3.50 | $2.35 | $2.50 | $2.45 | |
| 18 | Z0064800 | SELECTIVE CLEARING | 135 | UNIT | $406.00 | $340.00 | $375.00 | $340.00 | $47.00 | |
| 19 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 20 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | |
| 21 | 20100110 | TREE REMOV 6-15 | 55 | UNIT | $16.20 | $15.00 | $16.50 | $15.00 | $15.00 | |
| 22 | 20100210 | TREE REMOV OVER 15 | 60 | UNIT | $19.45 | $18.00 | $19.80 | $18.00 | $18.00 | |
| 23 | 20101300 | TREE PRUN 1-10 | 10 | EACH | $43.25 | $40.00 | $44.00 | $40.00 | $41.00 | |
| 24 | 20101350 | TREE PRUN OVER 10 | 20 | EACH | $87.00 | $80.00 | $88.00 | $80.00 | $81.00 | |
| 25 | 20200100 | EARTH EXCAVATION | 141 | CU YD | $47.30 | $100.00 | $55.00 | $78.00 | $60.00 | |
| 26 | 20201200 | REM & DISP UNS MATL | 857 | CU YD | $0.0100 | $40.00 | $30.00 | $0.0100 | $147.00 | |
| 27 | 21101600 | TOPSOIL F & P VAR DP | 17,389 | SQ YD | $7.00 | $6.00 | $7.00 | $6.12 | $5.65 | |
| 28 | 21101615 | TOPSOIL F & P 4 | 1,717 | SQ YD | $6.00 | $4.50 | $5.23 | $6.12 | $6.20 | |
| 29 | 25000115 | SEEDING CL 1B | 0.4 | ACRE | $2,318.00 | $3,400.00 | $3,300.00 | $3,400.00 | $6,000.00 | |
| 30 | 25000210 | SEEDING CL 2A | 3.2 | ACRE | $2,417.00 | $2,900.00 | $3,300.00 | $2,900.00 | $5,000.00 | |
| 31 | 25000400 | NITROGEN FERT NUTR | 251 | POUND | $3.00 | $4.00 | $2.20 | $4.00 | $3.00 | |
| 32 | 25000500 | PHOSPHORUS FERT NUTR | 251 | POUND | $3.00 | $4.00 | $2.20 | $4.00 | $3.00 | |
| 33 | 25000600 | POTASSIUM FERT NUTR | 251 | POUND | $3.00 | $4.00 | $2.20 | $4.00 | $3.00 | |
| 34 | 25000750 | MOWING | 13 | ACRE | $350.00 | $450.00 | $605.00 | $450.00 | $400.00 | |
| 35 | 25003115 | INTERSEED CL 1B | 2.8 | ACRE | $674.00 | $3,200.00 | $3,300.00 | $3,200.00 | $5,000.00 | |
| 36 | 25100115 | MULCH METHOD 2 | 0.4 | ACRE | $1,700.00 | $3,200.00 | $4,620.00 | $3,200.00 | $5,000.00 | |
| 37 | 25100630 | EROSION CONTR BLANKET | 15,424 | SQ YD | $0.8000 | $1.00 | $1.38 | $1.00 | $1.65 | |
| 38 | 25200110 | SODDING SALT TOLERANT | 1,957 | SQ YD | $7.00 | $7.00 | $12.28 | $7.00 | $7.25 | |
| 39 | 25200200 | SUPPLE WATERING | 85 | UNIT | $0.0100 | $50.00 | $0.0100 | $50.00 | $1.00 | |
| 40 | 40600290 | BIT MATLS TACK CT | 98,837 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 41 | 40600400 | MIX CR JTS FLANGEWYS | 330 | TON | $50.00 | $50.00 | $50.00 | $0.0100 | $100.00 | |
| 42 | 40600982 | HMA SURF REM BUTT JT | 1,811 | SQ YD | $13.30 | $0.0100 | $0.0100 | $7.25 | $0.0100 | |
| 43 | 40601005 | HMA REPL OVER PATCH | 215 | TON | $101.00 | $147.00 | $0.0100 | $125.00 | $117.00 | |
| 44 | 40605026 | P HMA SC SMA 9.5 F N80 | 21,525 | TON | $91.00 | $95.60 | $86.00 | $79.00 | $84.00 | |
| 45 | 42001300 | PROTECTIVE COAT | 2,748 | SQ YD | $1.05 | $1.00 | $1.10 | $1.00 | $1.50 | |
| 46 | 42400200 | PC CONC SIDEWALK 5 | 12,410 | SQ FT | $6.35 | $6.00 | $10.00 | $12.00 | $10.25 | |
| 47 | 42400800 | DETECTABLE WARNINGS | 1,206 | SQ FT | $31.55 | $30.00 | $33.00 | $30.00 | $26.00 | |
| 48 | 44000100 | PAVEMENT REM | 29 | SQ YD | $21.10 | $20.00 | $26.40 | $36.00 | $56.00 | |
| 49 | 44000156 | HMA SURF REM 1 3/4 | 219,636 | SQ YD | $1.70 | $1.75 | $1.45 | $1.95 | $2.40 | |
| 50 | 44000200 | DRIVE PAVEMENT REM | 9 | SQ YD | $21.10 | $50.00 | $24.20 | $36.00 | $52.00 | |
| 51 | 44000600 | SIDEWALK REM | 12,475 | SQ FT | $2.10 | $2.00 | $2.42 | $2.25 | $3.65 | |
| 52 | 44002212 | HMA RM OV PATCH 3 | 1,275 | SQ YD | $11.00 | $10.00 | $0.0100 | $9.75 | $14.50 | |
| 53 | 44201761 | CL D PATCH T1 10 | 6 | SQ YD | $152.00 | $200.00 | $125.00 | $185.00 | $109.00 | |
| 54 | 44201765 | CL D PATCH T2 10 | 1,097 | SQ YD | $101.00 | $125.00 | $70.00 | $100.00 | $99.00 | |
| 55 | 44201769 | CL D PATCH T3 10 | 200 | SQ YD | $92.00 | $100.00 | $70.00 | $82.00 | $89.00 | |
| 56 | 44201771 | CL D PATCH T4 10 | 141 | SQ YD | $84.00 | $100.00 | $70.00 | $85.00 | $79.00 | |
| 57 | 60250200 | CB ADJUST | 1 | EACH | $350.00 | $350.00 | $575.00 | $510.00 | $420.00 | |
| 58 | 60250400 | CB ADJ NEW T1F OL | 2 | EACH | $800.00 | $800.00 | $800.00 | $795.00 | $580.00 | |
| 59 | 60252800 | CB RECONST | 1 | EACH | $1,200.00 | $1,200.00 | $1,000.00 | $2,200.00 | $3,000.00 | |
| 60 | 60255500 | MAN ADJUST | 5 | EACH | $500.00 | $500.00 | $575.00 | $775.00 | $470.00 | |
| 61 | 60257900 | MAN RECONST | 1 | EACH | $1,300.00 | $1,300.00 | $1,500.00 | $2,450.00 | $3,000.00 | |
| 62 | 60260100 | INLETS ADJUST | 1 | EACH | $350.00 | $350.00 | $650.00 | $510.00 | $340.00 | |
| 63 | 60266600 | VALVE BOX ADJ | 10 | EACH | $250.00 | $250.00 | $650.00 | $415.00 | $310.00 | |
| 64 | 60300105 | FR & GRATES ADJUST | 37 | EACH | $380.00 | $380.00 | $650.00 | $525.00 | $320.00 | |
| 65 | 60300305 | FR & LIDS ADJUST | 67 | EACH | $360.00 | $360.00 | $650.00 | $450.00 | $470.00 | |
| 66 | 60404950 | FR & GRATES T24 | 5 | EACH | $400.00 | $400.00 | $500.00 | $510.00 | $515.00 | |
| 67 | 60406000 | FR & LIDS T1 OL | 2 | EACH | $390.00 | $390.00 | $400.00 | $575.00 | $360.00 | |
| 68 | 66900200 | NON SPL WASTE DISPOSL | 141 | CU YD | $73.00 | $20.00 | $85.00 | $0.0100 | $150.00 | |
| 69 | 66900530 | SOIL DISPOSAL ANALY | 5 | EACH | $1,850.00 | $1,250.00 | $1,485.00 | $1,425.00 | $1,450.00 | |
| 70 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,950.00 | $2,750.00 | $2,750.00 | $40,000.00 | $3,100.00 | |
| 71 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $900.00 | $2,500.00 | $2,750.00 | $40,000.00 | $2,300.00 | |
| 72 | 66901006 | REG SUB MON | 15 | CAL DA | $680.00 | $750.00 | $990.00 | $925.00 | $950.00 | |
| 73 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $1,500.00 | $3,300.00 | $4,000.00 | $2,750.00 | $3,000.00 | |
| 74 | 67100100 | MOBILIZATION | 1 | L SUM | $264,000.00 | $270,000.00 | $124,183.34 | $272,000.00 | $294,000.00 | |
| 75 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $79,400.00 | $35,640.00 | $417,000.00 | $30,000.00 | $50,000.00 | |
| 76 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $1.00 | $5,000.00 | $0.0100 | $10,000.00 | $7,100.00 | |
| 77 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $5,000.00 | $0.0100 | $10,000.00 | $7,100.00 | |
| 78 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $4,000.00 | $26,000.00 | $0.0100 | $40,000.00 | $50,000.00 | |
| 79 | 70300100 | SHORT TERM PAVT MKING | 16,811 | FOOT | $0.9000 | $1.00 | $0.7500 | $0.0100 | $0.0100 | |
| 80 | 70300150 | SHRT TRM PAVT MK REM | 5,604 | SQ FT | $0.0100 | $2.00 | $0.0100 | $0.0100 | $0.0100 | |
| 81 | 70300210 | TEMP PVT MK LTR & SYM | 2,959 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 82 | 70300220 | TEMP PVT MK LINE 4 | 95,200 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 83 | 70300240 | TEMP PVT MK LINE 6 | 15,925 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 84 | 70300250 | TEMP PVT MK LINE 8 | 2,719 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 85 | 70300260 | TEMP PVT MK LINE 12 | 4,396 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 86 | 70300280 | TEMP PVT MK LINE 24 | 2,482 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 87 | 70300520 | PAVT MARK TAPE T3 4 | 8,406 | FOOT | $4.50 | $1.25 | $0.0100 | $0.0100 | $0.0100 | |
| 88 | 72400310 | REMOV SIGN PANEL T1 | 36 | SQ FT | $10.00 | $10.00 | $100.00 | $10.00 | $10.00 | |
| 89 | 72400710 | RELOC SIGN PANEL T1 | 36 | SQ FT | $10.00 | $15.00 | $100.00 | $15.00 | $15.00 | |
| 90 | 78000100 | THPL PVT MK LTR & SYM | 2,959 | SQ FT | $3.75 | $4.00 | $4.13 | $3.75 | $4.75 | |
| 91 | 78000200 | THPL PVT MK LINE 4 | 95,200 | FOOT | $0.5000 | $0.5000 | $0.5500 | $0.5000 | $0.6000 | |
| 92 | 78000400 | THPL PVT MK LINE 6 | 15,925 | FOOT | $0.7000 | $0.7500 | $0.7700 | $0.7000 | $1.10 | |
| 93 | 78000500 | THPL PVT MK LINE 8 | 2,719 | FOOT | $1.00 | $1.00 | $1.10 | $1.00 | $1.35 | |
| 94 | 78000600 | THPL PVT MK LINE 12 | 4,396 | FOOT | $1.40 | $1.50 | $1.54 | $1.40 | $2.35 | |
| 95 | 78000650 | THPL PVT MK LINE 24 | 2,482 | FOOT | $4.00 | $4.00 | $4.40 | $4.00 | $5.00 | |
| 96 | 78008230 | POLYUREA PM T1 LN 6 | 5 | FOOT | $100.00 | $112.50 | $110.00 | $100.00 | $125.00 | |
| 97 | 78008250 | POLYUREA PM T1 LN 12 | 6 | FOOT | $200.00 | $225.00 | $220.00 | $200.00 | $125.00 | |
| 98 | 78100100 | RAISED REFL PAVT MKR | 2,460 | EACH | $19.50 | $22.00 | $21.45 | $19.50 | $26.00 | |
| 99 | 78300200 | RAISED REF PVT MK REM | 2,460 | EACH | $7.00 | $10.00 | $9.00 | $0.0100 | $0.0100 | |
| 100 | 85000200 | MAIN EX TR SIG INSTAL | 8 | EACH | $819.00 | $2,100.00 | $330.00 | $2,100.00 | $1,400.00 | |
| 101 | 88600600 | DET LOOP REPL | 7,486 | FOOT | $18.30 | $16.00 | $19.75 | $16.00 | $16.00 | |
| 102 | 89500400 | RELOC EX PED PUSH-BUT | 22 | EACH | $103.00 | $405.00 | $55.00 | $405.00 | $435.00 | |
| 103 | 89502376 | REBUILD EX HANDHOLE | 6 | EACH | $1,433.00 | $2,300.00 | $1,760.00 | $2,500.00 | $1,870.00 |