2020-075-RS
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | J. A. Johnson Paving Company Low bidder | $493,301 | ||
| 2 | Payne & Dolan, Inc. | $504,253 | +2.2% | |
| 3 | Peter Baker & Son Co. | $512,100 | +3.8% | |
| 4 | Schroeder Asphalt Services, Inc. | $521,967 | +5.8% | |
| 5 | Curran Contracting Company | $522,344 | +5.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 J. A. Johnson P… | #2 Payne & Dolan, … | #3 Peter Baker & S… | #4 Schroeder Aspha… | #5 Curran Contract… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $2,500.00 | $2,500.00 | $1,800.00 | $4,000.00 | $5,000.00 | |
| 2 | X0549200 | CLEAN PAVED DITCH | 528 | FOOT | $25.00 | $25.00 | $6.00 | $12.00 | $16.00 | |
| 3 | X2020110 | GRADING & SHAP SHLDRS | 66 | UNIT | $40.00 | $18.50 | $85.00 | $40.00 | $60.00 | |
| 4 | X5537800 | SS CLEANED 12 | 100 | FOOT | $10.00 | $4.00 | $4.00 | $4.00 | $4.00 | |
| 5 | X6030310 | FR & LIDS ADJUST SPL | 11 | EACH | $1,100.00 | $825.00 | $825.00 | $825.00 | $825.00 | |
| 6 | X7030005 | TEMP PAVT MKING REMOV | 12,121 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $0.7500 | $0.0500 | |
| 7 | Z0004562 | COMB C C&G REM & REPL | 320 | FOOT | $48.00 | $48.00 | $60.00 | $50.00 | $71.00 | |
| 8 | Z0012450 | CONCRETE STEPS | 1 | CU YD | $3,000.00 | $3,000.00 | $3,000.00 | $2,300.00 | $1,500.00 | |
| 9 | Z0018500 | DRAINAGE STR CLEANED | 10 | EACH | $480.00 | $450.00 | $450.00 | $450.00 | $450.00 | |
| 10 | Z0030850 | TEMP INFO SIGNING | 51.4 | SQ FT | $25.00 | $20.00 | $12.50 | $15.00 | $12.50 | |
| 11 | Z0033700 | LONG JOINT SEALANT | 8,800 | FOOT | $1.90 | $1.90 | $2.40 | $1.90 | $2.10 | |
| 12 | 20200100 | EARTH EXCAVATION | 22 | CU YD | $45.00 | $45.00 | $45.00 | $50.00 | $115.00 | |
| 13 | 20201200 | REM & DISP UNS MATL | 1.5 | CU YD | $200.00 | $45.00 | $75.00 | $300.00 | $115.00 | |
| 14 | 21101615 | TOPSOIL F & P 4 | 100 | SQ YD | $5.98 | $5.98 | $12.50 | $7.90 | $7.90 | |
| 15 | 25000400 | NITROGEN FERT NUTR | 2 | POUND | $4.00 | $4.00 | $1.00 | $0.0100 | $0.0100 | |
| 16 | 25000600 | POTASSIUM FERT NUTR | 2 | POUND | $4.00 | $4.00 | $1.00 | $0.0100 | $0.0100 | |
| 17 | 25200110 | SODDING SALT TOLERANT | 100 | SQ YD | $30.00 | $30.00 | $12.50 | $24.00 | $27.00 | |
| 18 | 25200200 | SUPPLE WATERING | 2 | UNIT | $25.00 | $25.00 | $1.00 | $110.00 | $25.00 | |
| 19 | 40600290 | BIT MATLS TACK CT | 10,841 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 20 | 40600400 | MIX CR JTS FLANGEWYS | 37 | TON | $350.00 | $135.00 | $250.00 | $125.00 | $250.00 | |
| 21 | 40600982 | HMA SURF REM BUTT JT | 157 | SQ YD | $1.75 | $21.00 | $2.05 | $10.00 | $18.00 | |
| 22 | 40604062 | HMA SC IL-9.5 D N70 | 2,025 | TON | $66.60 | $66.00 | $77.15 | $83.00 | $75.00 | |
| 23 | 42001300 | PROTECTIVE COAT | 267 | SQ YD | $0.1000 | $0.1000 | $0.0100 | $1.00 | $4.00 | |
| 24 | 42400200 | PC CONC SIDEWALK 5 | 1,440 | SQ FT | $8.00 | $8.00 | $8.50 | $12.00 | $7.75 | |
| 25 | 42400800 | DETECTABLE WARNINGS | 90 | SQ FT | $40.00 | $40.00 | $45.00 | $45.00 | $32.00 | |
| 26 | 44000155 | HMA SURF REM 1 1/2 | 24,063 | SQ YD | $1.75 | $1.75 | $2.90 | $1.65 | $1.95 | |
| 27 | 44000600 | SIDEWALK REM | 1,440 | SQ FT | $2.65 | $2.65 | $3.00 | $3.00 | $5.00 | |
| 28 | 44201815 | CL D PATCH T2 14 | 275 | SQ YD | $100.00 | $67.00 | $65.00 | $125.00 | $145.00 | |
| 29 | 44201819 | CL D PATCH T3 14 | 100 | SQ YD | $99.00 | $54.00 | $65.00 | $115.00 | $129.00 | |
| 30 | 44201821 | CL D PATCH T4 14 | 50 | SQ YD | $98.00 | $49.00 | $65.00 | $115.00 | $112.00 | |
| 31 | 48102100 | AGG WEDGE SHLD TYPE B | 90 | TON | $40.00 | $20.45 | $40.00 | $60.00 | $65.00 | |
| 32 | 50300225 | CONC STRUCT | 3 | CU YD | $1,500.00 | $1,850.00 | $1,850.00 | $1,500.00 | $1,000.00 | |
| 33 | 50901760 | PIPE HANDRAIL | 20 | FOOT | $400.00 | $400.00 | $240.00 | $236.91 | $240.00 | |
| 34 | 60250200 | CB ADJUST | 2 | EACH | $400.00 | $400.00 | $400.00 | $400.00 | $400.00 | |
| 35 | 60252800 | CB RECONST | 1 | EACH | $1,300.00 | $1,150.00 | $1,150.00 | $1,150.00 | $1,150.00 | |
| 36 | 60262700 | INLETS RECONST | 3 | EACH | $1,200.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | |
| 37 | 60266600 | VALVE BOX ADJ | 1 | EACH | $420.00 | $300.00 | $300.00 | $300.00 | $300.00 | |
| 38 | 60300105 | FR & GRATES ADJUST | 7 | EACH | $400.00 | $400.00 | $400.00 | $400.00 | $400.00 | |
| 39 | 60300410 | VAL BOX FR ADJ NEW FR | 2 | EACH | $900.00 | $415.00 | $415.00 | $415.00 | $415.00 | |
| 40 | 60404950 | FR & GRATES T24 | 7 | EACH | $420.00 | $400.00 | $400.00 | $400.00 | $400.00 | |
| 41 | 60406100 | FR & LIDS T1 CL | 11 | EACH | $400.00 | $385.00 | $385.00 | $385.00 | $385.00 | |
| 42 | 66900200 | NON SPL WASTE DISPOSL | 25 | CU YD | $157.55 | $100.00 | $62.00 | $70.00 | $80.00 | |
| 43 | 66900530 | SOIL DISPOSAL ANALY | 2 | EACH | $1,200.00 | $1,900.00 | $1,200.00 | $1,500.00 | $1,200.00 | |
| 44 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,200.00 | $2,950.00 | $2,200.00 | $2,250.00 | $2,200.00 | |
| 45 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $1,800.00 | $900.00 | $1,800.00 | $2,250.00 | $1,800.00 | |
| 46 | 66901006 | REG SUB MON | 3 | CAL DA | $670.00 | $760.00 | $100.00 | $1,580.00 | $670.00 | |
| 47 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $2,500.00 | $250.00 | $1,000.00 | $2,500.00 | $1,900.00 | |
| 48 | 67100100 | MOBILIZATION | 1 | L SUM | $29,000.00 | $115,000.00 | $43,625.00 | $24,250.00 | $36,250.00 | |
| 49 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $37,100.00 | $5,000.00 | $24,050.00 | $10,000.00 | $10,000.00 | |
| 50 | 70102622 | TR CONT & PROT 701502 | 1 | L SUM | $100.00 | $1.00 | $12,084.66 | $1.00 | $5,000.00 | |
| 51 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $100.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 52 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $100.00 | $3,650.00 | $794.00 | $1.00 | $1,000.00 | |
| 53 | 70300100 | SHORT TERM PAVT MKING | 5,295 | FOOT | $0.0100 | $0.0100 | $0.0100 | $1.00 | $0.2500 | |
| 54 | 70300150 | SHRT TRM PAVT MK REM | 1,765 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $2.00 | $2.00 | |
| 55 | 70300210 | TEMP PVT MK LTR & SYM | 194 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $2.50 | $0.2500 | |
| 56 | 70300220 | TEMP PVT MK LINE 4 | 23,859 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.3000 | $0.0500 | |
| 57 | 70300240 | TEMP PVT MK LINE 6 | 1,507 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.5000 | $0.1000 | |
| 58 | 70300250 | TEMP PVT MK LINE 8 | 135 | FOOT | $0.0100 | $0.0100 | $0.0100 | $2.50 | $0.2000 | |
| 59 | 70300260 | TEMP PVT MK LINE 12 | 171 | FOOT | $0.0100 | $0.0100 | $0.0100 | $2.50 | $0.5000 | |
| 60 | 70300280 | TEMP PVT MK LINE 24 | 194 | FOOT | $0.0100 | $0.0100 | $0.0100 | $5.00 | $0.7500 | |
| 61 | 70300520 | PAVT MARK TAPE T3 4 | 2,648 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.9000 | $1.25 | |
| 62 | 78000100 | THPL PVT MK LTR & SYM | 194 | SQ FT | $5.00 | $5.00 | $5.00 | $5.00 | $4.00 | |
| 63 | 78000200 | THPL PVT MK LINE 4 | 23,859 | FOOT | $0.7000 | $0.5800 | $0.5800 | $0.5800 | $0.6000 | |
| 64 | 78000400 | THPL PVT MK LINE 6 | 1,507 | FOOT | $1.05 | $1.05 | $1.05 | $1.05 | $0.8000 | |
| 65 | 78000500 | THPL PVT MK LINE 8 | 135 | FOOT | $1.40 | $1.20 | $1.20 | $1.38 | $1.00 | |
| 66 | 78000600 | THPL PVT MK LINE 12 | 171 | FOOT | $2.10 | $2.20 | $2.20 | $2.50 | $2.00 | |
| 67 | 78000650 | THPL PVT MK LINE 24 | 194 | FOOT | $4.20 | $5.00 | $5.00 | $5.00 | $4.00 | |
| 68 | 78100100 | RAISED REFL PAVT MKR | 310 | EACH | $32.00 | $26.00 | $26.00 | $35.00 | $30.00 | |
| 69 | 78300200 | RAISED REF PVT MK REM | 310 | EACH | $1.00 | $9.25 | $0.0100 | $15.00 | $12.50 | |
| 70 | 88600600 | DET LOOP REPL | 38 | FOOT | $129.90 | $129.90 | $129.90 | $130.00 | $130.00 |