2020-052-RS&SW
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Peter Baker & Son Co. Low bidder | $3,247,000 | ||
| 2 | Plote Construction, Inc. | $3,550,739 | +9.4% | |
| 3 | Arrow Road Construction Co. | $3,777,948 | +16.4% | |
| 4 | Builders Paving, LLC | $3,898,000 | +20.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Peter Baker & S… | #2 Plote Construct… | #3 Arrow Road Cons… | #4 Builders Paving… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $7,500.00 | $6,500.00 | $3,130.00 | $10,000.00 | |
| 2 | X0327611 | REM & REIN BRIC PAVER | 545 | SQ FT | $15.00 | $15.00 | $15.00 | $15.00 | |
| 3 | X4400501 | COMB C&G REMOV REPL < = 10FT | 425 | FOOT | $50.00 | $55.00 | $50.00 | $51.50 | |
| 4 | X5537800 | SS CLEANED 12 | 100 | FOOT | $5.00 | $5.00 | $5.00 | $5.00 | |
| 5 | X6030310 | FR & LIDS ADJUST SPL | 8 | EACH | $850.00 | $1,200.00 | $1,175.00 | $1,175.00 | |
| 6 | X7030005 | TEMP PAVT MKING REMOV | 46,045 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $0.2500 | |
| 7 | Z0018500 | DRAINAGE STR CLEANED | 59 | EACH | $275.00 | $275.00 | $275.00 | $275.00 | |
| 8 | Z0030850 | TEMP INFO SIGNING | 51.4 | SQ FT | $12.00 | $12.00 | $12.00 | $15.00 | |
| 9 | Z0033700 | LONG JOINT SEALANT | 108,890 | FOOT | $2.10 | $2.05 | $2.20 | $2.15 | |
| 10 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 11 | 20200100 | EARTH EXCAVATION | 40 | CU YD | $75.00 | $75.00 | $75.00 | $75.00 | |
| 12 | 21101615 | TOPSOIL F & P 4 | 160 | SQ YD | $10.00 | $10.00 | $10.00 | $10.00 | |
| 13 | 25200110 | SODDING SALT TOLERANT | 160 | SQ YD | $10.00 | $10.00 | $10.00 | $10.00 | |
| 14 | 40600290 | BIT MATLS TACK CT | 93,705 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.0500 | |
| 15 | 40600400 | MIX CR JTS FLANGEWYS | 312 | TON | $175.00 | $95.00 | $110.00 | $475.00 | |
| 16 | 40600982 | HMA SURF REM BUTT JT | 685 | SQ YD | $0.0100 | $14.00 | $3.05 | $25.00 | |
| 17 | 40604062 | HMA SC IL-9.5 D N70 | 3,783 | TON | $65.85 | $77.00 | $81.35 | $68.00 | |
| 18 | 40605026 | P HMA SC SMA 9.5 F N80 | 16,627 | TON | $95.60 | $94.00 | $50.00 | $99.00 | |
| 19 | 42400200 | PC CONC SIDEWALK 5 | 2,200 | SQ FT | $10.00 | $10.00 | $10.00 | $10.00 | |
| 20 | 42400800 | DETECTABLE WARNINGS | 260 | SQ FT | $32.00 | $32.00 | $32.00 | $32.00 | |
| 21 | 44000156 | HMA SURF REM 1 3/4 | 208,233 | SQ YD | $1.90 | $2.80 | $7.05 | $2.45 | |
| 22 | 44000600 | SIDEWALK REM | 2,200 | SQ FT | $5.00 | $5.00 | $5.00 | $5.00 | |
| 23 | 44201789 | CL D PATCH T2 12 | 2,063 | SQ YD | $30.00 | $85.00 | $30.00 | $140.00 | |
| 24 | 44201794 | CL D PATCH T3 12 | 388 | SQ YD | $30.00 | $84.00 | $30.00 | $125.00 | |
| 25 | 44201796 | CL D PATCH T4 12 | 245 | SQ YD | $30.00 | $83.00 | $30.00 | $103.00 | |
| 26 | 60300305 | FR & LIDS ADJUST | 2 | EACH | $465.00 | $450.00 | $450.00 | $450.00 | |
| 27 | 66900200 | NON SPL WASTE DISPOSL | 40 | CU YD | $63.00 | $100.00 | $150.00 | $125.00 | |
| 28 | 66900530 | SOIL DISPOSAL ANALY | 3 | EACH | $1,500.00 | $1,850.00 | $1,300.00 | $1,500.00 | |
| 29 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,400.00 | $2,950.00 | $4,500.00 | $2,500.00 | |
| 30 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $2,000.00 | $900.00 | $200.00 | $2,200.00 | |
| 31 | 66901006 | REG SUB MON | 10 | CAL DA | $90.00 | $680.00 | $650.00 | $600.00 | |
| 32 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $1,000.00 | $3,200.00 | $2,750.00 | $2,500.00 | |
| 33 | 67100100 | MOBILIZATION | 1 | L SUM | $195,405.57 | $197,500.00 | $247,000.00 | $232,542.35 | |
| 34 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $11,916.00 | $1.00 | $1.00 | $29,000.00 | |
| 35 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $80,441.00 | $20,000.00 | $193,000.00 | $1.00 | |
| 36 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | |
| 37 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | |
| 38 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | |
| 39 | 70300100 | SHORT TERM PAVT MKING | 21,988 | FOOT | $0.2500 | $0.0100 | $0.0100 | $0.8500 | |
| 40 | 70300150 | SHRT TRM PAVT MK REM | 7,292 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $1.00 | |
| 41 | 70300210 | TEMP PVT MK LTR & SYM | 3,516 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $1.25 | |
| 42 | 70300220 | TEMP PVT MK LINE 4 | 85,340 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.2000 | |
| 43 | 70300240 | TEMP PVT MK LINE 6 | 16,000 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.3000 | |
| 44 | 70300250 | TEMP PVT MK LINE 8 | 1,365 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.4000 | |
| 45 | 70300260 | TEMP PVT MK LINE 12 | 1,200 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.6000 | |
| 46 | 70300280 | TEMP PVT MK LINE 24 | 2,000 | FOOT | $0.0100 | $0.0100 | $0.0100 | $1.20 | |
| 47 | 70300520 | PAVT MARK TAPE T3 4 | 5,497 | FOOT | $1.20 | $1.50 | $1.50 | $0.9000 | |
| 48 | 78000100 | THPL PVT MK LTR & SYM | 3,500 | SQ FT | $4.00 | $4.00 | $3.75 | $4.00 | |
| 49 | 78000200 | THPL PVT MK LINE 4 | 85,340 | FOOT | $0.5000 | $0.5000 | $0.5000 | $0.5000 | |
| 50 | 78000400 | THPL PVT MK LINE 6 | 16,000 | FOOT | $0.7500 | $0.7500 | $0.7000 | $0.7500 | |
| 51 | 78000500 | THPL PVT MK LINE 8 | 1,365 | FOOT | $1.00 | $1.00 | $1.00 | $1.00 | |
| 52 | 78000600 | THPL PVT MK LINE 12 | 1,200 | FOOT | $1.50 | $1.50 | $1.50 | $1.50 | |
| 53 | 78000650 | THPL PVT MK LINE 24 | 2,000 | FOOT | $4.00 | $4.00 | $4.00 | $4.00 | |
| 54 | 78100100 | RAISED REFL PAVT MKR | 1,960 | EACH | $21.15 | $25.00 | $20.00 | $25.00 | |
| 55 | 78300200 | RAISED REF PVT MK REM | 1,918 | EACH | $9.00 | $10.00 | $5.00 | $8.00 | |
| 56 | 88600600 | DET LOOP REPL | 4,219 | FOOT | $15.70 | $15.80 | $15.80 | $15.80 |