2020-012-SW
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Triggi Construction, Inc. Low bidder | $788,016 | ||
| 2 | Davis Concrete Construction Co. | $891,189 | +13.1% | |
| 3 | J & J Newell Concrete Contractors, Inc. | $911,625 | +15.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Triggi Construc… | #2 Davis Concrete … | #3 J & J Newell Co… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $26,000.00 | $10,200.00 | $26,000.00 | |
| 2 | X0323360 | WOOD POLE REMOVAL | 1 | EACH | $500.00 | $1,000.00 | $500.00 | |
| 3 | X0326806 | WASHOUT BASIN | 1 | L SUM | $1,000.00 | $1,000.00 | $1,800.00 | |
| 4 | X0327890 | DRIVEWAY REMOV & REPL | 8 | SQ YD | $100.00 | $90.00 | $208.00 | |
| 5 | X0327979 | PAVMT MRKG REM GRIND | 2,196 | SQ FT | $1.50 | $0.9500 | $1.25 | |
| 6 | X0327980 | PAVMT MRKG REM WTR BL | 296 | SQ FT | $7.50 | $2.10 | $15.00 | |
| 7 | X2600012 | REM & REL SN P&P ASSY | 7 | EACH | $500.00 | $300.00 | $500.00 | |
| 8 | X4400220 | CURB REM & REPLACEMT | 11 | FOOT | $65.00 | $60.00 | $75.00 | |
| 9 | X4400221 | CURB REM & REPLACEMT < = 10FT | 10 | FOOT | $65.00 | $65.00 | $100.00 | |
| 10 | X4400501 | COMB C&G REMOV REPL < = 10FT | 125 | FOOT | $60.00 | $65.00 | $100.00 | |
| 11 | X4404200 | PAVED FLUME REMOVAL | 31 | FOOT | $10.00 | $25.00 | $20.00 | |
| 12 | X4420480 | CL D PATCH T1 6 SPL | 174 | SQ YD | $125.00 | $135.00 | $75.00 | |
| 13 | X4420482 | CL D PATCH T2 6 SPL | 55 | SQ YD | $100.00 | $125.00 | $75.00 | |
| 14 | X4420484 | CL D PATCH T3 6 SPL | 23 | SQ YD | $75.00 | $115.00 | $75.00 | |
| 15 | Z0004562 | COMB C C&G REM & REPL | 2,034 | FOOT | $50.00 | $57.00 | $65.00 | |
| 16 | Z0030850 | TEMP INFO SIGNING | 565.4 | SQ FT | $15.00 | $15.00 | $14.00 | |
| 17 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 18 | 20100210 | TREE REMOV OVER 15 | 20 | UNIT | $65.00 | $65.00 | $70.00 | |
| 19 | 20200100 | EARTH EXCAVATION | 326 | CU YD | $75.00 | $25.00 | $100.00 | |
| 20 | 21101615 | TOPSOIL F & P 4 | 1,193 | SQ YD | $2.00 | $10.00 | $15.00 | |
| 21 | 25000400 | NITROGEN FERT NUTR | 22 | POUND | $10.00 | $3.00 | $5.00 | |
| 22 | 25000600 | POTASSIUM FERT NUTR | 22 | POUND | $10.00 | $3.00 | $5.00 | |
| 23 | 25200100 | SODDING | 1,169 | SQ YD | $25.00 | $12.00 | $30.00 | |
| 24 | 25200200 | SUPPLE WATERING | 18 | UNIT | $1.00 | $0.0100 | $210.00 | |
| 25 | 40604062 | HMA SC IL-9.5 D N70 | 45.5 | TON | $350.00 | $390.00 | $130.00 | |
| 26 | 40800029 | BIT MATLS TACK CT | 311 | POUND | $0.1000 | $1.00 | $3.00 | |
| 27 | 42001300 | PROTECTIVE COAT | 2,486 | SQ YD | $0.1000 | $0.5000 | $2.00 | |
| 28 | 42400200 | PC CONC SIDEWALK 5 | 17,200 | SQ FT | $11.00 | $15.00 | $13.50 | |
| 29 | 42400800 | DETECTABLE WARNINGS | 1,406 | SQ FT | $25.00 | $25.00 | $30.00 | |
| 30 | 44000100 | PAVEMENT REM | 70 | SQ YD | $20.00 | $40.00 | $21.00 | |
| 31 | 44000155 | HMA SURF REM 1 1/2 | 443 | SQ YD | $25.00 | $26.00 | $15.00 | |
| 32 | 44000600 | SIDEWALK REM | 16,342 | SQ FT | $2.50 | $5.00 | $2.50 | |
| 33 | 60250200 | CB ADJUST | 8 | EACH | $300.00 | $450.00 | $500.00 | |
| 34 | 60250400 | CB ADJ NEW T1F OL | 2 | EACH | $750.00 | $565.00 | $850.00 | |
| 35 | 60255500 | MAN ADJUST | 10 | EACH | $300.00 | $475.00 | $600.00 | |
| 36 | 60260100 | INLETS ADJUST | 7 | EACH | $300.00 | $375.00 | $450.00 | |
| 37 | 60265700 | VV ADJUST | 6 | EACH | $300.00 | $400.00 | $200.00 | |
| 38 | 60617800 | PAVED FLUME | 31 | FOOT | $50.00 | $125.00 | $60.00 | |
| 39 | 66900200 | NON SPL WASTE DISPOSL | 326 | CU YD | $65.00 | $50.00 | $100.00 | |
| 40 | 66900530 | SOIL DISPOSAL ANALY | 13 | EACH | $1,200.00 | $1,100.00 | $1,500.00 | |
| 41 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $5,500.00 | $3,000.00 | $1,800.00 | |
| 42 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $500.00 | $2,500.00 | $2,200.00 | |
| 43 | 66901006 | REG SUB MON | 25 | CAL DA | $250.00 | $376.00 | $700.00 | |
| 44 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $2,000.00 | $1,500.00 | $3,500.00 | |
| 45 | 67100100 | MOBILIZATION | 1 | L SUM | $50,000.00 | $144,500.00 | $85,000.00 | |
| 46 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $35,000.00 | $1.00 | $4,275.00 | |
| 47 | 70102622 | TR CONT & PROT 701502 | 1 | L SUM | $1.00 | $1.00 | $4,275.00 | |
| 48 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $30,000.00 | $4,500.00 | $4,275.00 | |
| 49 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $1.00 | $1.00 | $4,275.00 | |
| 50 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.00 | $4,275.00 | |
| 51 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $5,000.00 | $1.00 | $4,275.00 | |
| 52 | 78000400 | THPL PVT MK LINE 6 | 3,768 | FOOT | $2.00 | $1.65 | $1.10 | |
| 53 | 78000600 | THPL PVT MK LINE 12 | 1,788 | FOOT | $4.00 | $3.60 | $2.20 | |
| 54 | 78000650 | THPL PVT MK LINE 24 | 137 | FOOT | $8.00 | $7.19 | $10.00 | |
| 55 | 85000200 | MAIN EX TR SIG INSTAL | 6 | EACH | $2,500.00 | $811.00 | $810.22 | |
| 56 | 89500400 | RELOC EX PED PUSH-BUT | 9 | EACH | $510.00 | $185.00 | $184.49 | |
| 57 | 89502376 | REBUILD EX HANDHOLE | 1 | EACH | $2,400.00 | $3,250.00 | $3,240.15 |