2019-080-RS&SW
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Builders Paving, LLC Low bidder | $4,038,000 | ||
| 2 | Plote Construction, Inc. | $4,216,193 | +4.4% | |
| 3 | Arrow Road Construction Co. | $4,336,197 | +7.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Builders Paving… | #2 Plote Construct… | #3 Arrow Road Cons… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $21,000.00 | $6,500.00 | $7,470.00 | |
| 2 | X5537800 | SS CLEANED 12 | 1,745 | FOOT | $6.35 | $6.35 | $2.50 | |
| 3 | X5538600 | SS CLEANED 36 | 130 | FOOT | $33.00 | $33.00 | $5.50 | |
| 4 | X6030310 | FR & LIDS ADJUST SPL | 76 | EACH | $730.00 | $700.00 | $700.00 | |
| 5 | X7030005 | TEMP PAVT MKING REMOV | 32,720 | SQ FT | $0.0100 | $0.0100 | $0.0100 | |
| 6 | Z0004562 | COMB C C&G REM & REPL | 992 | FOOT | $42.00 | $62.00 | $60.00 | |
| 7 | Z0018500 | DRAINAGE STR CLEANED | 356 | EACH | $330.00 | $330.00 | $365.00 | |
| 8 | Z0023201 | SED CONT SILT CURTAIN | 1 | EACH | $5,000.00 | $8,000.00 | $1,500.00 | |
| 9 | Z0030850 | TEMP INFO SIGNING | 51.4 | SQ FT | $26.00 | $12.00 | $12.00 | |
| 10 | Z0033700 | LONG JOINT SEALANT | 62,957 | FOOT | $3.00 | $2.20 | $2.32 | |
| 11 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $5,000.00 | $1,000.00 | $5,000.00 | |
| 12 | 20101000 | TEMPORARY FENCE | 50 | FOOT | $18.00 | $20.00 | $8.55 | |
| 13 | 20200100 | EARTH EXCAVATION | 57 | CU YD | $48.00 | $65.00 | $50.00 | |
| 14 | 20400800 | FURNISHED EXCAVATION | 18 | CU YD | $195.00 | $195.00 | $150.00 | |
| 15 | 21101615 | TOPSOIL F & P 4 | 72 | SQ YD | $6.00 | $6.00 | $27.06 | |
| 16 | 21101625 | TOPSOIL F & P 6 | 1,080 | SQ YD | $8.00 | $8.00 | $8.20 | |
| 17 | 25000110 | SEEDING CL 1A | 0.3 | ACRE | $2,000.00 | $2,000.00 | $1,672.80 | |
| 18 | 25000400 | NITROGEN FERT NUTR | 28 | POUND | $5.00 | $5.00 | $5.74 | |
| 19 | 25000600 | POTASSIUM FERT NUTR | 28 | POUND | $5.00 | $5.00 | $5.74 | |
| 20 | 25100630 | EROSION CONTR BLANKET | 1,080 | SQ YD | $1.25 | $1.25 | $0.8800 | |
| 21 | 25200110 | SODDING SALT TOLERANT | 72 | SQ YD | $25.00 | $25.00 | $29.52 | |
| 22 | 25200200 | SUPPLE WATERING | 1 | UNIT | $100.00 | $100.00 | $820.00 | |
| 23 | 28000400 | PERIMETER EROS BAR | 215 | FOOT | $6.00 | $4.00 | $4.54 | |
| 24 | 28100109 | STONE RIPRAP CL A5 | 15 | SQ YD | $650.00 | $175.00 | $650.00 | |
| 25 | 28200200 | FILTER FABRIC | 19 | SQ YD | $50.00 | $10.00 | $50.00 | |
| 26 | 40201000 | AGGREGATE-TEMP ACCESS | 54 | TON | $125.00 | $1.00 | $20.00 | |
| 27 | 40600290 | BIT MATLS TACK CT | 77,813 | POUND | $0.0100 | $0.0100 | $1.10 | |
| 28 | 40600400 | MIX CR JTS FLANGEWYS | 173 | TON | $470.00 | $125.00 | $100.00 | |
| 29 | 40600982 | HMA SURF REM BUTT JT | 815 | SQ YD | $18.00 | $12.00 | $5.45 | |
| 30 | 40602985 | HMA BC IL-9.5 N70 | 12,911 | TON | $65.00 | $69.00 | $71.90 | |
| 31 | 40605026 | P HMA SC SMA 9.5 F N80 | 11,297 | TON | $89.00 | $95.00 | $106.00 | |
| 32 | 42001300 | PROTECTIVE COAT | 628 | SQ YD | $3.00 | $1.00 | $1.00 | |
| 33 | 42400200 | PC CONC SIDEWALK 5 | 6,003 | SQ FT | $8.00 | $6.00 | $6.00 | |
| 34 | 42400800 | DETECTABLE WARNINGS | 334 | SQ FT | $34.00 | $32.00 | $32.00 | |
| 35 | 44000164 | HMA SURF REM 3 3/4 | 115,279 | SQ YD | $5.70 | $7.25 | $6.50 | |
| 36 | 44000600 | SIDEWALK REM | 6,003 | SQ FT | $2.70 | $4.00 | $4.00 | |
| 37 | 44201773 | CL D PATCH T1 11 | 12 | SQ YD | $160.00 | $225.00 | $217.30 | |
| 38 | 44201777 | CL D PATCH T2 11 | 156 | SQ YD | $110.00 | $130.00 | $105.00 | |
| 39 | 44201781 | CL D PATCH T3 11 | 43 | SQ YD | $104.00 | $129.00 | $88.00 | |
| 40 | 44201783 | CL D PATCH T4 11 | 100 | SQ YD | $104.00 | $128.00 | $87.00 | |
| 41 | 54261236 | CONC ES 542001 36 1:2 | 1 | EACH | $24,000.00 | $23,500.00 | $23,500.00 | |
| 42 | 550A0750 | STORM SEW CL A 3 36 | 38 | FOOT | $700.00 | $685.00 | $685.00 | |
| 43 | 55101600 | STORM SEWER REM 36 | 46 | FOOT | $260.00 | $250.00 | $250.00 | |
| 44 | 60223800 | MAN TA 6 DIA T1F CL | 1 | EACH | $44,000.00 | $42,500.00 | $42,500.00 | |
| 45 | 60252800 | CB RECONST | 2 | EACH | $1,300.00 | $1,250.00 | $1,250.00 | |
| 46 | 60255410 | CB CLEANED | 1 | EACH | $329.00 | $329.00 | $500.00 | |
| 47 | 60257900 | MAN RECONST | 7 | EACH | $1,600.00 | $1,550.00 | $1,550.00 | |
| 48 | 60266600 | VALVE BOX ADJ | 1 | EACH | $330.00 | $525.00 | $325.00 | |
| 49 | 60300105 | FR & GRATES ADJUST | 10 | EACH | $530.00 | $525.00 | $525.00 | |
| 50 | 60300305 | FR & LIDS ADJUST | 7 | EACH | $610.00 | $600.00 | $600.00 | |
| 51 | 60406000 | FR & LIDS T1 OL | 1 | EACH | $800.00 | $785.00 | $785.00 | |
| 52 | 66900200 | NON SPL WASTE DISPOSL | 57 | CU YD | $135.00 | $145.00 | $180.00 | |
| 53 | 66900530 | SOIL DISPOSAL ANALY | 2 | EACH | $1,850.00 | $1,800.00 | $1,400.00 | |
| 54 | 66901001 | REG SUB P-CONST PLAN | 1 | LSUM | $2,500.00 | $2,950.00 | $2,600.00 | |
| 55 | 66901003 | REG SUB F CON REPORT | 1 | LSUM | $2,500.00 | $900.00 | $1,000.00 | |
| 56 | 66901006 | REG SUB MON | 15 | CAL DA | $750.00 | $180.00 | $700.00 | |
| 57 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $2,600.00 | $3,500.00 | $2,500.00 | |
| 58 | 67100100 | MOBILIZATION | 1 | L SUM | $239,625.90 | $250,000.00 | $363,000.00 | |
| 59 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $100.00 | $1.00 | $24,500.00 | |
| 60 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $100.00 | $189,600.00 | $23,850.00 | |
| 61 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $35,000.00 | $1.00 | $1.00 | |
| 62 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $100.00 | $1.00 | $1.00 | |
| 63 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $10,000.00 | $1.00 | $1.00 | |
| 64 | 70300100 | SHORT TERM PAVT MKING | 142,800 | FOOT | $0.1000 | $0.0100 | $0.0100 | |
| 65 | 70300150 | SHRT TRM PAVT MK REM | 142,800 | SQ FT | $0.0100 | $0.0100 | $0.0100 | |
| 66 | 70300210 | TEMP PVT MK LTR & SYM | 2,267 | SQ FT | $1.25 | $1.00 | $0.0100 | |
| 67 | 70300220 | TEMP PVT MK LINE 4 | 54,881 | FOOT | $0.2500 | $0.0100 | $0.0100 | |
| 68 | 70300240 | TEMP PVT MK LINE 6 | 8,695 | FOOT | $0.3000 | $0.0100 | $0.0100 | |
| 69 | 70300250 | TEMP PVT MK LINE 8 | 189 | FOOT | $0.6000 | $0.0100 | $0.0100 | |
| 70 | 70300260 | TEMP PVT MK LINE 12 | 4,750 | FOOT | $0.8000 | $0.0100 | $0.0100 | |
| 71 | 70300280 | TEMP PVT MK LINE 24 | 1,159 | FOOT | $1.25 | $0.0100 | $0.0100 | |
| 72 | 70300520 | PAVT MARK TAPE T3 4 | 71,400 | FOOT | $1.10 | $0.0100 | $0.0100 | |
| 73 | 78000100 | THPL PVT MK LTR & SYM | 2,267 | SQ FT | $4.85 | $3.75 | $3.75 | |
| 74 | 78000200 | THPL PVT MK LINE 4 | 54,881 | FOOT | $0.6200 | $0.5000 | $0.5000 | |
| 75 | 78000400 | THPL PVT MK LINE 6 | 8,695 | FOOT | $1.05 | $0.7500 | $0.7500 | |
| 76 | 78000500 | THPL PVT MK LINE 8 | 189 | FOOT | $1.50 | $1.00 | $1.00 | |
| 77 | 78000600 | THPL PVT MK LINE 12 | 4,750 | FOOT | $2.30 | $1.50 | $1.50 | |
| 78 | 78000650 | THPL PVT MK LINE 24 | 1,159 | FOOT | $4.85 | $3.75 | $3.75 | |
| 79 | 78100100 | RAISED REFL PAVT MKR | 1,840 | EACH | $24.00 | $22.00 | $22.00 | |
| 80 | 78300200 | RAISED REF PVT MK REM | 1,738 | EACH | $14.00 | $11.00 | $6.35 | |
| 81 | 88600600 | DET LOOP REPL | 5,001 | FOOT | $17.00 | $16.70 | $16.70 | |
| 82 | 89500400 | RELOC EX PED PUSH-BUT | 16 | EACH | $440.00 | $410.00 | $410.00 | |
| 83 | 89502376 | REBUILD EX HANDHOLE | 12 | EACH | $2,300.00 | $2,210.00 | $2,210.00 |