15-00275-00-BT
Bidders 8
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Chicagoland Paving Contractors, Inc. Low bidder | $224,900 | ||
| 2 | D. Construction, Inc. | $239,894 | +6.7% | |
| 3 | Martam Construction Incorporated | $261,955 | +16.5% | |
| 4 | Lorusso Cement Contractors, Inc. | $270,382 | +20.2% | |
| 5 | Schroeder Asphalt Services, Inc. | $278,201 | +23.7% | |
| 6 | K-Five Construction Corporation | $293,654 | +30.6% | |
| 7 | Sumit Construction Co., Inc. | $336,412 | +49.6% | |
| 8 | Alliance Contractors, Inc. | $346,827 | +54.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Chicagoland Pav… | #2 D. Construction… | #3 Martam Construc… | #4 Lorusso Cement … | #5 Schroeder Aspha… | #6 K-Five Construc… | #7 Sumit Construct… | #8 Alliance Contra… |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | XX003338 | TEST HOLE | 10 | EACH | $250.00 | $400.00 | $300.00 | $157.50 | $400.00 | $160.00 | $200.00 | $100.00 | |
| 2 | X0322936 | REMOV EX FLAR END SEC | 1 | EACH | $270.00 | $450.00 | $288.20 | $215.25 | $250.00 | $220.00 | $100.00 | $150.00 | |
| 3 | X0327036 | BIKE PATH REM | 666 | SQ YD | $15.00 | $10.00 | $7.00 | $18.78 | $7.50 | $8.00 | $16.00 | $40.00 | |
| 4 | X4020900 | AGG SURF CSE B SPL | 6,336 | SQ YD | $3.00 | $3.15 | $5.60 | $4.03 | $3.25 | $3.85 | $4.50 | $15.90 | |
| 5 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $3,500.00 | $3,000.00 | $23,305.70 | $2,887.50 | $5,000.00 | $2,800.00 | $20,000.00 | $2,600.00 | |
| 6 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $2,500.00 | $5,000.00 | $7,900.00 | $5,720.40 | $5,200.00 | $6,600.00 | $10,000.00 | $12,980.00 | |
| 7 | 20101000 | TEMPORARY FENCE | 4,641 | FOOT | $2.00 | $4.00 | $4.00 | $3.15 | $4.00 | $2.65 | $4.20 | $3.50 | |
| 8 | 20200100 | EARTH EXCAVATION | 626 | CU YD | $35.00 | $28.00 | $25.00 | $31.97 | $32.00 | $85.00 | $50.00 | $1.00 | |
| 9 | 20800150 | TRENCH BACKFILL | 4 | CU YD | $45.00 | $100.00 | $37.10 | $76.82 | $75.00 | $84.50 | $40.00 | $14.00 | |
| 10 | 21001000 | GEOTECH FAB F/GR STAB | 6,336 | SQ YD | $1.25 | $2.00 | $1.10 | $2.88 | $1.10 | $0.8500 | $3.00 | $1.00 | |
| 11 | 21101505 | TOPSOIL EXC & PLAC | 637 | CU YD | $25.00 | $15.00 | $17.70 | $13.23 | $18.00 | $22.00 | $65.00 | $1.00 | |
| 12 | 21101625 | TOPSOIL F & P 6 | 4,255 | SQ YD | $4.20 | $6.93 | $6.30 | $6.51 | $9.45 | $6.65 | $7.50 | $4.50 | |
| 13 | 25000200 | SEEDING CL 2 | 3 | ACRE | $2,080.00 | $2,839.10 | $2,581.00 | $2,887.50 | $1,500.00 | $3,000.00 | $1,800.00 | $2,420.00 | |
| 14 | 25000400 | NITROGEN FERT NUTR | 270 | POUND | $3.15 | $3.30 | $3.00 | $2.63 | $4.15 | $2.70 | $2.00 | $1.00 | |
| 15 | 25000600 | POTASSIUM FERT NUTR | 270 | POUND | $3.15 | $3.30 | $3.00 | $2.63 | $4.15 | $2.70 | $2.00 | $1.00 | |
| 16 | 25100630 | EROSION CONTR BLANKET | 14,520 | SQ YD | $1.05 | $0.8700 | $0.8000 | $1.31 | $1.00 | $1.35 | $1.50 | $1.20 | |
| 17 | 25200110 | SODDING SALT TOLERANT | 60 | SQ YD | $20.00 | $9.90 | $9.00 | $26.25 | $100.00 | $26.75 | $16.00 | $20.00 | |
| 18 | 25200200 | SUPPLE WATERING | 1 | UNIT | $1.05 | $0.0200 | $0.0100 | $105.00 | $50.00 | $108.00 | $125.00 | $200.00 | |
| 19 | 28000250 | TEMP EROS CONTR SEED | 2,143 | POUND | $1.25 | $2.20 | $2.00 | $3.15 | $4.25 | $3.25 | $2.10 | $0.1000 | |
| 20 | 28000305 | TEMP DITCH CHECKS | 100 | FOOT | $15.00 | $10.67 | $9.70 | $12.60 | $10.00 | $12.85 | $14.00 | $15.00 | |
| 21 | 28000400 | PERIMETER EROS BAR | 6,893 | FOOT | $2.15 | $2.42 | $2.20 | $2.05 | $3.00 | $2.10 | $2.80 | $2.50 | |
| 22 | 35101600 | AGG BASE CSE B 4 | 35 | SQ YD | $10.00 | $10.00 | $7.60 | $17.25 | $8.50 | $9.60 | $5.50 | $18.90 | |
| 23 | 35101800 | AGG BASE CSE B 6 | 918 | SQ YD | $8.50 | $12.00 | $8.20 | $9.20 | $10.00 | $13.75 | $8.00 | $20.10 | |
| 24 | 40201000 | AGGREGATE-TEMP ACCESS | 39 | TON | $25.00 | $30.00 | $29.40 | $41.98 | $40.00 | $30.00 | $10.00 | $63.50 | |
| 25 | 40603335 | HMA SC "D" N50 | 155 | TON | $110.00 | $85.00 | $98.00 | $128.80 | $155.00 | $100.00 | $135.00 | $116.00 | |
| 26 | 42001300 | PROTECTIVE COAT | 47 | SQ YD | $15.25 | $2.00 | $2.40 | $3.68 | $6.50 | $1.10 | $3.00 | $1.00 | |
| 27 | 42400200 | PC CONC SIDEWALK 5 | 313 | SQ FT | $9.40 | $8.00 | $8.00 | $6.10 | $12.75 | $15.00 | $12.00 | $11.40 | |
| 28 | 42400800 | DETECTABLE WARNINGS | 20 | SQ FT | $41.00 | $30.00 | $29.00 | $39.10 | $40.00 | $35.00 | $36.00 | $23.70 | |
| 29 | 44000500 | COMB CURB GUTTER REM | 51 | FOOT | $10.00 | $10.00 | $7.60 | $10.03 | $30.00 | $8.60 | $9.00 | $50.00 | |
| 30 | 44000600 | SIDEWALK REM | 156 | SQ FT | $2.50 | $2.50 | $3.60 | $3.80 | $12.00 | $3.75 | $3.00 | $10.00 | |
| 31 | 542A0217 | P CUL CL A 1 12 | 16 | FOOT | $270.00 | $65.00 | $69.90 | $56.07 | $89.00 | $57.00 | $40.00 | $220.40 | |
| 32 | 54213657 | PRC FLAR END SEC 12 | 1 | EACH | $3,025.00 | $500.00 | $1,306.90 | $546.00 | $950.00 | $555.00 | $350.00 | $399.15 | |
| 33 | 60603800 | COMB CC&G TB6.12 | 51 | FOOT | $53.00 | $32.00 | $27.70 | $25.30 | $90.00 | $107.00 | $35.00 | $64.60 | |
| 34 | 66900200 | NON SPL WASTE DISPOSL | 290 | CU YD | $85.00 | $35.00 | $65.00 | $115.69 | $100.00 | $85.00 | $35.00 | $129.00 | |
| 35 | 67100100 | MOBILIZATION | 1 | L SUM | $4,402.30 | $23,500.00 | $15,000.00 | $8,800.00 | $3,000.00 | $17,000.00 | $20,000.00 | $21,698.85 |