ROCK CUT PHASE 3-2023
- Let date
- Friday, November 18, 2022
- Contract
- 46934 · job page
- District
- District 2
- County
- Winnebago
- Highway
- Limits
- The proposed improvements consist of road reconstruction, culvert replacement, ADA and parking improvements, and all other work to complete the improvement at INDR's Rock Cut State Park located in Winnebago County.
- Classification
- Road reconstruction, culvert replacement, ADA and parking improvements, and all other work to complete the imp
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | N-Trak Group LLC Low bidder | $4,447,038 | ||
| 2 | William Charles Construction Company, LLC | $4,714,023 | +6.0% | |
| 3 | Fischer Excavating, Inc. | $5,037,347 | +13.3% | |
| 4 | Plote Construction, Inc. | $5,061,000 | +13.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 N-Trak Group LLC | #2 William Charles… | #3 Fischer Excavat… | #4 Plote Construct… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0300019 | REM REIN PARKING BLKS | 31 | EACH | $65.00 | $65.73 | $65.00 | $85.00 | |
| 2 | X0300249 | REMOV EX GATE | 1 | EACH | $836.00 | $845.33 | $836.00 | $836.00 | |
| 3 | X0301339 | REM EX PARKING BLOCKS | 159 | EACH | $15.00 | $36.14 | $47.00 | $80.00 | |
| 4 | X0321309 | CONCRETE PAD | 64 | SQ YD | $116.55 | $161.79 | $170.00 | $145.00 | |
| 5 | X0323013 | TUBULAR STEEL GATE | 1 | EACH | $8,321.00 | $8,413.87 | $8,321.00 | $8,321.00 | |
| 6 | X0323378 | CONC PARKING BLOCKS | 173 | EACH | $175.00 | $176.95 | $175.00 | $115.00 | |
| 7 | X0325712 | RELOC EXIST ELEC SYS | 1 | L SUM | $2,916.00 | $22,209.88 | $21,400.00 | $2,916.00 | |
| 8 | X0327880 | WAYFINDING SIGN SP | 1 | L SUM | $22,355.00 | $17,624.54 | $22,355.00 | $17,430.00 | |
| 9 | X0328017 | STRM MIT BANK CRED | 1,437 | EACH | $90.00 | $78.00 | $78.00 | $78.00 | |
| 10 | X0328022 | WL MIT BANK CRED | 0.2 | EACH | $55,000.00 | $50,000.00 | $50,000.00 | $50,000.00 | |
| 11 | X0900064 | MEMBR WTRPR SYS B STR | 341 | SQ YD | $43.00 | $40.45 | $40.00 | $28.00 | |
| 12 | X1700114 | CONCRETE PAD REMOVAL | 103 | SQ FT | $7.00 | $14.30 | $6.00 | $10.00 | |
| 13 | X2510001 | WOODLAND SEEDING SPL | 196,716 | SQ FT | $0.2500 | $0.2800 | $0.2500 | $0.2500 | |
| 14 | X2600016 | MINOR SIGN COMPLETE | 7 | EACH | $5,625.00 | $3,227.63 | $5,625.00 | $3,192.00 | |
| 15 | X2600040 | STONE BOULDERS SPL | 20 | EACH | $450.00 | $303.35 | $300.00 | $500.00 | |
| 16 | X2800400 | PERIMETER EROS BAR SP | 22,167 | FOOT | $4.75 | $8.09 | $4.75 | $4.75 | |
| 17 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $112,000.00 | $25,000.00 | $14,000.00 | $12,500.00 | |
| 18 | X7240207 | REM EX SIGN COMPL | 8 | EACH | $600.00 | $607.38 | $250.00 | $537.00 | |
| 19 | X7240300 | SIGN REMOVAL | 14 | EACH | $100.00 | $565.53 | $150.00 | $375.00 | |
| 20 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $37,000.00 | $70,000.00 | $49,650.00 | $49,650.00 | |
| 21 | Z0022800 | FENCE REMOVAL | 98 | FOOT | $8.00 | $8.09 | $8.00 | $8.00 | |
| 22 | Z0076604 | TRAINEES TPG | 2,000 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 23 | 20100110 | TREE REMOV 6-15 | 99 | UNIT | $27.50 | $27.44 | $23.00 | $23.00 | |
| 24 | 20100210 | TREE REMOV OVER 15 | 121 | UNIT | $41.50 | $41.75 | $35.00 | $35.00 | |
| 25 | 20100500 | TREE REMOV ACRES | 7 | ACRE | $10,700.00 | $10,736.94 | $9,000.00 | $9,000.00 | |
| 26 | 20101000 | TEMPORARY FENCE | 18,365 | FOOT | $0.0100 | $3.54 | $14.20 | $3.50 | |
| 27 | 20200100 | EARTH EXCAVATION | 32,874 | CU YD | $18.25 | $20.98 | $17.00 | $22.00 | |
| 28 | 20300100 | CHANNEL EXCAVATION | 700 | CU YD | $21.00 | $46.59 | $20.00 | $60.00 | |
| 29 | 20700220 | POROUS GRAN EMBANK | 383 | CU YD | $48.00 | $90.24 | $37.00 | $90.00 | |
| 30 | 20800150 | TRENCH BACKFILL | 45 | CU YD | $0.0100 | $0.0100 | $40.00 | $60.00 | |
| 31 | 21001000 | GEOTECH FAB F/GR STAB | 7,153 | SQ YD | $2.00 | $5.95 | $1.80 | $4.00 | |
| 32 | 21101505 | TOPSOIL EXC & PLAC | 8,422 | CU YD | $13.00 | $11.89 | $9.00 | $27.00 | |
| 33 | 21301048 | EXPLOR TRENCH 48 | 2,000 | FOOT | $12.00 | $0.0100 | $9.00 | $10.00 | |
| 34 | 25000115 | SEEDING CL 1B | 6 | ACRE | $3,500.00 | $3,033.48 | $3,500.00 | $3,500.00 | |
| 35 | 25000400 | NITROGEN FERT NUTR | 537 | POUND | $3.00 | $3.03 | $3.00 | $3.00 | |
| 36 | 25000500 | PHOSPHORUS FERT NUTR | 537 | POUND | $3.00 | $3.03 | $3.00 | $3.00 | |
| 37 | 25000600 | POTASSIUM FERT NUTR | 537 | POUND | $3.00 | $3.03 | $3.00 | $3.00 | |
| 38 | 25100115 | MULCH METHOD 2 | 6 | ACRE | $2,500.00 | $3,033.48 | $2,500.00 | $2,500.00 | |
| 39 | 25100630 | EROSION CONTR BLANKET | 28,846 | SQ YD | $2.50 | $1.52 | $2.50 | $2.50 | |
| 40 | 28000250 | TEMP EROS CONTR SEED | 596 | POUND | $3.00 | $5.06 | $3.00 | $3.00 | |
| 41 | 28000305 | TEMP DITCH CHECKS | 4,000 | FOOT | $8.00 | $6.07 | $8.00 | $8.00 | |
| 42 | 28000315 | AGG DITCH CHECKS | 4 | TON | $90.00 | $650.00 | $80.00 | $180.00 | |
| 43 | 28000500 | INLET & PIPE PROTECT | 19 | EACH | $100.00 | $505.58 | $350.00 | $350.00 | |
| 44 | 28100105 | STONE RIPRAP CL A3 | 214 | SQ YD | $48.00 | $33.31 | $25.00 | $70.00 | |
| 45 | 28100107 | STONE RIPRAP CL A4 | 383 | SQ YD | $52.00 | $78.80 | $48.00 | $80.00 | |
| 46 | 28100109 | STONE RIPRAP CL A5 | 147 | SQ YD | $81.00 | $104.07 | $60.00 | $100.00 | |
| 47 | 28200200 | FILTER FABRIC | 744 | SQ YD | $3.00 | $7.17 | $3.00 | $10.00 | |
| 48 | 30300011 | AGG SUBGRADE IMPROVE | 44,131 | TON | $19.50 | $18.21 | $25.00 | $21.00 | |
| 49 | 31101400 | SUB GRAN MAT B 6 | 2,148 | SQ YD | $9.00 | $9.31 | $8.00 | $20.00 | |
| 50 | 40200900 | AGG SURF CSE B | 5 | CU YD | $62.00 | $156.29 | $166.00 | $160.00 | |
| 51 | 40600275 | BIT MATLS PR CT | 96,283 | POUND | $0.2000 | $0.6000 | $0.8300 | $0.8300 | |
| 52 | 40600290 | BIT MATLS TACK CT | 9,629 | POUND | $0.0100 | $0.5400 | $0.6200 | $0.6200 | |
| 53 | 40602965 | HMA BC IL-9.5FG N50 | 4,951 | TON | $83.50 | $80.47 | $79.39 | $79.39 | |
| 54 | 40604000 | HMA SC IL-9.5FG C N50 | 4,952 | TON | $83.50 | $81.62 | $79.39 | $79.39 | |
| 55 | 42400200 | PC CONC SIDEWALK 5 | 4,934 | SQ FT | $9.05 | $9.86 | $11.00 | $10.00 | |
| 56 | 44000600 | SIDEWALK REM | 343 | SQ FT | $3.50 | $4.29 | $2.50 | $5.00 | |
| 57 | 50105220 | PIPE CULVERT REMOV | 1,157 | FOOT | $22.00 | $25.75 | $7.00 | $20.00 | |
| 58 | 50200100 | STRUCTURE EXCAVATION | 763 | CU YD | $30.00 | $65.64 | $25.00 | $60.00 | |
| 59 | 51500100 | NAME PLATES | 2 | EACH | $750.00 | $791.74 | $700.00 | $1,000.00 | |
| 60 | 54001001 | BOX CUL END SEC C1 | 4 | EACH | $0.0100 | $0.0100 | $40,000.00 | $0.0100 | |
| 61 | 54001002 | BOX CUL END SEC C2 | 2 | EACH | $60,000.00 | $32,791.19 | $24,000.00 | $74,000.00 | |
| 62 | 54001003 | BOX CUL END SEC C3 | 2 | EACH | $12,500.00 | $14,760.25 | $13,500.00 | $15,000.00 | |
| 63 | 54001004 | BOX CUL END SEC C4 | 2 | EACH | $7,000.00 | $6,764.73 | $7,200.00 | $7,500.00 | |
| 64 | 54010302 | PCBC 3X2 | 48 | FOOT | $400.00 | $363.44 | $420.00 | $400.00 | |
| 65 | 54010504 | PCBC 5X4 | 74 | FOOT | $550.00 | $589.90 | $780.00 | $800.00 | |
| 66 | 54010804 | PCBC 8X4 | 86 | FOOT | $725.00 | $995.67 | $890.00 | $1,200.00 | |
| 67 | 54011205 | PCBC 12X5 | 141 | FOOT | $1,200.00 | $1,288.02 | $1,700.00 | $1,500.00 | |
| 68 | 542A0217 | P CUL CL A 1 12 | 336 | FOOT | $62.00 | $117.63 | $58.00 | $70.00 | |
| 69 | 542A0229 | P CUL CL A 1 24 | 80 | FOOT | $85.00 | $100.84 | $75.00 | $100.00 | |
| 70 | 542A5470 | P CUL CL A 1 EQRS 15 | 72 | FOOT | $104.00 | $137.66 | $95.00 | $115.00 | |
| 71 | 542A5473 | P CUL CL A 1 EQRS 18 | 174 | FOOT | $105.00 | $121.05 | $100.00 | $120.00 | |
| 72 | 54213657 | PRC FLAR END SEC 12 | 23 | EACH | $900.00 | $1,182.98 | $700.00 | $1,300.00 | |
| 73 | 54213669 | PRC FLAR END SEC 24 | 1 | EACH | $1,300.00 | $1,645.55 | $1,000.00 | $1,500.00 | |
| 74 | 54214710 | PRCF END S EL EQRS 15 | 2 | EACH | $1,100.00 | $1,552.80 | $900.00 | $1,500.00 | |
| 75 | 54214713 | PRCF END S EL EQRS 18 | 8 | EACH | $1,100.00 | $1,557.91 | $1,000.00 | $1,500.00 | |
| 76 | 59100100 | GEOCOMPOSITE WALL DR | 341 | SQ YD | $23.00 | $40.45 | $40.00 | $24.00 | |
| 77 | 59300100 | CONTR LOW-STRENG MATL | 108 | CU YD | $200.00 | $147.04 | $199.44 | $235.00 | |
| 78 | 60201366 | CB TA 4 DIA T37F&G | 2 | EACH | $3,400.00 | $4,184.86 | $3,750.00 | $3,500.00 | |
| 79 | 60205066 | CB TA 5 DIA T37F&G | 1 | EACH | $4,400.00 | $5,365.61 | $4,500.00 | $4,000.00 | |
| 80 | 60600605 | CONC CURB TB | 71 | FOOT | $45.00 | $48.54 | $48.00 | $45.00 | |
| 81 | 63200310 | GUARDRAIL REMOV | 278 | FOOT | $8.93 | $9.03 | $8.00 | $8.93 | |
| 82 | 64100115 | SIGHT SCRN (WF) TP 6 | 104 | FOOT | $220.80 | $223.26 | $221.00 | $220.80 | |
| 83 | 67000500 | ENGR FIELD OFFICE B | 12 | CAL MO | $2,500.00 | $3,500.00 | $7,000.00 | $2,400.00 | |
| 84 | 67100100 | MOBILIZATION | 1 | L SUM | $250,000.00 | $283,000.00 | $250,000.00 | $303,187.07 | |
| 85 | 72000100 | SIGN PANEL T1 | 162 | SQ FT | $30.00 | $41.46 | $30.00 | $41.00 | |
| 86 | 72800100 | TELES STL SIN SUPPORT | 135 | FOOT | $20.00 | $21.23 | $25.00 | $21.00 | |
| 87 | 73000100 | WOOD SIN SUPPORT | 370 | FOOT | $22.00 | $25.28 | $22.00 | $25.00 | |
| 88 | 78000100 | THPL PVT MK LTR & SYM | 865 | SQ FT | $10.00 | $6.27 | $30.00 | $6.20 | |
| 89 | 78000200 | THPL PVT MK LINE 4 | 37,561 | FOOT | $0.7000 | $0.8700 | $0.7000 | $0.8600 | |
| 90 | 78000400 | THPL PVT MK LINE 6 | 1,085 | FOOT | $1.05 | $1.30 | $1.05 | $1.29 | |
| 91 | 78000600 | THPL PVT MK LINE 12 | 1,221 | FOOT | $2.10 | $3.03 | $2.10 | $3.00 | |
| 92 | 78000650 | THPL PVT MK LINE 24 | 107 | FOOT | $4.20 | $6.27 | $4.20 | $6.20 | |
| 93 | 81028390 | UNDRGRD C PVC 4 | 115 | FOOT | $37.09 | $34.75 | $33.45 | $37.09 | |
| 94 | 87301815 | ELCBL C SERV 6 3C | 115 | FOOT | $14.10 | $10.29 | $9.90 | $14.10 |