D 6 HT PVMNT MRK RPR 24-05
Bidders 1
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Varsity Striping & Construction Co. Low bidder | $2,196,936 |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Varsity Stripin… |
|---|---|---|---|---|---|---|
| 1 | X7800825 | HS THPL PM LN 5 | 95,695 | FOOT | $0.3100 | |
| 2 | X7800835 | HS THPL PM LN 6 | 8,885 | FOOT | $0.3700 | |
| 3 | 78000100 | THPL PVT MK LTR & SYM | 2,813 | SQ FT | $4.25 | |
| 4 | 78000400 | THPL PVT MK LINE 6 | 3,585 | FOOT | $1.05 | |
| 5 | 78000500 | THPL PVT MK LINE 8 | 4,880 | FOOT | $1.40 | |
| 6 | 78000600 | THPL PVT MK LINE 12 | 3,220 | FOOT | $2.09 | |
| 7 | 78000650 | THPL PVT MK LINE 24 | 3,032 | FOOT | $4.50 | |
| 8 | 78009000 | MOD URETH PM LTR-SYM | 34,419 | SQ FT | $3.50 | |
| 9 | 78009005 | MOD URETH PM LINE 5 | 1,585,046 | FOOT | $0.9600 | |
| 10 | 78009006 | MOD URETH PM LINE 6 | 155,672 | FOOT | $1.15 | |
| 11 | 78009008 | MOD URETH PM LINE 8 | 66,485 | FOOT | $1.54 | |
| 12 | 78009012 | MOD URETH PM LINE 12 | 47,426 | FOOT | $2.31 | |
| 13 | 78009024 | MOD URETH PM LINE 24 | 16,628 | FOOT | $4.75 | |
| 14 | 78300201 | PAVMT MRKG REM GRIND | 10,000 | SQ FT | $0.9000 |