$1.81Avg low bid / SQ YD
$2.45Avg of all bids
—Avg engineer's estimate
7Jobs · 54,723.3 SQ YD
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2024 | 1 | 570 | $6.00 | $12.44 |
| 2023 | 1 | 138 | $39.23 | $28.90 |
| 2022 | 1 | 129 | $25.32 | $25.32 |
| 2021 | 1 | 39,124 | $1.23 | $1.71 |
| 2020 | 1 | 4,277 | $3.54 | $3.49 |
| 2019 | 1 | 9,992 | $2.25 | $2.83 |
| 2018 | 1 | 493.3 | $2.00 | $3.50 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jan 19, 2024 | 62T14 | CookDistrict 1 | 570 SQ YD | $6.00 | Martam Construction Incorporated |
| Nov 17, 2023 | 72H57 | HancockDistrict 6 | 138 SQ YD | $39.23 | Freesen, a div of UCM, Inc. |
| Nov 18, 2022 | 74A69 | EffinghamDistrict 7 | 129 SQ YD | $25.32 | Sangamo Construction Company |
| Jan 15, 2021 | 78802 | MassacDistrict 9 | 39,124 SQ YD | $1.23 | E. T. Simonds Construction Company |
| Mar 6, 2020 | 61G16 | DupageDistrict 1 | 4,277 SQ YD | $3.54 | Martam Construction Incorporated |
| Jul 12, 2019 | 76K44 | WashingtonDistrict 8 | 9,992 SQ YD | $2.25 | The Kilian Corporation |
| Jun 15, 2018 | 76J98 | MadisonDistrict 8 | 493.3 SQ YD | $2.00 | The Kilian Corporation |