$4,569.34Avg low bid / EACH
$5,050.69Avg of all bids
—Avg engineer's estimate
5Jobs · 11 EACH
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 3 | 6 | $3,493.78 | $4,731.56 |
| 2025 | 2 | 5 | $5,860.00 | $5,745.25 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jan 16, 2026 | 62K64 | CookDistrict 1 | 2 EACH | $2,449.10 | F. H. Paschen, S.N. Nielsen & Associates LLC |
| Jan 16, 2026 | 62K65 | CookDistrict 1 | 3 EACH | $3,775.60 | F. H. Paschen, S.N. Nielsen & Associates LLC |
| Jan 16, 2026 | 62U12 | CookDistrict 1 | 1 EACH | $4,737.70 | F. H. Paschen, S.N. Nielsen & Associates LLC |
| Nov 7, 2025 | 62U41 | CookDistrict 1 | 3 EACH | $5,900.00 | Lorig Construction Company |
| Mar 7, 2025 | 62P43 | CookDistrict 1 | 2 EACH | $5,800.00 | Lorig Construction Company |