$8,173.93Avg low bid / EACH
$6,451.64Avg of all bids
—Avg engineer's estimate
5Jobs · 43 EACH
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 1 | 27 | $10,300.00 | $6,952.09 |
| 2025 | 4 | 16 | $4,586.18 | $4,950.30 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jun 12, 2026 | 64L94 | HenryDistrict 2 | 27 EACH | $10,300.00 | Valley Construction Co. |
| Aug 1, 2025 | 99760 | WilliamsonDistrict 9 | 6 EACH | $4,000.00 | Samron Midwest Contracting, Inc. |
| Jun 13, 2025 | 64J66 | WinnebagoDistrict 2 | 1 EACH | $12,343.00 | Stenstrom Excavation & Blacktop, Inc. |
| Apr 25, 2025 | 64N98 | OgleDistrict 2 | 4 EACH | $5,258.96 | William Charles Construction Company, LLC |
| Mar 7, 2025 | 64R02 | LeeDistrict 2 | 5 EACH | $3,200.00 | Martin & Company Excavating |