$10.64Avg low bid / FOOT
$18.37Avg of all bids
—Avg engineer's estimate
10Jobs · 41,441 FOOT
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2023 | 1 | 2,035 | $25.00 | $24.20 |
| 2022 | 2 | 18,555 | $10.05 | $18.45 |
| 2021 | 1 | 1,420 | $16.00 | $19.93 |
| 2020 | 4 | 15,775 | $8.31 | $18.13 |
| 2019 | 1 | 441 | $25.00 | $39.06 |
| 2018 | 1 | 3,215 | $12.00 | $13.88 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jun 16, 2023 | 85741 | WinnebagoDistrict 2 | 2,035 FOOT | $25.00 | N-Trak Group LLC |
| Mar 11, 2022 | 61H45 | LakeDistrict 1 | 2,113 FOOT | $11.00 | A Lamp Concrete Contractors, Inc. |
| Jan 21, 2022 | 72M18 | Sangamon, MontgomeryDistrict 6 | 16,442 FOOT | $9.93 | Illinois Valley Paving, a div of UCM, Inc. |
| Jun 11, 2021 | 85706 | WinnebagoDistrict 2 | 1,420 FOOT | $16.00 | Fischer Excavating, Inc. |
| Nov 6, 2020 | 61G70 | LakeDistrict 1 | 11,796 FOOT | $8.00 | A Lamp Concrete Contractors, Inc. |
| Nov 6, 2020 | 90922 | VermilionDistrict 5 | 156 FOOT | $70.00 | ICC Group Inc. |
| Apr 24, 2020 | 70C64 | ChampaignDistrict 5 | 513 FOOT | $17.94 | Sangamo Construction Company |
| Mar 6, 2020 | 61G31 | LakeDistrict 1 | 3,310 FOOT | $5.00 | A Lamp Concrete Contractors, Inc. |
| Jun 14, 2019 | 61E01 | KaneDistrict 1 | 441 FOOT | $25.00 | Martam Construction Incorporated |
| Mar 9, 2018 | 60X10 | WillDistrict 1 | 3,215 FOOT | $12.00 | Judlau Contracting, Inc. |