$8,628.40Avg low bid / EACH
$8,365.98Avg of all bids
—Avg engineer's estimate
14Jobs · 59 EACH
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 1 | 2 | $7,481.25 | $6,834.76 |
| 2025 | 13 | 57 | $8,668.66 | $8,505.18 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jan 16, 2026 | 61J01 | DupageDistrict 1 | 2 EACH | $7,481.25 | R. W. Dunteman Company |
| Nov 7, 2025 | 62R51 | WillDistrict 1 | 1 EACH | $6,150.00 | Iroquois Paving Corporation |
| Sep 19, 2025 | 87846 | KendallDistrict 3 | 1 EACH | $13,750.00 | D. Construction, Inc. |
| Sep 19, 2025 | 62W62 | Cook, Dupage, WillDistrict 1 | 2 EACH | $12,400.00 | John Burns Construction Company |
| Sep 19, 2025 | 62R22 | WillDistrict 1 | 1 EACH | $5,447.20 | D. Construction, Inc. |
| Jun 13, 2025 | 62W90 | Cook, Lake, MchenryDistrict 1 | 23 EACH | $6,853.65 | H & H Electric Co. |
| Jun 13, 2025 | 62N39 | Dupage, CookDistrict 1 | 1 EACH | $6,970.08 | Meade Inc. |
| Jun 13, 2025 | 61J86 | LakeDistrict 1 | 1 EACH | $6,168.00 | Lake County Grading Company, LLC |
| Apr 25, 2025 | 62N33 | DupageDistrict 1 | 15 EACH | $13,000.00 | John Burns Construction Company |
| Apr 25, 2025 | 62V75 | LakeDistrict 1 | 1 EACH | $6,379.00 | Peter Baker & Son Co. |
| Apr 25, 2025 | 62X94 | MchenryDistrict 1 | 3 EACH | $6,670.42 | Berger Excavating Contractors, Inc. d/b/a Berger Contractors, Inc. |
| Mar 7, 2025 | 62N91 | CookDistrict 1 | 3 EACH | $7,980.00 | Dunnet Bay Construction Company & K-Five Construction Corporation |
| Mar 7, 2025 | 62W61 | VariousDistrict 1 | 1 EACH | $6,759.85 | H & H Electric Co. |
| Jan 17, 2025 | 61J91 | KaneDistrict 1 | 4 EACH | $5,276.00 | Geneva Construction Company |