$241.08Avg low bid / EACH
$243.80Avg of all bids
—Avg engineer's estimate
6Jobs · 3,697 EACH
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2022 | 1 | 1,075 | $294.00 | $311.11 |
| 2021 | 2 | 672 | $279.37 | $279.37 |
| 2020 | 1 | 650 | $195.00 | $200.58 |
| 2019 | 1 | 650 | $206.15 | $200.58 |
| 2018 | 1 | 650 | $195.00 | $200.58 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jun 17, 2022 | 66M44 | VariousDistrict 3 | 1,075 EACH | $294.00 | Northern Contracting, Inc. |
| Jun 11, 2021 | 66L80 | VariousDistrict 3 | 650 EACH | $278.21 | COLLINS & HERMANN, INC. |
| Mar 5, 2021 | 66F09 | KankakeeDistrict 3 | 22 EACH | $313.58 | Kankakee Valley Construction Co., Inc. & Gallagher Asphalt Corporation |
| Jul 31, 2020 | 66K93 | VariousDistrict 3 | 650 EACH | $195.00 | Northern Contracting, Inc. |
| Jun 14, 2019 | 66J51 | VariousDistrict 3 | 650 EACH | $206.15 | COLLINS & HERMANN, INC. |
| Jun 15, 2018 | 66H67 | VariousDistrict 3 | 650 EACH | $195.00 | Northern Contracting, Inc. |