$80.02Avg low bid / CU YD
$62.94Avg of all bids
—Avg engineer's estimate
4Jobs · 1,093 CU YD
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2023 | 1 | 300 | $199.76 | $199.76 |
| 2022 | 1 | 48 | $100.00 | $100.00 |
| 2019 | 2 | 745 | $30.51 | $43.78 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Apr 28, 2023 | 68F26 | PeoriaDistrict 4 | 300 CU YD | $199.76 | Otto Baum Company, Inc. |
| Aug 5, 2022 | 62N27 | WillDistrict 1 | 48 CU YD | $100.00 | D. Construction, Inc. |
| Sep 20, 2019 | 78739 | UnionDistrict 9 | 707 CU YD | $27.82 | Sierra Bravo Contractors, LLC |
| Mar 8, 2019 | 61F57 | KaneDistrict 1 | 38 CU YD | $80.55 | Curran Contracting Company |