$21,591.66Avg low bid / EACH
$22,176.16Avg of all bids
—Avg engineer's estimate
5Jobs · 6 EACH
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2022 | 1 | 1 | $9,911.76 | $17,455.88 |
| 2021 | 1 | 1 | $40,797.49 | $44,030.55 |
| 2020 | 1 | 1 | $38,000.00 | $35,950.00 |
| 2019 | 1 | 1 | $22,840.70 | $28,946.90 |
| 2018 | 1 | 2 | $9,000.00 | $6,837.69 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jan 21, 2022 | 93762 | SangamonDistrict 6 | 1 EACH | $9,911.76 | Freesen, a div of UCM, Inc. |
| Apr 23, 2021 | 93747 | SangamonDistrict 6 | 1 EACH | $40,797.49 | Freesen, a div of UCM, Inc. |
| Sep 18, 2020 | 76N15 | MadisonDistrict 8 | 1 EACH | $38,000.00 | Stutz Excavating, Inc. |
| Aug 2, 2019 | 93733 | SangamonDistrict 6 | 1 EACH | $22,840.70 | Freesen, a div of UCM, Inc. |
| Mar 9, 2018 | 60X10 | WillDistrict 1 | 2 EACH | $9,000.00 | Judlau Contracting, Inc. |