$46.77Avg low bid / CU YD
$63.04Avg of all bids
—Avg engineer's estimate
10Jobs · 1,801 CU YD
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2022 | 2 | 472 | $34.41 | $60.59 |
| 2021 | 2 | 193 | $46.79 | $58.31 |
| 2019 | 3 | 345 | $66.17 | $62.22 |
| 2018 | 3 | 791 | $45.67 | $70.17 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jan 21, 2022 | KE018 | HenryDistrict 2 | 152 CU YD | $90.00 | Advanced Asphalt Company |
| Jan 21, 2022 | MA032 | MarshallDistrict 4 | 320 CU YD | $8.00 | Gensini Excavating, Inc. |
| Mar 5, 2021 | RC010 | OgleDistrict 2 | 111 C.Y. | $55.50 | Sjostrom & Sons, Inc. |
| Jan 15, 2021 | MA031 | MarshallDistrict 4 | 82 C.Y. | $35.00 | Gensini Excavating, Inc. |
| Sep 20, 2019 | TR010 | CarrollDistrict 2 | 20 C.Y. | $220.00 | Tri-City Electric Company of Iowa |
| Jan 18, 2019 | RC008 | OgleDistrict 2 | 107 C.Y. | $50.00 | Martin & Company Excavating |
| Jan 18, 2019 | WA073 | LakeDistrict 1 | 218 C.Y. | $60.00 | Copenhaver Construction, Inc. |
| Aug 3, 2018 | KE015 | HenryDistrict 2 | 193 C.Y. | $50.00 | Brandt Construction Co. |
| Aug 3, 2018 | KE016 | HenryDistrict 2 | 425 C.Y. | $45.00 | Brandt Construction Co. |
| Jun 15, 2018 | RC007 | OgleDistrict 2 | 173 C.Y. | $42.50 | Stenstrom Excavation & Blacktop, Inc. |