$129,759.19Avg low bid / EACH
$307,935.16Avg of all bids
—Avg engineer's estimate
4Jobs · 4 EACH
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 1 | 1 | $5,610.81 | $4,055.41 |
| 2025 | 2 | 2 | $255,300.00 | $481,050.00 |
| 2024 | 1 | 1 | $2,825.96 | $5,912.98 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jul 31, 2026 | 78520 | JeffersonDistrict 9 | 1 EACH | $5,610.81 | E. T. Simonds Construction Company |
| Aug 1, 2025 | 64C24 | WinnebagoDistrict 2 | 1 EACH | $500,000.00 | OHLA Central, Inc. |
| Jun 13, 2025 | 64B40 | JodaviessDistrict 2 | 1 EACH | $10,600.00 | Civil Constructors, Inc. d/b/a Helm Civil and Fischer Excavating, Inc. J.V. |
| Dec 13, 2024 | 78633 | WilliamsonDistrict 9 | 1 EACH | $2,825.96 | E. T. Simonds Construction Company |