$16,916.16Avg low bid / EACH
$17,752.60Avg of all bids
—Avg engineer's estimate
5Jobs · 5 EACH
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 2 | 2 | $7,305.41 | $5,852.70 |
| 2025 | 2 | 2 | $31,375.00 | $26,879.00 |
| 2024 | 1 | 1 | $7,220.00 | $9,610.00 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jul 31, 2026 | 78520 | JeffersonDistrict 9 | 1 EACH | $5,610.81 | E. T. Simonds Construction Company |
| Jan 16, 2026 | 64L27 | StephensonDistrict 2 | 1 EACH | $9,000.00 | Martin & Company Excavating |
| Aug 1, 2025 | 64C24 | WinnebagoDistrict 2 | 1 EACH | $50,000.00 | OHLA Central, Inc. |
| Jun 13, 2025 | 64B40 | JodaviessDistrict 2 | 1 EACH | $12,750.00 | Civil Constructors, Inc. d/b/a Helm Civil and Fischer Excavating, Inc. J.V. |
| Dec 13, 2024 | 78633 | WilliamsonDistrict 9 | 1 EACH | $7,220.00 | E. T. Simonds Construction Company |