$317.04Avg low bid / SQ YD
$303.70Avg of all bids
—Avg engineer's estimate
4Jobs · 6,059 SQ YD
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 1 | 95 | $385.00 | $385.00 |
| 2025 | 3 | 5,964 | $315.96 | $303.09 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jan 16, 2026 | 74C61 | Clay, EffinghamDistrict 7 | 95 SQ YD | $385.00 | Howell Paving, Inc. |
| Jun 13, 2025 | 66R54 | FordDistrict 3 | 715 SQ YD | $285.00 | G. M. Sipes Construction, Inc. |
| Apr 25, 2025 | 68H82 | TazewellDistrict 4 | 34 SQ YD | $500.00 | G. M. Sipes Construction, Inc. |
| Apr 25, 2025 | 76J62 | St.clairDistrict 8 | 5,215 SQ YD | $319.00 | Christ Bros. Asphalt, Inc. |