DISTRICT WIDE STRIPING/RAISED PAVEMENT MARKINGS
- Let date
- Thursday, January 5, 2017
- CCSJ
- 0925-00-065
- District
- Childress
- County
- Childress
- Highway
- VA
- Limits
- DISTRICTWIDE STRIPING
- Classification
- Construction
- Project number
- NH 2017(460)
- Working days
- 60
Bidders 8
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $967,350 | ||
| 1 | TEXAS PANHANDLE CONSTRUCTION, INC. Low bidder | $799,498 | -17.4% | |
| 2 | L&L COMPANY | $840,100 | -13.2% | +5.1% |
| 3 | FLAT LINE, INC. | $868,738 | -10.2% | +8.7% |
| 4 | STRIPE-A-ZONE, INC. | $879,911 | -9.0% | +10.1% |
| 5 | BARRICADES UNLIMITED | $923,054 | -4.6% | +15.5% |
| 6 | PAVEMENT MARKINGS INC. | $971,228 | +0.4% | +21.5% |
| 7 | TOTAL HIGHWAY MAINTENANCE, LLC | $1,000,000 | +3.4% | +25.1% |
| 8 | TRP CONSTRUCTION GROUP, LLC | $1,046,454 | +8.2% | +30.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 TEXAS PANHANDLE… | #2 L&L COMPANY | #3 FLAT LINE, INC. | #4 STRIPE-A-ZONE, … | #5 BARRICADES UNLI… | #6 PAVEMENT MARKIN… | #7 TOTAL HIGHWAY M… | #8 TRP CONSTRUCTIO… |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 500-6001 | MOBILIZATION | 1 | LS | $99,390.51 | $1.00 | $1.00 | $1.00 | $500.00 | $1.00 | $3,500.00 | $954.47 | $75,000.00 |
| 2 | 502-6001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 | MO | $7,000.00 | $1.00 | $1.00 | $1.00 | $2.02 | $1,000.00 | $100.00 | $1.00 | $1,500.00 |
| 3 | 666-6036 | REFL PAV MRK TY I (W)8"(SLD)(100MIL) | 18,376 | LF | $0.5500 | $0.5000 | $0.5000 | $0.4000 | $0.6000 | $0.4400 | $0.6000 | $0.5700 | $0.6500 |
| 4 | 666-6300 | RE PM W/RET REQ TY I (W)4"(BRK)(100MIL) | 74,680 | LF | $0.2200 | $0.2000 | $0.2100 | $0.2200 | $0.2800 | $0.2300 | $0.3100 | $0.2700 | $0.2700 |
| 5 | 666-6303 | RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) | 1,852,869 | LF | $0.2100 | $0.2000 | $0.2100 | $0.2190 | $0.2150 | $0.2300 | $0.2400 | $0.2500 | $0.2400 |
| 6 | 666-6312 | RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) | 326,320 | LF | $0.2200 | $0.2050 | $0.2100 | $0.2200 | $0.2800 | $0.2300 | $0.2700 | $0.2700 | $0.2700 |
| 7 | 666-6315 | RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) | 1,524,579 | LF | $0.2100 | $0.2000 | $0.2100 | $0.2190 | $0.2150 | $0.2300 | $0.2400 | $0.2500 | $0.2400 |
| 8 | 672-6007 | REFL PAV MRKR TY I-C | 1,982 | EA | $2.10 | $2.50 | $2.50 | $2.20 | $2.00 | $2.80 | $2.40 | $2.40 | $2.50 |
| 9 | 672-6009 | REFL PAV MRKR TY II-A-A | 11,123 | EA | $2.20 | $2.10 | $2.50 | $2.20 | $2.00 | $2.80 | $2.20 | $2.40 | $2.25 |
| 10 | 672-6010 | REFL PAV MRKR TY II-C-R | 1,868 | EA | $2.00 | $2.50 | $2.50 | $2.50 | $2.00 | $2.80 | $2.80 | $2.40 | $2.50 |