LANDSCAPE DEVELOPEMENT
- Let date
- Tuesday, August 8, 2017
- CCSJ
- 0915-12-591
- District
- San Antonio
- County
- Bexar
- Highway
- VA
- Limits
- VARIOUS LOCATIONS IN BEXAR COUNTY
- Classification
- Construction
- Project number
- NH 1702(678)
- Working days
- 95
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $527,386 | ||
| 1 | ENCINO LANDSCAPE, INC. Low bidder | $510,193 | -3.3% | |
| 2 | YELLOWSTONE LANDSCAPE - CENTRAL, INC. | $706,794 | +34.0% | +38.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 ENCINO LANDSCAP… | #2 YELLOWSTONE LAN… |
|---|---|---|---|---|---|---|---|
| 1 | 100-6008 | PREPARING ROW (TREE) (0" TO 6" DIA) | 29 | EA | $350.00 | $400.00 | $57.92 |
| 2 | 170-6001 | IRRIGATION SYSTEM | 1 | LS | $120,000.00 | $50,000.00 | $163,842.15 |
| 3 | 192-6004 | PLANT MATERIAL (5-GAL) | 4,196 | EA | $27.00 | $25.00 | $15.33 |
| 4 | 192-6005 | PLANT MATERIAL (15-GAL) | 400 | EA | $120.00 | $110.00 | $68.55 |
| 5 | 192-6013 | MULCH | 13,181 | SY | $2.00 | $3.00 | $5.14 |
| 6 | 192-6049 | PLANT MATERIAL (MIN 4' TRNK HT) (PALM) | 12 | EA | $450.00 | $500.00 | $662.18 |
| 7 | 193-6001 | PLANT MAINTENANCE | 30 | MO | $2,000.00 | $2,000.00 | $3,294.91 |
| 8 | 193-6002 | PLANT MAINTENANCE | 11 | CYC | $2,500.00 | $5,000.00 | $13,225.49 |
| 9 | 193-6005 | PLANT REPLACEMENT (5-GAL) | 5 | EA | $30.00 | $30.00 | $27.42 |
| 10 | 193-6007 | IRRIGATION SYSTEM OPER AND MAINT | 30 | MO | $2,000.00 | $2,000.00 | $901.29 |
| 11 | 193-6009 | PLANT REPLACEMENT (15 GAL) | 5 | EA | $160.00 | $200.00 | $122.25 |
| 12 | 500-6001 | MOBILIZATION | 1 | LS | $37,732.32 | $60,000.00 | $69,354.84 |
| 13 | 502-6001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 | MO | $3,000.00 | $3,000.00 | $5,398.01 |