MILLED CENTERLINE RUMBLE STRIPS
- Let date
- Wednesday, March 8, 2017
- CCSJ
- 0200-12-015
- District
- Beaumont
- County
- Hardin
- Highway
- FM 418
- Limits
- DISTRICT WIDE
- Classification
- Construction
- Project number
- STP 2017(802)HES
- Working days
- 26
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $261,301 | ||
| 1 | STRIPE-A-ZONE, INC. Low bidder | $134,988 | -48.3% | |
| 2 | CRABTREE BARRICADE SYSTEMS, INC. | $152,398 | -41.7% | +12.9% |
| 3 | BATTERSON, LLP | $159,716 | -38.9% | +18.3% |
| 4 | TRP CONSTRUCTION GROUP, LLC | $177,615 | -32.0% | +31.6% |
| 5 | INTERSTATE BARRICADES & MARKINGS, INC. | $249,909 | -4.4% | +85.1% |
| 6 | TOTAL HIGHWAY MAINTENANCE, LLC | $266,068 | +1.8% | +97.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 STRIPE-A-ZONE, … | #2 CRABTREE BARRIC… | #3 BATTERSON, LLP | #4 TRP CONSTRUCTIO… | #5 INTERSTATE BARR… | #6 TOTAL HIGHWAY M… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 500-6001 | MOBILIZATION | 1 | LS | $26,372.13 | $83.94 | $17,500.00 | $13,000.00 | $15,000.00 | $18,500.00 | $20,000.00 |
| 2 | 502-6001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 | MO | $5,000.00 | $0.1000 | $10,000.00 | $1,400.00 | $2,500.00 | $3,000.00 | $5,000.00 |
| 3 | 533-6001 | RUMBLE STRIPS (SHOULDER) | 85,545 | LF | $0.5500 | $0.1300 | $0.1300 | $0.2000 | $0.1500 | $0.2500 | $0.4500 |
| 4 | 533-6002 | RUMBLE STRIPS (CENTERLINE) | 230,198 | LF | $0.3600 | $0.1850 | $0.1100 | $0.2100 | $0.2300 | $0.4500 | $0.4500 |
| 5 | 666-6311 | RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL) | 34,430 | LF | $0.3300 | $0.3000 | $0.3000 | $0.2500 | $0.3600 | $0.3500 | $0.3500 |
| 6 | 666-6314 | RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL) | 178,810 | LF | $0.3300 | $0.3130 | $0.2800 | $0.2500 | $0.3000 | $0.3500 | $0.3500 |
| 7 | 672-6009 | REFL PAV MRKR TY II-A-A | 6,450 | EA | $3.82 | $2.31 | $2.80 | $3.90 | $4.00 | $4.00 | $3.00 |