| 1 | 161-6022 |
GENERAL USE COMPOST (4") | 19,213 | SY |
$3.00 |
$5.25 |
$3.00 |
$6.41 |
|
| 2 | 170-6001 |
IRRIGATION SYSTEM | 1 | LS |
$180,000.00 |
$113,865.25 |
$130,000.00 |
$143,078.28 |
|
| 3 | 180-6001 |
WILDFLOWER SEEDING | 8.2 | AC |
$3,000.00 |
$1,500.00 |
$3,000.00 |
$2,287.64 |
|
| 4 | 192-6013 |
MULCH | 19,213 | SY |
$3.00 |
$3.35 |
$3.00 |
$6.39 |
|
| 5 | 192-6016 |
PLANT BED PREPARATION | 19,213 | SY |
$3.00 |
$2.00 |
$2.00 |
$0.5480 |
|
| 6 | 192-6021 |
PLANT MATERIAL (5 GAL) (TREE) | 4,300 | EA |
$26.00 |
$25.00 |
$30.00 |
$8.98 |
|
| 7 | 192-6023 |
PLANT MATERIAL (15 GAL) (TREE) | 219 | EA |
$125.00 |
$130.00 |
$130.00 |
$48.07 |
|
| 8 | 192-6028 |
PLANT MATERIAL (1 GAL) (SHRUB) | 405 | EA |
$10.00 |
$8.75 |
$8.00 |
$4.33 |
|
| 9 | 192-6031 |
PLANT MATERIAL (5 GAL) (SHRUB) | 3,680 | EA |
$30.00 |
$25.00 |
$30.00 |
$8.58 |
|
| 10 | 193-6001 |
PLANT MAINTENANCE | 24 | MO |
$2,000.00 |
$2,500.00 |
$2,000.00 |
$11,577.26 |
|
| 11 | 193-6007 |
IRRIGATION SYSTEM OPER AND MAINT | 24 | MO |
$1,000.00 |
$900.00 |
$2,000.00 |
$909.12 |
|
| 12 | 402-6001 |
TRENCH EXCAVATION PROTECTION | 50 | LF |
$10.00 |
$0.1000 |
$0.0100 |
$17.99 |
|
| 13 | 403-6001 |
TEMPORARY SPL SHORING | 50 | SF |
$10.00 |
$0.1000 |
$0.0100 |
$97.06 |
|
| 14 | 432-6002 |
RIPRAP (CONC)(5 IN) | 1 | CY |
$1,000.00 |
$0.1000 |
$0.0100 |
$1,190.29 |
|
| 15 | 500-6001 |
MOBILIZATION | 1 | LS |
$87,300.00 |
$73,000.00 |
$80,000.00 |
$92,982.46 |
|
| 16 | 502-6001 |
BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 | MO |
$2,500.00 |
$3,000.00 |
$3,000.00 |
$5,068.77 |
|
| 17 | 506-6035 |
SANDBAGS FOR EROSION CONTROL | 50 | EA |
$5.00 |
$0.1000 |
$0.0100 |
$2.59 |
|
| 18 | 506-6038 |
TEMP SEDMT CONT FENCE (INSTALL) | 200 | LF |
$2.50 |
$0.1000 |
$0.0100 |
$1.93 |
|
| 19 | 506-6039 |
TEMP SEDMT CONT FENCE (REMOVE) | 200 | LF |
$1.00 |
$0.1000 |
$0.0100 |
$0.2230 |
|
| 20 | 506-6041 |
BIODEG EROSN CONT LOGS (INSTL) (12") | 810 | LF |
$5.00 |
$0.0100 |
$10.00 |
$4.87 |
|